Академический Документы
Профессиональный Документы
Культура Документы
Program
Derun Li
Center for Beam Physics
Lawrence Berkeley National Laboratory
dE dE dE
dx dx dx
RF Cavities
High gradient RF cavities to compensate for lost longitudinal energy
Strong magnetic field to confine muon beams
Lose energy in LH absorbers
Goal:
Development of NC 201-MHz cavity that can operate at ~ 16 MV/m
under a few Tesla solenoidal B fields
Designing, engineering, fabricating, conditioning
and operating a cavity at 16 MV/m with B is a challenging
Introduction (Contd)
NCRF R&D Programs
Develop highest possible NCRF accelerating structure to meet the
requirements for NF or MC
Prototype of 201 MHz cavity
Completed cavity design and fabrication
Cavity installation at MTA in Sept. 2005
Assembly and vacuum
RF power plumbing
RF conditioning started in late Feb. 2006
Experimental studies at 805 MHz with and without external
magnetic fields up to 5-Tesla (2.5 Tesla for MICE)
Completed 5-cell cavity with open iris test at Lab G
Designed, fabricated and tested pillbox-like cavity with demountable
windows at Lab G and moved and resumed recently at MTA, FNAL
Tests with two curved Be windows
Reached 32 MV/m easily without external magnetic field
More tests are in progress with magnetic fields versus achievable gradient
Button test
Cavity Status at Last MUTAC
Where we were at last MUTAC in Berkeley (Apr-2005)
Welding of cooling tube to cavity
Extruding of four ports and vacuum leak tight
Placed purchase order of curved Be windows
Work needs to be done at the time:
Cavity interior buffing
Chemical cleaning and high pressure water rinse of the
cavity interior
Surface cleaning + electro-polishing (EP)
High power RF conditioning of RF couplers with windows
Low power microwave measurements of the cavity with windows:
Frequency
Quality factor Q
Couplings
RF coupler measurement and tuning
Packing and shipping to MTA, FNAL
Outside The Cavity at J-Lab
in Apr-2005
cavity body
cooling tube
ports and
flanges
leak tight
Extruded ports
Inside outer and inner
surface finish
Cavity Progress: Final Interior Buffing
Best possible surface treatment: like SCRF
cavities
Final interior buffing of cavity is performed to
ensure the surfaces are ready for electropolishing
Less buffing needed near equator where fields are
lower
An automated process of buffing was developed
using a rotary buffing wheel and a cavity rotation
fixture
Some local hand work required to clean up some
areas
A series of pads with graduated coarseness was
used
Goal was scratch depth shallow enough for EP
removal
Cavity Progress: EP Setup
Coupler shipment
Final Assembly & Measurement at MTA
Cavity assembly was mounted on the
support and couplers were installed in a View port with RF probes
portable clean room
Dummy copper windows (flat) are used
initially
Couplers were set and frequency was
measured End plate with
Bakeout system hardware wasdiagnostic
installedports
System is leak tight
RF loop couplers
Low Power Measurements at MTA
f = 199.578 MHz
Q0 = 49,000 ~ 51,000 (better
than 90% of the design
value)
Two couplers
balanced
coupling adjustments
S11Measurement
Tuner Measurements
Mechanical tuning plates at four
locations
Dial indicators to measure
displacement between Al plates
Tuning measurement in air
Equivalent to MICE cavity
under vacuum
Adjusted up to 2-mm with 8 steps
of 0.25-mm each
Measured tuner sensitivity
~ 78 kHz/mm
Calculated tuner sensitivity
115 kHz/mm
Disagreements are due to
Dial indicators
deflection of the Al plates
Curved Be Windows
Two windows available now (LBNL)
42-cm in diameter and 0.38-mm in thickness
Good braze (between the two annular copper frames and the
thin beryllium foil)
Achieved the designed window profile
Thin Ti-N coatings on both sides
Ready for HP tests
42cm
Asymmetric RF Heating
ANSYS simulations
A 15o slice cavity model Heat flux (w/m2)
Solve for RF fields
8.4 kW average heating power
20 Co water cooling
Heat flux and temperature distribution
Stress and displacement
Frequency shifts
T ~ 130 Co
Frequency shift of 94 kHz from room
temperature to full RF power due to
Cavity body expansion (small)
T ~ 70 Co
Window displacement (major)
Tuner
Tuning sensitivity 115 kHz/mm
500 kHz range
Temperature (Co)
Asymmetric RF Heating (contd)
High!
Thermalstress
Elasticstresslimitofberylliumis310MPa
Elasticstresslimitofberylliumis310MPa
RF Pulse Heating on the Windows
ANSYS Transient simulations:
Solve for RF fields
center
Scaled (normalized) the fields to
4.5 MW peak power
Apply the power distribution
within 124.4 us pulse and 15 Hz
repetition rate
Temperature rise
middle Window and cavity deformation
using the temperature
distribution
Cavity frequency shift
Temperature rise by a single pulse
~ 1 Co at r = R = 21-cm
edge Cavity frequency change:
~ 80 Hz
RF Heat Transient to Steady State
8.4 kW average heating power: same pulse and rep. rate
Monitor temperature at
three locations on the
windows at r = 0; r = R/2;
r = R = 21-cm
From 20 Co to steady
state, it takes ~ 13 mins
with frequency shift of 94
kHz. This frequency shift
is well within the cavity
bandwidth and can be
tuned easily by
mechanical tuners
Cavity frequency stability with the Be windows under RF
heating (from transient to steady state) is not a problem
Preliminary Test: Setup at MTA
RF probes
201 MHz
The cavity coaxial RF
power line
Vacuum pump
Radiation monitor
2 [MV/m]/division
Without external magnetic field, the
cavity was conditioned very quietly
and quickly to reach
~ 16 MV/m successfully
Gradient is limited by RF power of
0.1 ms/division
4.2 MW due to the modulator.
Summary
The cavity reached design gradient of 16 MV/m
successfully with almost no hard MPs:
Careful handling of the cavity
Good and clean surface finish
EP and high pressure water rinsing
Ti-N coatings of the windows
Test plan being actively developed to include test
studies with
Thin and curved Be windows
RF heating on the windows: transient and steady state
External magnetic fields and achievable gradients versus the
magnetic fields
Numerical and experimental studies of MP for the 201 MHz
cavity