SLOPE STABILIZATION / CONTROL

OF LAND SLIDING AT VULNERABLE


LOCATION OF GDA PARKING
PLAZA AT NATHIAGALI.
(KM 34 OF ABBOTTABAD-NATHIAGALI-
BARRIAN ROAD)

JULY , 2016
ISSUE
At KM 34 on Abbottabad-Nathia Gali- Barrian Road, there is a open
parking plaza of GDA .
The space for Plaza was created by cutting the hillside which has
disturbed the natural stability of the hill slopes
The soil strata has started sliding away now due to this unstable hill slope
because of excessive rainfalls and weathering affects.
The Breast Wall constructed by GDA at back of Plaza (only 6 ft high) has
also undergone cracking due to movement and pressure of unstable soil
strata (Picture Annexed)
A No. of large trees on this slope have also become dangerous due to
sliding away of adjoining soil and there roots have got exposed now.
(CONT..)
ISSUE
The PCC road of GDA on top of the unstable slop has also cracked and
settled down (Picture Annexed)
There are a number of private residences and other buildings near this
location along the cracked PCC road. In case of land sliding at this point,
there is strong likelihood of huge damages to these buildings as well.
The land siding, if it happens, may also block the important road
connecting Abbottabad with Nathiagali and Murree due to falling of forest
trees
The rain water/surface runoff is also directed towards this location
adding to the vulnerability of the sliding strata
SOLUTION

To construct a Breast wall in a height of almost 18M to retain and support


the unstable slope of that strata and counter the chances of land sliding.
The Retaining wall will be constructed in 3 steps each of 6 meter height
and 15 meter length.
Proper drainage system for rain water/surface runoff needs to be provided
to direct the water away from this location at a safe disposal point.
The approx. cost for carrying out the above remedial works is Rs. 3
Millions
PHOTOGRAPHS
Asphalt plant at Harnao
7
Asphalt plant on Murree Expressway

8
Concrete batch plant near Changlagali

9
10
Breast wall near Taj Mahal Hotel

11
COST ESTIMATE

MRS 2016
Schedule
Description of Item Unit
Item No.
Rate Qty Amount

A- BREAST WALL

03-60-a Structural Excavation in Common Material m3 315.25 157.50 49,651.88

Plain Cement Concrete incl. placing,


06-05-i m3 5,090.88 5.40 27,490.75
compacting, finishing & curing (Ratio 1:4:8)

Random rubble masonry in found. & plinth


08-01-d-03 m3 5,369.72 109.35 587,178.88
In cement,sand mortar : Ration 1:6

Plain Cement Concrete incl. placing,


06-05-h Cu,m 5,861.65 12.15 71,219.05
compacting, finishing & curing (Ratio 1:3:6)
Pointing flush on stone work, upto 20'
11-19-c-02 height On stone work raised : In c/s mortar m2 334.43 81.00 27,088.83
1:3
Amount for 6m high, 15 m long Retaining wall (one Step) 762,629

Total Amount for 3 steps Rs 2287887

B- DRAINAGE SYSTEM (L.S) Rs. 800,000


12
G/Total Rs. 3087887
13
THANKS