TABLE OF CONTENTS
One Room Building
Concrete work in foundation (Center line and separate
wall method)
Brickwork in footing (Center line and separate wall
method)
Brickwork in walls (Center line and separate wall
method)
Two Rooms Building
Concrete work in foundation (Center line and separate
wall method)
A

5m
A B B

4m

0.3m
0.3m

3.5m
Plan

0.4m
0.6m

Section at A-A and B-B 0.5m


0.6m
Thickness of footing and foundation is 30 cm each 0.9m
5.3m

4.3 m

0.9 m

Center Line Method


Total Center line = 5.3+5.3+4.3+4.3=19.2 m
Width = 0.9 m Total Qty of concrete in foundation= (19.20.90.3) cum
6.2m
5.3m

4.3 m

3.4 m

0.9 m

Separate Wall Method


Long Wall = 5.3+0.9=6.2 m Short Wall = 4.3-0.9=3.4 m
Width = 0.9 m Total Qty of concrete in fdn= (26.20.90.3) + (23.40.90.3)cum
5.3m

4.3 m

0.6 m

Center Line Method


Total Center line = 5.3+5.3+4.3+4.3=19.2 m
Width = 0.6 m Total Qty of brickwork in Ist footing= (19.20.60.3) cum
5.9 m
5.3m

4.3 m

3.7 m

0.6 m

Separate Wall Method


Long Wall = 5.3+0.6=5.9 m Short Wall = 4.3-0.6=3.7 m
Width = 0.6 m Total Qty of brickwork in Ist footing= (25.90.60.3) + (23.70.60.3)cum
5.3m

4.3 m

0.3 m

Center Line Method


Total Center line = 5.3+5.3+4.3+4.3=19.2 m
Width = 0.3 m Total Qty of brickwork in walls= (19.20.33.5) cum
5.6 m
5.3m

4.3 m

4m

0.3 m

Separate Wall Method


Long Wall = 5.3+0.3=5.6 m Short Wall = 4.3-0.3=4.0 m
Width = 0.3 m Total Qty of brickwork in walls= (25.60.33.5) + (24.00.33.5)cum
A

5m B B
A

4m
0.3m

0.3m

Plan
3.5m

0.4m
0.6m

Section at A-A and B-B 0.5m


0.6m
Thickness of footing and foundation is 30 cm each 0.9m
5.3m 5.3m

4.3 m

Intermediate wall

0.9 m

Center Line Method


Total Center line = 5.3+5.3+5.3+5.3+4.3+4.3+4.3=34.1 m
Width = 0.9 m Total Qty of concrete in fdn= (34.10.90.3) (20.9(0.9/2) 0.3)cum
11.5 m
5.3m 5.3m

4.3 m

Intermediate wall

0.9 m

3.4m

Separate Wall Method


Long Wall = 5.3+5.3+0.9=11.5 m Short Wall = 4.3-0.9=3.4 m
Width = 0.9 m Total Qty of concrete in fdn= (211.50.90.3) + (33.40.90.3)cum