MSETCL TURNKEY PROJECTS


Summery of MSETCL Projects from 2007-2009 in
Nagpur Zone
132/33KV EHV Substation at Karanja (Lad), Amravati,
Rajur (Aurangabad) & Chandwad (Nasik) in 2007-08

132/33KV Substation at Lakhandur, Bhandara in 2009-10

220/132/33KV Substation at Balapur, Amravati in 2009-10

220/132/33KV Substation at Bambhori, Jalgaon in 2009-10

400KV Switching substation at Chandrapur in 2009-10

ABB Group
July 6, 2017 | Slide 2
132/33KV Substation at Karanja (Lad), Amravati
2007-08
LOA No- MSETCL/CO/TKP-I/ABB/T-0701/6801,02,03 dated
26.06.2007
Supply Value- Rs.114,131,535/-

Civil Value- Rs. 16,615,652/-

Erection Value- Rs. 3,537,104/-

Complision Period-12 Months from date of handing over of


site
Date of Handing over of Site-21/01/2008

Date of Complision of work by ABB- 22/01/2009 (12 Months)

Date of Commessioning of Karanja s/s- 04/07/2009

Delay due to non readyness of 132KV line

Electrical Inspector approval

Date of Civil Work complision- 21.01.2009

Date of Erection & Commessioning- 22/01/2009

ABB Group
July 6, 2017 | Slide 3
132/33KV Substation at Karanja (Lad), Amravati
2007-08
Total Amount of work Executed
Supply Value- Rs. 11,72,53,688/-

Civil Value- Rs. 1,33,24,851 /-

Erection Value- Rs. 32,25,308 /-

Pending Activities at MSETCL

Excess/Extra Items amount pending at MSETCL-


Rs.60,29,910/-
LD amount (10% of Contract Value)Pending at MSETCL-
Rs.1,14,13,154 /-
Civil Retaintion Amount pending at MSETCL- Rs.1,332,485/-

PV Claims at MSETCL- Rs.2,385,915/-

ABB Group
July 6, 2017 | Slide 4
132/33KV Substation at Rajur, Aurangabd 2007-08

LOA No- MSETCL/CO/TKP-I/ABB/T-0701/6801,02,03 dated


26.06.2007
Supply Value- Rs.114,131,535/-
Civil Value- Rs. 16,615,652/-
Erection Value- Rs. 3,537,104/-
Complision Period-12 Months from date of handing over of
site
Date of Handing over of Site - 16/11/2007
Date of Complision of work by ABB- 31/07/2008 (12 Months)
Date of Commessioning of Rajur s/s- 02/12/2009
Delay due to non readyness of 132KV line & Still 132KV
Lines are not commessioned
Electrical Inspector approval
Date of Civil Work complision- 05.08.2008
Date of Erection & Commessioning- 02/12/2009

ABB Group
July 6, 2017 | Slide 5
132/33KV Substation at Rajur, Aurangabd 2007-08

Total Amount of work Executed


Supply Value- Rs. 11,54,68,717/-

Civil Value- Rs. 1,33,24,851 /-

Erection Value- Rs. 38,84,547 /-

Pending Activities at MSETCL

Excess/Extra Items amount pending at MSETCL-


Rs.40,19,802/-
LD case of amount (10% of Contract Value) Pending at
MSETCL Division Office- Rs.1,14,13,154 /-
Civil Retaintion Amount pending at MSETCL- Rs.14,61,127/-

PV Claims pending at MSETCL- Rs.25,22,237/-

Taking over or Handing over Certificate are still pending

ABB Group
July 6, 2017 | Slide 6
132/33KV Substation at Chandwad, Nasik 2007-08

LOA No- MSETCL/CO/TKP-I/ABB/T-0701/6801,02,03 dated


26.06.2007
Supply Value- Rs.114,131,535/-

Civil Value- Rs. 16,615,652/-

Erection Value- Rs. 3,537,104/-

Complision Period-12 Months from date of handing over of


site
Date of Handing over of Site - 22/01/2008

Date of Complision of work by ABB- 31/01/2009 (12 Months)

Date of Commessioning of Chandwad s/s- 07/02/2009

Delay of only 15 Day due to initial tesing of s/s

Date of Civil Work complision- 31.01.2009

ABB Group
July 6, 2017 | Slide 7
132/33KV Substation at Chandwad,Nasik 2007-08

Total Amount of work Executed


Supply Value- Rs. 11,79,05,292/-

Civil Value- Rs. 1,33,24,851 /-

Erection Value- Rs. 43,45,402 /-

Pending Activities at MSETCL

Excess/Extra Items amount pending at MSETCL-


Rs.40,19,802/-
LD case of amount (10% of Contract Value) Pending at
MSETCL Division Office- Rs.1,14,13,154 /-
Civil Retaintion Amount pending at MSETCL- Rs.14,61,127/-

PV Claims pending at MSETCL- Rs.25,22,237/-

Taking over or Handing over Certificate are still pending

ABB Group
July 6, 2017 | Slide 8
132/33KV Substation at Lakhandur, Bhandara
2009-10
LOA No- MSETCL/CO/Rr.Proj/TC-II/TKC-IV/T-0804/7431,32,33 dated
02.06.2009
Supply Value- Rs.10,64,25,738/-
Civil Value- Rs. 1,80,46,345/-
Erection Value- Rs. 41,37,967/-
Complision Period-12 Months from date of LOA
Date of Handing over of Site-21/08/2009
Date of Complision of work - (12 Months from LOA)
Present status/progress at Lakhandur s/s
Supply of Material- 90%(132 & 33KV CB,Earting material,Gantry
& equipment structure,station Trafo,Disc Insulators,CI
Pipes,132 & 33KV Isolator, 132KV CT & PT, )
Civil Work- 132KV Gantry Foundation (100%), Control Room
(Plint Level) (80%), 33KV Gantry Structure -(100%), 132 & 33KV
equipment structure (90%)
Erection Work- 33KV gantry structure(100%), 132KV Gantry
structure(80%), 132 & 33KV Equipment Structure (60%)
ABB Group
July 6, 2017 | Slide 9
132/33KV Substation at Lakhandur, Bhandara
2009-10
Delay in Civil Work due to layout changes in SLD,Plan &
Section layout from site.
Delay in Civil drawings due delay in SBC report.
Even though ABB taking over site in Aug-09, progress of s/s
is per schedule but due revision in plan layout approvals
progress of s/s delays.
Payment for s/s work has been made as per activity
schedule of aggrement due to which our bills of supply has
been held up. We request you to make payment of material as
per actual progess of project
Date of Commessioning as per Aggrement- 02/06/2010
Excepated date of Complision of Project- 30/08/2010

ABB Group
July 6, 2017 | Slide 10
220/132/33KV Substation at Balapur, Amravati
2009-10
LOA No- MSETCL/CO/Rr.Proj/TC-II/TKC-IV/T-0804/7431,32,33 dated
02.06.2009
Supply Value- Rs.35,69,51,733/-
Civil Value- Rs.4,73,49,861/-
Erection Value- Rs.1,03,36,452/-
Complision Period-12 Months from date of LOA or MSETCL
Clerance letter i.e.27/08/2009
Date of Handing over of Site-21/12/2009
Date of Complision of work - (12 Months from LOA or MSETCL
clerance letter)
Present status/progress at Balapur s/s
Supply of Material- 85% (220,132 & 33KV CB, 350MT Gantry
& Equipment Structure, CI pipes,220,132 & 33KV
Isolator,220 & 132KV CT & PT,Disc insulator)
Civil Work- 220KV Gantry-60%,132KV gantry-60%, 220KV
Control Room Excavation-50%
Erection Work-Yet to started expected in May-2010
Earthing Of s/s 132KV & 33KV 40%

ABB Group
July 6, 2017 | Slide 11
220/132/33KV Substation at Balapur, Amravati
2009-10
Delay in Work due to three times change in layouts from
division & Circle office also delay in Civil drawings due delay
in SBC report.
Resions for Delay in work for Balapur s/s
SLD,Plan & Section layout changes three times from
02.09.2009.
Delay in SBC reports and Civil Drawings.

Due to changes in layout drawing unable to freez layout


marking and coordination points for civil works.
Due to chnages in layour material procurment & its
delivery at site has been delayed.
Date of commessioning of Balapur s/s- 27/08/2010 as per
contract arrgement
Excepated date of commessioning of Balapur s/s- 31/12/2010

ABB Group
July 6, 2017 | Slide 12
132/33KV Substation at Barshi-Takli, Amravati
2009-10
LOA No- MSETCL/CO/Rr.Proj/TC-II/TKC-IV/T-0804/7431,32,33 dated
02.06.2009
Supply Value- Rs.10,29,94,153/-
Civil Value- Rs.2,18,98,377/-
Erection Value- Rs.41,33,423/-
Complision Period-12 Months from date of LOA or MSETCL
Clerance letter (Still awaited). MERC approval is still awaited
from MSETCL due to which site handing over and other
activities are pending.
Date of Handing over of Site- Pending due to MERC approval
Date of Complision of work - (12 Months from LOA or MSETCL
clerance letter)
Present status/progress at Balapur s/s
Supply of Material- Nil
Civil Work- Nil
Erection Work- Nil

ABB Group
July 6, 2017 | Slide 13
220/132/33KV Substation at Bambhori, Jalgaon
2009-10
LOA No- MSETCL/CO/Rr.Proj/TC-II/TKC-IV/T-0804/7431,32,33 dated
02.06.2009
Supply Value- Rs.27,82,47,159/-
Civil Value- Rs. 3,18,14,871/-
Erection Value- Rs. 73,26,355/-
Complision Period-12 Months from date of LOA
Date of Handing over of Site -09/09/2009
Date of Complision of work - (12 Months from LOA)
Present status/progress at Bambhori s/s
Supply of Material- 90%(220KV,132 & 33KV CB, Earting material,
310MT Gantry & equipment structure,station Trafo,Disc
Insulators,CI Pipes,220,132 & 33KV Isolator, 220,132KV CT & PT )
Civil Work- 220KV Gantry foundation- 90%,132KV Gantry
Foundation (100%), Control Room (80%), 33KV Gantry Structure -
(100%), 220,132 & 33KV equipment structure (90%)
Erection Work- 33KV gantry structure(100%), 220KV & 132KV
Gantry structure(80%), 132 & 33KV Equipment Structure (70%)
ABB Group
July 6, 2017 | Slide 14
400KV Switching Substation at Chandrapur,
2009-10
LOA No- C.E/Tran.Proj/TKC-I/T-0804/29/10393,94,95 dated 31.07.2009
Supply Value- Rs.22,02,26,444/-
Civil Value- Rs.11,14,48,891/-
Erection Value- Rs.46,14,719/-
Complision Period-18 Months from date of Handing over of
Site.
Date of Handing over of Site- Pending due to Varieous Issue
Approch road to Site of 0.5KM is not ready
Compound wall & its coordinates points are pending
SLD, Plan & Section layout submitted for approval from
Oct-09 and approved on 08.02.2010.
Due to dealy in layout approval material/equipment
quantity can not freez & its activity schedule can not
complited within time.
ABB already nominated civil & Erection Contractor from
our end

ABB Group
July 6, 2017 | Slide 15
400KV Switching Substation at Chandrapur,
2009-10
Date of Complision of work - (18 Months from date of
handing over of site)
Present status/progress at Chandrapur s/s
Supply of Material- Nil

Civil Work- Nil

Erection Work- Nil

Commessiong of s/s realted with readyness of incoming line


to matchup with activity schedule.
Payment of material should be made as per actual progress
of work at site beside activity schedule.

ABB Group
July 6, 2017 | Slide 16
THANK YOU