Академический Документы
Профессиональный Документы
Культура Документы
DEMILLO,ROGELIO JR.G.
ANNEX A
DETAILED ENGINEERING FOR THE PROCUREMENT OF
INFRASTRUCTURE PROJECTS
Detailed engineering shall proceed only on the basis of the feasibility or preliminary
engineering study made which establishes the technical viability of the project and
conformance to land use and zoning guidelines prescribed by existing laws.
b) Site Investigation
c) Soils and Foundation Investigation
d) Construction Materials Investigation
e) Preparation of Design Plans
f) Preparation of Technical Specifications
g) Preparation of Quantity and Cost Estimates
h) Preparation of Program of Work
i) Preparation of Proposed Construction Schedule (and estimated Cash Flow for
projects with Schedule over Six (6) Months)
j) Preparation of Site or Right-of-Way Plans including
Schedule of Acquisition
k) Preparation of Utility Relocation Plan
l) Preparation and Submission of Design Report
m) Environmental Impact Statement for critical project as defined by the
Department of Environment and Natural Resources (DENR)
n) Preparation of minimum requirements for a Construction Safety and Health
Program for the project being considered
For projects to be implemented by phases, the Procuring Entity shall ensure that there
is a clear delineation of work for each phase, which must be usable, and structurally sound.
It shall also ensure the conduct of the detailed engineering activities for each phase as
provided for in Item 2 of this Guidelines.
ANNEX B
GENERAL PRINCIPLES ON CONSULTING SERVICES
Hiring of Consultants
4.1. Consultants shall be hired on the basis of their proven expertise, experience
and capability. Under certain conditions provided herein, cost may be included as a
factor in the selection of consultants.
Construction Supervision. These include the following:
a) Inspection and expediting of the work;
b) Verification and checking of quantities and qualities of work accomplished by the contractor as
against the approved plans, specifications, and programs of work;
c) Issuance of instruction for corrections of defects on the work;
d) Verification and recommendation for approval of statements of work accomplished and
certificate of project completed by the contractor;
e) Review and recommendation for approval of progress and final billings of the contractor; and
f) Provision of record or as-built drawings of the completed projects.
The above do not mean direction, superintendence, or management of
construction.
ANNEX C
RECOMMENDED EARLIEST POSSIBLE TIME AND MAXIMUM PERIOD
ALLOWED FOR THE PROCUREMENT OF GOODS AND SERVICES
2.1. For Variation Orders, the contractor shall be paid for additional work items whose
unit prices shall be derived based on the following:
a. For additional/extra works duly covered by Change Orders involving work items
which are exactly the same or similar to those in the original contract, the applicable
unit prices of work items original contract shall be used.
ANNEX F
CONTRACT IMPLEMENTATION GUIDELINES FOR THE PROCUREMENT
OF CONSULTING SERVICES
APPENDIX B
LEASE OF REAL PROPERTY AND VENUE:
RATING FACTORS AND
DETERMINATION OF REASONABLENESS OF RENTAL RATES
ANNEX I
GUIDELINES ON TERMINATION OF CONTRACTS
1. Coercive Practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation
in a procurement process, or affect the execution of a contract.
2. Collusive Practice means a scheme or arrangement including practice among bidders (prior to or after bid submission) designed to
establish bid prices at artificial non-competitive levels to prevent free and open competition.
3. Corrupt Practice means the offering, giving, receiving or soliciting of anything of value to influence the action of a public official in the
selection process or in contract execution. It also means entering, on behalf of the Government, into any contract or transaction manifestly
and grossly disadvantageous to the same, whether or not the public officer profits or will profit thereby; and similar acts as provided in
Republic Act 3019.
4. Fraudulent Practice means a misrepresentation of facts in order to influence a selection process or the execution of a contract to the
detriment of the Procuring Entity.
5. Head of the Procuring Entity refers to: (i) the head of the agency or his duly authorized official, for national government agencies; (ii) the
governing board or its duly authorized official, for government-owned and/or controlled corporations; or (iii) the local chief executive, for local
government units. Provided, that in a department, office or agency where the procurement is decentralized, the Head of each decentralized
unit shall be considered as the Head of the Procuring Entity subject to the limitations and authority delegated by the head of the department,
office or agency.
6. Implementing Unit refers to the unit or office having direct supervision or administration over the implementation of the contract such as
the Project Management Office or the End-User Unit.
7. Termination in Part means the termination of a part but not all, of the work that has not been completed and accepted under a contract.
8. Termination in Whole means the termination of all of the work that has not been completed and accepted under a contract.