1. The PERT diagram and estimated time of the activities of a project are given below.
Estimated time and immediate predecessor(s) of the activities of a project
for The PERT problem are given below :

Activity a b m Predecessor(s)
A 2 4 3 -
B 3 7 5 -
C 6 22 14 A
D 4 6 5 A
E 4.5 7.5 3 B
F 4.5 9.5 7 B
G 5 15 7 D,E
H 2 8 5 F,G
Find:
(a)The probability to complete the project in 20 days.
(b)Project completion time with 80% probability. 2
(c)The probability to complete the activities A and D in 12 days.
Estimated time and immediate predecssor(s) of the activities of a project
for The PERT problem are given below :

Activity a b m Predecessor(s)
A 7 11 9 -
B 5 11 8 A
C 1 5 3 A
D 2 4 3 B
E 4.5 7.5 3 B
F 3.5 8.5 6 C
G 3 9 4.5 D,E,F
H 2 4 3 E,F
Find:
The probability to complete the project in 23 days.
The project completion time corresponding to 90% probability. 3
The probability to complete the activities A and C in 17 days.
Estimated time and immediate predecssor(s) of the activities of a project
for The PERT problem are given below :

Activity a b m Predecessor(s)

A 1 7 4 -
B 2 2 2 -
C 2 8 5 A
D 3 5 4 A
E 4 8 6 B,C
F 2 6 4 B,C
G 3 9 6 D,E

Find:
The critical path and expected project completion time.
The probability the project will be done in 27 days
The project completion time corresponding to 90% probability.
4
Given an auditing project with the following activities
Activity S.D Crtical? ET
a, add 2 yes 2
b, balance 1 3
c, count 0 yes 4
d, deduct 3 2
e, edit 1 yes 1
f, finance 2 6
g, group 2 yes 4
h, hold 0 yes 2
Find:
i. The probability of completing this project in 12 weeks ( or less).
ii. The probability of completing this project in 13 weeks ( or less). Or 16
weeks ( or less)
iii. The number of weeks required to assure a 92.5 percent chance 5 of
completion..