Академический Документы
Профессиональный Документы
Культура Документы
optimistic time (a): the time the activity would take if things did go well
most likely time (m ): the consensus best estimate of the activitys duration
pessimistic time (b): the time the activity would take if things did not go well
PERT Uncertain activity timings
The probabilistic data for project activities generally follow Beta distribution.
The formula for mean () and variance (2) of Beta distribution are given below.
The range for the time estimates if from a to b. The most likely time will be
anywhere in between the range from a to b.
The expected project completion time = i, where i is the expected time of the
ith critical activity.
For the purpose of this analysis, the Beta distribution is approximated to standard
normal distribution whose statistic is given below.
z = (x )/,
where x actual project completion time
expected project completion time
standard deviation of the expected project completion time
Therefore, P(x C) represents the probability that the project will be completed
on or before the C time units.
Analyze the paths through the network and find the critical path.
The length of the critical path is the mean of the project duration probability
distribution which is assumed to be normal.
Probability computations can now be made using the normal distribution table.
PERT A case study for insight
1) Consider the following data of a project with uncertain activity timings.
Duration (weeks)
Activity Predecessor(s) a m b
A - 1 2 3
B - 2 2 8
C A 6 7 8
D B 1 2 3
E A 1 4 7
F C,D 1 5 9
G C,D,E 1 2 3
H F 1 2 9
(a) Construct the project network.
(b) Find the expected duration and variance of each activity.
(c) Find the critical path and the expected project completion time.
(d) What is the probability of completing the project on or before 20 weeks?
(e) If the probability of completing the project is 0.8, find the expected project
completion time.
PERT A case study for insight
Solution:
(a) As a first step, by using the information given in Table, we interlink the various
activities and thus achieve the project network
E G
C
H
D F
B
PERT A case study for insight
Solution:
(b) As a second step, by using the information given in Table, we find out the mean
time (average time) and variance for all the activities of the project.
The formula for the mean time and variance for the activities are as given below
E G
C
H
D F
B
PERT A case study for insight
E 2 6 G 9 11
4 9 15 2 15 17
A 0 2 H 14 17
2 0 2 C 2 9 3 14 17
7 2 9
F 9 14
D 3 5
5 9 14
B 0 3 2 7 9
3 4 7
PERT A case study for insight
Float for various activities of the present example:
(e) P( x C) = 0.8
P [(x - )/ (C )/ ] = 0.8
P [z (C 17)/ 1.945] = 0.8
From the standard normal table, the value of z is 0.84 when the cumulative probability is
0.8. Therefore, (C 17)/1.945 = 0.84
The Project will be completed in 18.63 weeks (approximately 19 weeks) if the probability
of completing the project is 0.8.
PERT Practice problem
P1) Consider the following data of a project with uncertain activity timings.
Duration (weeks)
Activity Predecessor(s) a m b
A - 4 5 12
B - 1 1.5 5
C A 2 3 4
D A 3 4 11
E A 2 3 4
F C 1.5 2 2.5
G D 1.5 3 4.5
H B,E 2.5 3.5 7.5
I H 1.5 2 2.5
J F,G,I 1 2 3
(a) Construct the project network.
(b) Find the expected duration and variance of each activity.
(c) Find the critical path and the expected project completion time.
(d) What is the probability of completing the project on or before 16 weeks?
(e) If the probability of completing the project is 0.9, find the expected project completion time.
PERT Practice problem
P2) Consider the following data of a project with uncertain activity timings.
Duration (weeks)
Activity Predecessor(s) a m b
A - 4 4 10
B - 1 2 9
C - 2 5 14
D A 1 4 7
E A 1 2 3
F A 1 5 9
G B, C 1 2 9
H C 4 4 4
I D 2 2 8
J E, G 6 7 8
(a) Construct the project network.
(b) Find the expected duration and variance of each activity.
(c) Find the critical path and the expected project completion time.
(d) What is the probability of completing the project on or before 12 weeks?
(e) If the probability of completing the project is 0.85, find the expected project completion time.
CPM & PERT Benefits
Benefits
Especially useful when scheduling and controlling large projects
Critical path and slack time analyses help pinpoint activities that need to be
closely watched
Project documentation and graphics point out who is responsible for various
activities
Is the money spent equal to, less than, or greater than the budget?
If the project must be finished in a shorter time, what is the way to accomplish
this at least cost?
CPM & PERT Limitations
Limitations
Project activities have to be clearly defined, independent, and stable in their
relationships
PERT assumes a beta distribution for these time estimates, but the actual
distribution may be different