Академический Документы
Профессиональный Документы
Культура Документы
Energy
Basic concept
Typical
configuration &
components
Benefits
Characteristics of
a good
opportunity
Market drivers
Case studies
Energy Exchange: Federal Sustainability for
Typical DG Technologies:
Engine Generators
Turbine Generators
Solar Photovoltaic
Wind Turbine
Fuel Cells
Energy Exchange: Federal Sustainability for
CHP Typical
Configuration
Use fuel to first Generate Power, then
Capture resulting heat for use as:
Heating
Cooling
Both
Thermall
y
Activate
d
Machine
Prime
Mover
Energy Exchange: Federal Sustainability for
Microturbine
Electrical Equipment
Absorption Chiller
Steam
Turbine
MicroTurbin
e
Fast Start up
Hi part load
efficiency
Island mode
capable
Operates on low
pressure gas
High Reliability
Low Emissions
High-grade Heat
No cooling
required
High overall
efficiency
Any fuel type
Long working
life
High reliability
Small # of
moving parts
Compact size &
wt.
Low emissions
No cooling
required
Disadvantage
s
High maintenance
costs
Low temperature
thermal output
Higher emissions
Needs cooling
Requires gas
compression
Poor efficiency at
low loads
Output varies w/
ambient temp
Slow start up
Low power to
heat ratio
High costs
Low temp.
thermal output
Lower mech.
Efficiency
Typical Sizes
< 5MW
500kW 300MW
500kW
300MW+
30kW 1MW
Installed
Costs $/kW
1,500 2,900
1,200 3,300
670 1,100
2,500 4,300
O&M Costs
/kWh
0.9 - 2.5
0.9 - 1.3
0.6 1.0
0.9 1.3
Advantages
Combustion
Turbine
Typically synchronous
Grid interconnection
Generator on IC Engine
Switchgear
Typical uses:
HRSG
Economizer
Absorption Chiller
150oF 250oF
Shaft Power to
Drive Load
(30%)
Energy Distributions
Generation is on-site
for a Typical
Reciprocating Engine
Particularly applicable to Military Bases
Economic/Financial
Wide spark spread
Low or no standby charges/penalties
Access to Funding/Financing
ESPCs/UESCs
Utility Rebates and Incentives
Regulatory/Utility
Favorable permitting environment
Simple, clear, fair interconnection requirements
Energy Exchange: Federal Sustainability for
ry Hub Gas Prices expected to Remain between $3.00 and $6.00 thru 20
$/MMBTU
Cents/kwh
13
Forecast
Spark Spread
Historical
Forecast
Contract value
Construction: $82 million
O&M: $90 million
Schedule
Contract signed February 2012
Construction begins Summer 2012
Construction completion August 2015
15-year O&M Phase begins
16
Bob Albertini
Pepco Energy Services
balbertini@pepcoenergy.com
708-710-5645
17