Wellhead Platform

Project Handover and


Commissioning
BMB & CKD

PSS Project Involvement Process

Pre FEED & FEED


- Interface with Operation, F&E to consolidates and feedbacks of Operation & Maintenance Histories e.g. Process/Equipment reliability, Operate &
Maintenance lessons learned and/or improvement expectation to Project Team for implementation.
Detail Design
- Ensure the agreed of improvement items are fully implemented in the project
Note: not much sharing the past lessons
- Review & Update operating and maintenance philosophy as necessary
learned for BMB&CKD project due to late
Fabricate & Construction
involvement
- Review and preparation to register the new asset facilities in SAP
- Review SPIR and provide the final recommendation to maintenance for final inventory setting.
- Review and develop maintenance planning activities (PM job cards) and register in SAP
- Review and develop Operating and Maintenance procedure as necessary
- Identify training needed for offshore team as necessary
- Perform FAT/SAT and pre- commissioning at fabrication yards to minimize offshore rectification activities
- Ensure the readiness of documentations for all activities (BF and GF) that need to execute at offshore
- Confirm necessary actions and documents are completed for MCD handover inclusive preservation of equipment during drilling stage
MCD
- Perform final inspection, process/equipment functional test and commissioning to confirm properly install, design functions and performances.
- Confirms all necessary preservation equipment are proper preservation with monitoring log sheet and readiness to handover WHP to Drilling
Drilling & Flow Line Installation
- Activates SAP for maintenance planning activities (PM job cards) to ensure all equipment are having properly maintenance actions to maintain in a good
conditions
- Interface with HUC and Operation team to perform Pre-Startup Safety Review (PSSR) process (check & confirm all necessary documents are fully update, no
any major punch items and readiness of platform startup)
Platform Startup
- Assist Operation team to Startup

BMB & CKD Work Planning


Review and classify criticality of punch items (after topside sails out) with Operation to ensure all critical items are
completed rectification prior MCD
Review and update maintenance planning tasks as necessary
Review and finalize operation spare with Maintenance to set and/or adjust inventory as necessary
Interface with Design /Package Engineer to review the functionalities and performances of packages are met the design.
Identify procedures and/or actions needed for process/equipment preservation during drilling activities period
Interface with HUC and Operation to identify documents needed, criticality of punch items, criteria of inspection & check
sheet for MCD handover (example as attachment ).

MCD Handover will be accepted when all systems are commissioned and accepted by offshore disciplines with
TAs approval prior final acknowledgement project handover by POD Manager
Expected to start commissioning BMB on Sep 8, 2012 (7 days prior mobilized date of Drilling)
HUC

MCD Handover Submission

Drilling

Startup for First Gas

Sep 8

Commissioning & Handover to


Drilling with minor punch's

Flow Line
Installation

Sep 15

Feb
2013

Special System Testing Required Prior Handover


Process & Utilities
Instrument Gas system

Open Drain system


Closed Drain system
Washdown Water
Diesel system

Pedestal Crane

- Operating test at design flow rate by using


compress air as medium until dew point is achieved
- 2 hrs full load test run on open drain caisson pump
- Auto start/stop function test using water and air as medium
- Capacity test and running for 30 minute
- Pump testing plus all pipe work must be left with full
of diesel
- Function Test plus Load Test

Instrument & Control

Fire & Gas/ESD/Emergency


Process Shutdown (PSD)
SCADA system
Communication

- Local and Remote Function Test


- Local Function Test
- Fully commissioning and Function Test
- Telephone, Radio and Broadband Function Test

Electrical
Auxiliary Generator
UPS Power
Navigational Aid
Emergency Lighting

Running test at maximum platform load plus


protection function test
Charge / discharge load test with Aux Generator and
charge / discharge test with Solar array plus system
monitoring and protection function test
-Test all light, fog horn and control functionality plus
-Battery charge/discharge testing
-Function Test

System/Equipment Preservation during Drilling Activities.

Pipeline ( BMA to BMB) & (CKA to CKD)


Production Header Pig Launcher
Wellhead Control Panel
Pedestal Crane
Auxiliary Generator
Solar Power System
Instrument Gas Package
Closed Drain Pump
Wash Water Pump
SCADA and Communication

Finding Gaps;
Ineffectiveness of communication between Project/Design Engineers, F&E (TA) and End Users
to review all problems in the past, lesson learn and/or additional improve requirements to be
accepted and implemented in the project.
Package equipment documents / drawings are not available and/or provide enough info to review
prior FAT/SAT subsequently no specific items / functions that need to be concentrated.
Function and authorization of PMT QA/QC (Project or TA representative?)
Improper workflow and response timeframe of Design/TA Engineers on the design issue.