Академический Документы
Профессиональный Документы
Культура Документы
Semester 6
Yo Kai Sin
Nobert Voo
Munzir Akmal
Putri Razak
Qi Bing Duo
Semester 5
Haziq Zariful
Chua Jia Cheng
Vivian Tan
Khor Seem Leng
Cecilia Tie
Lau Sii
Stephanie Yeoh
Question 1
What are the essential
requirements for formation of
contract? Discuss whether a
Offer
Section
The
Acceptance
Section
Consideration
An
Common
Consideration
Certainty
The
Capacity
For
Any
An
Question 2
Advise Jazzy on the validity of
Can-Dos claim for extension of
time and additional payment
arising from the collapsed
temporary works.
Extension of Time
Under PAM Contract 2006:
Contractual effect:
Can-Do (contractor) has no grounds to claim for any
extension of times because the relevant sub-clauses
have been deleted by Jolly (contractor)
Jolly (employer) instructed Gulp (QS) to delete the
sub-clauses on variations, delays, impediment and
prevention caused the employer which were
relevant events for the extension of the time for
completion.
Extension of Time
According to PAM Contract 2006,
Extension of Time
Under FIDIC :
Contractual effect:
Can-Do (contractor) has no grounds to claim for any
extension of times because the relevant sub-clauses
have been deleted by Jolly (the employer).
The deleted clauses to extend time may result in time
at large. Contractors obligations then is to complete
in a reasonable time.
Extension of Time
According to FIDIC,
Additional Payment
Under PAM Contract 2006:
Contractual effect:
Can-Do (contractor) is not entitle to claim
additional payment from the collapsed
temporary work because he only submitted
the claim for loss and expenses 40 days after
the event citing.
Additional Payment
Under FIDIC :
Contractual effect:
In this case, the contractor fails to give notice
of a claim within such period of 28 days,
therefore the contractor shall not be entitled
to any additional payment.
According to FIDIC
FIDIC
As
Therefore,
???
1.
2.
3.
4.
5.
6.
PAM
Clause
This
The
Question 4 : Situation
Changes to
apartment
type mix
Requested
Jolly (Client)
Can-Do
Argued
(Contractor)
Question 4
If the standard form of contract is the
Agreement and conditions of PAM Contract
2006 (Without Quantities),
HOWEVER
Jolly (Client ) had instructed Gulp (Qs) to delete the
sub-clauses on variation and delay from the relevant
events to ensure contractor has no ground to claim EOT.
Hence, Picasso has no right to approve EOT to Can-Do.
The only remedies might be to find another contractor
to execute the variation works.
Question 5
Advice Jolly on the
contractual implications of
replacing Er Jazzy and
appointing their own
employee, Er Jo-Jo, as the
name Engineer.
FIDIC Form
Clause
1.1.2.4
Engineer:
is the person appointed by employer to exercise the power on behalf of
employer.
a decision maker holding balance between employer and contractor on
matters of opposing interests.
SubClause
3.5
Engineer:
In determinant of any matter, the Engineer shall consult with each party in
endeavour to reach agreement.
If agreement is not achieved, then he shall make fair determination in
accordance with the Contract, taking into consideration of all relevant
circumstances.
SubClause
3.4
Engineer
if employer intends to replace the engineer , the employer shall, not less
than 21 days before the intended date of replacement, give notice to the
contractor [ name, address and relevant experience of intended
replacement Er]
Contractor have rights to raise reasonable objection by giving notice to
the employer with supporting particulars.
Employer to give full and fair considerations.
PAM Form
Clause
23.8 (r)
Any appointment of
replacement person under
Articles 3,4,5 & 6, the
contractor is entitled to
extension of time.
Clause
24.3 (r)
Any appointment of
replacement person under
Articles 3,4,5 & 6, the
contractor is entitled to loss
and expense .
Conclusion
Jolly cannot Why?
replace Er
Jazzy and
appoint their May not allow the
engineer to make
own
fair determination
employee Er and act firmly in
making decisions.
Jo Jo.
Results may be
biased, more
advantages
towards employer.
Notice of intention to
replace the engineer
must be given to the
contractor not less
than 21 days before
the intended date of
replacement with
name, address and
relevant experience of
the engineer.
FIDIC FORM
Summary of Ques 5
A) Clause 23.8 (r)Extension of time
( Relevant Event)
B) Clause 24.3 (i)Loss and Expense
( Matters materially
affecting the regular
progress of the
works)
PAM CONTRACT
Question 6:
Discuss the procedure and
consequences for suspension of
the works. Answer the question
on the assumption that you are
the named Engineer and has
issued an instruction to Can-Do to
suspend progress of the works.
FIDIC Contract
Sub-clause 8.8 EI to suspend progress of work or certain parts
of the work
Contractor protect, store and secure Works against loss or
damage.
If suspension > 84 days, contractor request for engineers
permission to proceed
Engineer gives permission within 28 days for works to
recommence
If failed to do so, suspended portion will be omitted from the
works
If whole of the works suspended, Contractor terminate
contract immediately; claim for additional cost
FIDIC Contract
Sub-clause 8.9 If the Contractor suffers delay or
incurs cost from complying with the instruction,
Contractor shall be entitled subject to Sub-Clause
20.1 [Contractors Claim] for EOT or payment for any
such cost by giving notice to Engineer.
After receiving such notice, Engineer shall proceed to
assess these matters in accordance with Sub-Clause
3.5 [Determination].
If it is the Contractors fault for suspension of the
works, he shall not be entitled to EOT or payment of
Cost incurred.
Clause
24.3(c)
QUESTION 7
Advice Gulp on how they should
respond to Jollys instructions
during the tender documentation
period on the sub-clauses to be
deleted in the contract form.
FIDIC Contract
Gulp should advise Jolly as follows:
If the sub-clauses that are relevant for extension of time were
to be deleted, time cannot be extended if there is any delay
caused by employer or neutral events, and time will be at large.
When time is at large, the original date of taking-over no longer
applies.
If the Employer defaults and caused delay, there is no
mechanism in the contract to extend time and fix new Time for
Completion.
No definite Time for Completion to work towards
Contractor is only required to complete within reasonable time
as assessed by engineer
Employers right to claim delay damages no longer applies
Contractor finishes later than reasonable time, employer
entitled to common law damages provided such losses are actual
and proven.
If there are EOT provisions: Sub-Clause 8.4 Contractor shall be entitled subject to SubClause 20.1 for an extension of Time of Completion for delay
caused by relevant events of sub-clauses 8.4(a) to 8.4(e).
New Time for Completion can be fixed
Protect Employers right to recover delay damages for neutral
events or employer-responsible events
Prevents time for completion for being at large
In the case of PAM Form of Contract 2006, Clause 23.0 is
applicable for extension of time claim.
Therefore, Gulp should advise Jolly not to delete the sub-clauses
related to EOT from the contract form due to the implications
mentioned above.
Question 8
In the event Can-Do becomes insolvent, how
would you advise Jolly on the implications
and arrangements for completing the works
and recovering delay damages, the losses
and expenses incurred and the extra costs in
having the works completed by another
contractor?
ADVICE to JOLLY
Jolly is advised to notify Can-Do in writing, that the his employment has
been determined in accordance with Clause 25.3.
Can-Do shall vacate the Site and return possession of the Site to Jolly
within 14 Days from receipt of Notice of Determination under Clause 25.7.
Jolly has the right to employ and pay other persons to carry out and
complete the Works.
Jolly can also instruct Can-Do to remove any or all facilities from
site within a reasonable time under Clause 25.4( c ).
Can-Do must pay for all cost incurred to complete the Works
including all loss and/or expense suffered by Jolly. Jolly is not
bound to make further payment to Can-Do, including payments
which have been certified but not yet paid under Clause 25.4(d).
Under FIDIC
Sub-Clause 15.2 states that The Employer shall be entitled to terminate the
Contract if the Contractor becomes bankrupt or insolvent, goes into liquidation,
has a receiving or administration order made against him The Employer may by
notice terminate immediately.
ADVICE to JOLLY
Can-Do shall then leave the Site and deliver any required Goods, all
Contractors Document, and other design documents made by or
for him, to the Engineer, Jazz.
Under FIDIC
ADVICE to JOLLY
Jolly can recover from Can-Do any losses and damages incurred by
Jolly and any extra costs of completing the Works, after allowing
for any sum due to Can-Do under Sub-Clause 15.3 [Valuation at
Date of Termination].
After recovering any such losses, damages and extra cost, Jolly
shall pay any balance to Can-Do.
Question 9
Can-Do are entitled to claim for Extension of Time if the reason was fall under
the Relevant Event stated in Clauses 23.8.
Clause 23.8 (m)- any act of prevention or breach of contract by the employer.
Jolly prevent the Can-Do to proceeding to existing work due to the variation
work to the bedroom.
The act of prevention by Jolly caused the Can-Do delays the Completion of Time.
Can-Do must give a written notice of delay to Jazz his intention to claim for
Extension of Time and the notice shall be given within the 28 Days from the
date of Relevant Events commence.
The written notice is condition precedent for the Can-Do to entitled to claim
for Extension of Time.
The Contractor are not entitled to claim for Extension of Time due to the
employer deleted the sub-clauses was included with delay caused by
employer which relevant event do not entitle the contractor to claim for
Extension of Time.
FIDIC Contract
Clauses 20.1 - Contractor Claim
If the Contractor fails to give notice of a claim within such period of 28 days, the
Time for Completion shall not be extended, the Contractor shall not be entitled
to additional payment, and the Employer shall be discharged from all liability in
connection with the claim. Otherwise, the following provisions of this Sub-Clause
shall apply.
variation (unless an adjustment to the Time for Completion has been agreed
under Sub-Clause 13.3 [Variation Procedure] or other substantial change in the
quantity of an item of work included in the Contract.
(b) a cause of delay giving an entitlement to extension of time under a SubClauses of these Condition.
(a)
Can-Do
Question 10:
a)
b)
Under FIDIC
ADVICEs to
Picasso
Under FIDIC
ADVICEs to
Picasso
The consequential effect under clause 10.2 (a); (b); and (c), the part which is used shall be
deemed to have been taken over as from the date on which it is used.
The Contractor shall cease to be liable for the care of such part as from this date, when
responsibility shall pass to the Employer, and if requested by the Contractor, the Engineer
shall issue a Taking-Over Certificate for this part.
The Contractor will be entitled subject to Sub-Clause 20.1 [Contractor Claims], if the
Contractor incurs the cost.
The Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or
determine this Cost and profit.
The delay damages there after for completion of the remainder of the works shall be
reduced.
Clause 16.2, the Employer only has the right to possess without the
consent of the Contractor under following clause 16.2 (a) and (b).
Due to the condition of Mr Joll made surprise visit to the site and
furious at the slow patchy progress and shoddy workmanship, Mr Joll
had decided to ask Engineer to omit some portions of the work.
Under Clause 16.1, the consent of the Contractor has to obtain as the
Employer wishes to take possession and occupy any part of Works.
Question 11:
Discuss Jazzs action to issue an instruction to omit
portions of the works from Can-Dos contracted
scope so that another contractor can be engaged
to carry out the omitted portions.
Under FIDIC
JAZZs
ACTIONs
Question 12 - FIDIC
Question 12 - FIDIC
Advise Jolly (employer) on their rights in respect of the failure of the membrane
roofing works
Scenario
They were found to be caused by poor workmanship and failure of the membrane roofing.
Contractor refused to attend the defective roofing works;
a.
b.
_______________________________________________________________________________
According to FIDIC Condition of Contract,
If the Contractor fails to remedy any defect or damage within a reasonable time, a date may
be fixed by (or on behalf of) the Employer, on or by which the defect or damage is to be
remedied. The Contractor shall be given reasonable notice of this date. If the Contractor fails
to remedy the defect or damage by this notified date and this remedial work was to be
executed at the cost of the Contractor under Sub-Clause 11.2 [Cost of Remedying Defects], the
Employer may (at his option):
Question 12 FIDIC
Advise Jolly (employer) on their rights in respect of the failure of the membrane roofing works (cont.)
The contractor should remedy to the defective works by the Defects Liability Period (Clause 11.4).
Unfortunately, Mr Jolly cannot claim any damages due to DNP has long expired and Can-Dos
obligations were over as evidenced by the Performance Certificate.
Mr Jolly made a surprised visit to the site accompanied by Bang Bang and he found out that,
the workmanship by Can-Do was shoddy. But he did not ask the engineer to issue DNP to the
contractor. If he did, Mr Jolly would have been able to ask Can-Do to remedy the issue.
He also could have issued a notice to Extension of Defects notification period which must have
been issue before the expire (clause 2.5)
Clause 2.5 Employers Claim
The notice shall be given as soon as practicable and no longer than 28 days after the
Employer became aware, or should have become aware, of the event or circumstances giving
rise to the claim. A notice relating to any extension of the Defects Notification Period shall be
given before the expiry of such period.
Question 13
Can-Do :
Clause 20
Contractor must submit their notice to claim for extension of time within 28 days after the
event causing the delay.
Failure to give notice, under clause 20.1, contractor is not entitled to additional payment.
Within 42 days contractor shall send to the engineer a fully detailed claim.
Jazz :
Clause 20
Within 42 days after receiving a claim engineer shall response with approval or disapproval.
According to clause 20.1 the notice shall be given as soon as practicable and not later than
28 days after the contractor became aware, or should have become aware, of the event or
circumstances.
If the contractor fails to give notice of a claim within 28 days the time for completion shall
not be extended, the contractor shall not be entitled to additional payment.
Can-Do
1)
Contractor to give written notice of intention to claim within 28 days from commencement of
relevant event. This written application is a condition precedent to any EOT.
2)
Contractor to submit subsequent official application and substantiation of claim within 28 days of
end of cause of delay.
Jazz
Q14
Clause 11.6a
Where the varied work is of similar character executed under similar condition, the work price
or rate in the contract shall be used for the valuation.
Clause 11.6b
Where the varied work is of similar character to work included in the contract but not
executed under similar condition, the work price or rate in the contract shall be used for the
valuation with fair adjustment
Clause 11.6c
Where the varied work is not of similar character, or not executed under similar condition, the
valuation shall be at a fair market rates and prices. The BoQ rates shall be the basis of rates for
the valuation.
Clause 11.6d
Where the varied work cannot be properly measured and valued or when the above rules are
inapplicable or inappropriate in the circumstances, the valuation shall be based upon daywork
rates or prices.
Clause 11.6e
Where the varied work involves items to be omitted, the rates or prices in the contract shall
determine the valuation of items omitted. If omissions substantially vary the conditions under
which any remaining items of work are carried out, the rates or prices of such remaining items
shall be valued under clause 11.6a,b,c
Key words
QUESTION 15
Question 16A
Notifies
engineer
Give notice to
engineer
Sub-clause
20.1 claim
procedure
applied
No
No EOT
EOT
No
Additional
No Additional cost
cost
Employer
not
Employer not
liable
liable
Is the
conditions
unforeseeable
?
Claim
Claim rejected
rejected
Question 16B
Notifies architect
Give notice to
architect
Architect shall
ascertained such
amount and issue in
interim certificate
No
No EOT
EOT
No
Additional
No Additional cost
cost
Employer
not
Employer not
liable
liable
Claim
Claim rejected
rejected
a) late issue of AI
h) discovery of antiquities
Differences
PAM
Engineer
Architect
Claim condition
This formal
application shall be
submitted within 42
days after the
contractor became
aware of the rising
of the events.
Submission of
Detailed claim
This formal
application shall be
submitted after the
28 days of
completion of the
relevant matters.