Presentation at Ecopetrol
October 2008
CONFIDENTIAL 1
Why FCC Troubleshooting is Complex
8/14/2006 CONFIDENTIAL 3
Attack the Problem Systematically
8/14/2006 CONFIDENTIAL 5
Potential Reasons For Increased
Catalyst Losses
# 3 = Operational changes
8/14/2006 CONFIDENTIAL 6
Typical 2-Stage Cyclone System
Plenum
Gas Outlet Tube
2nd Barrel
Gas Inlet Duct Stage
1st
Stage
Dust Hopper
Cone
Dipleg
Flapper Valve
8/14/2006 CONFIDENTIAL 7
#1. Cyclone or Mechanical Damage -
Holes in Cyclone or Plenum
Operational effects Catalyst effects
increased attrition of
fresh catalyst
8/14/2006 CONFIDENTIAL 11
#2. Change in Catalyst / Attrition
Increase in cyclone
pressure drop
8/14/2006 CONFIDENTIAL 12
#3. Operational Changes -
Increased Catalyst Entrainment
8/14/2006 CONFIDENTIAL 13
#3. Operational Changes -
Reactor-side Coking
8/14/2006 CONFIDENTIAL 14
Symptoms of Catalyst Circulation
Problems
8/14/2006 CONFIDENTIAL 15
Potential Reasons For Circulation
Constraints
8/14/2006 CONFIDENTIAL 16
Typical FCC Aeration Layout
REGENERATOR
STRIPPER
RISER
FEED
STEAM
STEAM STEAM
STEAM
AIR
STEAM
AIR
8/14/2006 CONFIDENTIAL 17
#1. Poor Standpipe Aeration
8/14/2006 CONFIDENTIAL 19
#2. Catalyst Particle Size (Too
Course)
8/14/2006 CONFIDENTIAL 20
#3. FCC Mechanical Issues -
Cyclone Problems
8/14/2006 CONFIDENTIAL 22
#3. FCC Mechanical Issues -
Refractory Obstructing Slide Valve
Operational /
mechanical effects Catalyst effects
8/14/2006 CONFIDENTIAL 23
#3. FCC Mechanical Issues -
Air Grid Pluggage
Operational /
Catalyst effects
mechanical effects
High grid P
Low grid P
8/14/2006 CONFIDENTIAL 25
Conclusions