GIS BUILDING

Costa Rica
Common Practice
Costa Rica GIS Substation (ICE )

Coronado
Jac
Coyol
Minimum
Commisioning
Requirements

Mounting place shall be throughly cleaned


The paint shall not scale-off or crinkles
Electric supply for SF6 Processing Unit
Grounding system connected and tested
Lighting system installed and working
Moving crank shall be working
Epoxy finish floor treatment (if required)
Minimum Tools

Minimum following tools shall be supplied.


Dew point measurement meter
SF6 gas leakage detector
Precision pressure gauge
Gas-service carts (with Gas filling and Evacuating
Plant / Gas reclaimer)
On line PD monitoring system 230kV GIS modules.
Coronado Substation
GIS Outdoors
Coronado Substation
GIS Indoors 1
Coronado Substation
GIS Indoors 2
Coronado Substation
GIS Indoors 3
Coyol Substation
GIS Indoors
Jac Substation
GIS Indoors 1
Questions ?

Thank You for your time