Академический Документы
Профессиональный Документы
Культура Документы
COLONEL. P NALLATHAMBI
STRUCTURAL CONSULTANT
SAKTHI CONSULTACY, CHENNAI
CONTACT 94440 20706
Mail id: nalla.sakthi@gmail.com
CONSTRUCTION FAILURES
General thinking is, Collapse of structure
only a construction failure.
2. Unethical Practice of providing less steel, less cement, covering it below earth ,
Use of substandard materials, improper curing etc.
4. Serviceability- Deflection,
Vibration, Cracks.
4. DEVELOPMENT LENGTH Ld TO BE
CONSIDERED CAREFULLY.
WELD/ COUPLE THE RFT IF
REQUIRED.
If full brick wall is provided over a cantilever slab without beam support,
the slab will bend and cause crack in the wall after certain period.
Therefore, the wall not to touch the roof or fill with soft material over wall
top to avoid cracks.
6 thick Slab shall be provided for the shorter span more than 4.2m (14)
& up to 5.0m (17) length and 7 thick Slab shall be provided for the
shorter span more than 5.0 m (17) & up to 6.0m (20) length and 8 thick
Slab shall be provided for the shorter span more than 6.0 m (20) & up to
7.0m (23) length.
Slab or Wall thickness more than 175mm (7), double layer of re-bar shall
be provided
1. PLINTH BEAM 15 TO 18
2. TIE BEAM 18 TO 20
3. FLOOR BEAMS 12 TO 15
4. GRID BEAMS 20 TO 30
Beam main bars are more than 20#, stirrups should have min 10#.
Column
Column main bars are more than 20#, ties should have min 10#.
L, T and + shape columns shall be adopted where both direction to be
supported.
Orientation of column is an important factor in carrying capacity.
Stilt floor column width shall be 12 to avoid weak story effect
Strong column and weak beam concept to be followed.
Lapping in the mid h/3 part as per Is 13920
DEVELOPMENT OF STRESS IN CONCRETE
DEVELOPMENT LENGTH Ld BE
PROVIDED FOR BOTH SIDE OF THE
MEMBER.
Ld DEPENDS ON:-
GRADE OF CONCRTE;
GRADE OF STEEL;
DIA OF BARS;
As engineering professionals
its also important to learn
how we can help prevent the
kind of destruction
We learn more from buildings
that fall down than from
buildings that stand up.
In fact, it is often easier to learn from
failures rather than from successes.
Forensic Engineering
Early engineering was all
done using experience.
2. 10-member team of the PWD, inspected, one of the team members said neither
The basement nor the soil quality had caused the collapse. The columns and
beams, constructed by the promoter were not as per the design/drawing created
by the architect.
5. The causes for failure is due to negligence of structural design and quality
Control aspects. There was no proper mechanism and procedures to monitor and
regulate the construction activity. No one can be fixed responsible for the
collapse of building and accountability is not known
DELHI METRO BRIDGE FAILURE IN JUNE 2009
Figure 1
The original design consisted of long suspension rods hanging down
from the ceiling.
These hanging suspension rods would then support upper and lower
beams.
The two beams would, in turn, bear the weight of the two walkway floors.
In the proposed design, the rods were hung from the ceiling, then the
upper deck beams were threaded on and slid up the rods, then heavy
washers and nuts where run up the rods to support the upper beam.
The lower beams were then similarly fitted onto the rods at the bottom,
and again were supported with nuts and washers under each end.
HYATT REGENCY WALKWAY COLLAPSE
Unbraced
excavations.
Scaffolding.
Falsework.
Formwork.
Excavation supports.
Temporary erection
and shoring.
Temporary erection and shoring.
Bracing and guying.
CONCLUSION
CHANGING MINDSET TO LATEST
TECHNOLOGY IS MUST