Академический Документы
Профессиональный Документы
Культура Документы
WATER
RETICULATIO
N
INTRODUCTION
Water
reticulation system is to
supply treated water at sufficient
pressure and sufficient quantity to
the consumers.
The
WATER DEMAND
ITEM
NET
AREA/PERSON
WATER
CONSUMTION
TOTAL (m3/day)
Stadium
300 Person
16.50
Office
177 m2
1.77
18.27
CALCULATION
Case 1: Water Pipelines Design for Peak Flow
Domestic average flow x 2.5 (SPAN)
= 12.69 lpm x 2.5 (Peak factor for urban & rural area)
= 31.72 lpm @ 0.529 lps
Case 2: Water Pipelines Design for Fire Flow
Domestic average flow + Fire flow
= 12.69 lpm + 2700 lpm (Class B) (SPAN)
= 2,712.69 lpm @ 45.21 lps
DRAWING LAYOUT
RETICULATION PIPELINE
DESCRIPTION
SIZE OF WATER
TANK
Total water demand for this development
= 18.27 m3/day
@ 4,018.92 gpd
So, 2m x 2m x 4m
LAYOUT COLD
WATER
CIVIL WORK
SEWERAGE
INTRODUCTION
Sewerage : The sewerage system comprises the
proposed
following : -
sewer
needed
lines
is
to
to
collect,
cater
the
a) Stadium
b) Office
)The proposed inverts of the sewer line are
designed cater the Sewerage disposal from the
building which are then piped to the existing
manhole by means of gravity flow.
)The services manholes provided are spaced at
regular interval not exceeding 90m.
)All pipe connections are flexible rubber ring
joints and pipes are laid on granular bedding
DESIGN CRITERIA
a) The design parameters for the sewerage system are
based on the Malaysian Standard, MS1228. Code of
practise for design and installation of sewerage system
and guidelines for developer Design and installation
of sewerage system by the Director General of Sewerage
Services Department.
b) Wherever technically and economically feasible, gravity
sewers will be designed to maintain minimum cleansing
velocities of 0.8 m/sec.
c) This is to avoid the settlement of solids and to minimize
the potential for corrosion resulting from the hydrogen
sulphide.
d) For erosion prevention, it is recommended that as a
POPULATION
EQUIVALENT
CALCULATION
Calculation of Population Equivalent (P.E)
1. Stadium = 0.2 per person (Table A.1 `Sewerage Treatment
Plant Volume 4)
2. Office = 3 per 100 m2
(Table A.1 `Sewerage Treatment
No Volume
Type
Density
PE/Unit
PE
Plant
4)
1
2
125
person
0.2 person
25
13.5 x
13.1
= 177 m2
3 /100 m2
5.31
Stadium
Office
Total
30
SIZE (mm)
GRADIENT
CAPACITY (m3/s)
VELOCITY (m/s)
225
1: 150
0.040
1.02
0.225 0.63 1
V 0.849110 (
)
4
150
Capacity = A.V
0.54
1.02m / s 2
A= pipe cross sectional
= ( x 0.2252)/4 x 1.02
= 0.040 m3/s
iii. The velocity of flow should not fall below 0.8m/sec and
not greater than 4.0m/sec.
)Manhole
Max. Spacing
Minimum Depth
Manhole covers :
Design Standards
The sewer reticulations are design based on the following manual:
a) Malaysian Standard MS1228: 1991 Code of Practice for Design
and Installation of Sewerage Systems.
b) Guidelines for Developers Volume 1 Sewerage Policy for New
Developments.
c) Guidelines for Developers Volume 3 Sewer Networks & Pump
Stations.
d) Guidelines for Developers Volume 4 Sewage Treatment Plants.
e) Guidelines for Developers Volume 5 Septic Tanks.
Example Calculation
SEWERAGE DESIGN
DRAWING LAYOUT
SEWERAGE
SEPTIC TANK
DESIGN
CALCULATION
Inside Dimension
(mm)
PE
30
Capacit
y
(Litres)
6750
Width
(W1)
Lengt
h
(L1)
Liqui
d
Dept
h
(D1)
1375
3365
1525
Air
Spac
e
(S)
305
Filter Bed
Inlet/Outle
t Pipe
Inside Dimension
(mm)
Depth Below
WL (mm)
Width
(W2)
Lengt
h
(L2)
Liqui
d
Dept
h
(D2)
2300
2400
1500
Inlet
3065
10
Outle
t
610
BQ FOR WATER
RETICULATION AND
SEWERAGE