Академический Документы
Профессиональный Документы
Культура Документы
INDUSTRIAL MANAGEMENT
PLANT LOCATION,
LAYOUT AND LINE
BALANCING
CHAPTER 2
consideration mu s t be given to the safe location of the plant so t h a t it does not impose a
CLIMATE :
Adverse climatic conditions a t site will increase costs. Extremes of low temperatures will
require the provision of additional insulation and special heating for equipment and
piping. Similarly, excessive humidity and hot temperatures pose serious problems and
mu s t be considered for selecting a site for the plant. Stronger structures will be needed a t
direct new investment to preferred locations; such as areas of high unemployment. The
vary from one location to another. Similarly, local regulations on zoning, building codes,
nuisance aspects and others facilities can have a major influence on the final choice of the
plant site.
OBJECTIVES OF PLANT LAYOUT
The main objective consists of organizing equipment and
working areas in the most efficient way, and a t the same
time satisfactory and safe for the personnel doing the
work.
Sense of Unity
The feeling of being a unit pursuing the same
objective.
Minimum Movement of people, material and resources.
Safety
In the movement of materials and personnel work
flow.
Flexibility
In designing the plant layout taking into account the
changes over short and medium terms in the
production process and manufacturing volumes.
OBJECTIVES OF PLANT LAYOUT
These main objectives are reached through the attainment
of the following facts:
Congestion reduction.
Elimination of unnecessary occupied areas.
Reduction of administrative and indirect work.
Improvement on control and supervision.
Better adjustment to changing conditions.
Better utilization of the workforce, equipment and services.
Reduction of material handling activities and stock in
process.
Reduction on parts and quality risks.
Reduction on health risks and increase on workers safety.
Moral and workers satisfaction increase.
Reduction on delays and manufacturing time, as well as
increase in production capacity.
All these factors will not be reached simultanesly, so the
best solution will be a balance among them.
PRINCIPLES OF PLANT LAYOUT
M i n i m u m move me nt:
A good layout is one t h a t permits the minimum movement between
the operations. The plant a nd machinery in case of product layout
a nd departments in case of process layout should be arranged as per
sequence of operations of most of the products.
Since straight line is the shortest distance between any two points,
men and materials as far as possible should be made to move along
the straight pa t h
A door may be made in a wall or a hole may be drilled in a ceiling if
t h a t eliminates or reduces material handling in place of stairs or a
distant door.
PRINCIPLES OF PLANT LAYOUT (CONT.)
U ni-direction flow:
A good layout is one t h a t makes the materials move only in the forward
direction, towards stage of completion, with any backtracking.
Since straight line is the shortest distance between any two, points,
materials as far as possible should be made to move on the principle of
straight-line flow. And when straight line flow is not possible, other flows
like U-shaped flow, circular flow or zig zag flow may be adopted, but the
layout may ensure t h a t materials move in the forward direction.
To ensure forward flow, equipment if necessary may be duplicated.
Ma x imu m accessibility:
A good layout is one t h a t makes all servicing and maintenance point readily
accessible.
Machines should be kept sufficiently ap art and with reasonable clearance from
the wall so t h a t lubrication, adjustment and replacement of belts, removal of
parts a t the time of repairs etc can be done conveniently by the maintenance
staff.
Area in front of electrical panels and fire extinguishers should be kept free
from obstructions.
PLANT LAYOUT PROCEDURE
P l a n t La y o u t P ro c e d u re - P h a s e 1 Information G a t h e r in g
Determine what will be produced
Determine how many will be produced
Determine what components will be made or purchased
Determine required operations
Determine sequence of operations
Set time standards for each operation
P l a n t La y o u t P ro c e d u re - P h a s e 2 P ro d u c t i o n a n d F l o w
Analysis
Determine the plant rate, R
Determine the number of machines
Balance production lines
Study the flow requirement
Determine activity relationships
Layout each workstation
PLANT LAYOUT PROCEDURE (C0NT.)
P l a n t La y o ut P ro c e d u re - P h a s e 3 S u p p o r t S e r v i c e s
Identify needs for personal and plant services
Identify office needs
Develop total space requirements
Select material handling equipment
Allocated area
Develop plot plan and building shape
P l a n t La y o u t P ro c e d u re - P h a s e 4 I m p l e m e n t a t i o n a n d
E v a l u a t io n
Construct master plan
Seek input and adjust
Seek approvals
Install
S ta r t up
Follow up
FACILITIES LAYOUT
DEFINITION :
A facility layout is a n arrangement of
everything needed for production of
goods or delivery of services.
A facility is a n entity t h a t facilitates the
performance of any job. It may be a
machine tool, a work centre, a
manufacturing cell, a machine shop, a
department, a warehouse, etc. (Heragu,
1997).
REASON FOR FACILITIES LAYOUT
Reason :
Minimize delays in materials handling a nd customer movement.
Maintain flexibility.
Use labor a n d space effectively.
Promote high employee morale a nd customer satisfaction.
Provide for good housekeeping a nd maintenance.
Enchange sales as appropriate in manufacturing a nd service.
Product A
Product B
Shipping
And
Welding Grinder Inspection Receiving Painting
(C) FIXED POSITION OR LOCATION LAYOUT
man /labor
stationary
(D) COMBINED LAYOUT
Certain manufacturing units may require all three processes
namely intermittent process (job shops), the continuous process
(mass production shops) and the representative process combined
process [i.e. miscellaneous shops].
In most of industries, only a product layout or process layout or
fixed location layout does not exist.
Thus, in manufacturing concerns where several products are
produced in repeated numbers with no likelihood of continuous
production, combined layout is followed.
Generally, a combination of the product and process layout or
other combination are found, in practice, e.g. for industries
involving the fabrication of parts and assembly, fabrication tends
to employ the process layout, while the assembly areas often
employ the product layout.
In soap, manufacturing plant, the machinery manufacturing soap
is arranged on the product line principle, but ancillary services
such as heating, the manufacturing of glycerin, the power house,
the water treatment plant etc. are arranged on a functional basis.
(D) COMBINED LAYOUT (CONT.)
The following figure shows a combined position
layout :
ProcessLayout ProductLayout
Producevariousoperation Manufacturingvarious
componentparts
Assembly
Stamping Welding Heattreatment A B C D E
2. TRADERS
When two outlets carry almost same merchandise, customers
usually buy in the one t h a t is more appealing to them. Thus,
customers are attracted and kept by good layout i.e. good
lighting, attractive colours, good ventilation, air conditioning,
modern design and arrangement and even music.
All of these things mean customer convenience, customer
appeal and greater business volume. The customer is always
impressed by service, efficiency and quality.
Hence, the layout is essential for handling merchandise,
which is arranged as per the space available and the type and
magnitude of goods to be sold keeping in mind the
convenience of customers.
There are three kinds of layouts in retail operations today.
(a) Self service or modified self service layout
(b) Full service layout
(c) Special layouts
2. TRADERS (CONT.)
The self-service layouts, cuts down on sales clerk’s time and allow
customers to select merchandise for themselves. Customers should be led
through the store in a way t h a t will expose them to as much display area
as possible, e.g. Grocery Stores or department stores. In those stores,
necessities or convenience goods should be placed a t the rear of the store.
The use of colour and lighting is very important to direct attention to
interior displays and to make the most of the stores layout.
All operations are not self-service. Certain specialty enterprises sell to
fewer numbers of customers or higher priced product, e.g. Apparel, office
machines, sporting goods, fashion items, hardware, good quality shoes,
jewellery, luggage and accessories, furniture and appliances are all
examples of products t h a t require time and personal attention to be sold.
These full service layouts provide area and equipment necessary in such
cases.
Some layouts depend strictly on the type of special store to be set up, e.g.
TV repair shop, soft ice cream store, and drive-in soft drink stores are all
examples of business requiring special design. Thus, good retail layout
should be the one, which saves rent, time and labour.
3. SERVICES CENTERS AND ESTABLISHMENT
Facilities and
Forecasting Capacity Equipment
Planning
Process
Selection
Work
Technological
Design
Change
QUESTIONS BEFORE SELECTING A
PROCESS
Balance delay (BD) = Total idle time for all workstations x100
Total available working time on all stations
= 1 – LE
EXAMPLE 1:
In one company, production time available per day is 480
minutes a n d 40 units are required per day. The d a t a is
shown below for nine tasks.
PRIORITY OF
TASK TIME
TASK
A 10 -
B 11 A
C 5 B
D 4 B
E 12 A
F 3 C ,D
G 7 F
H 11 E
I 3 G ,H
TOTAL TIME 66
QUESTION 1 :
Determine :
1. Identify precedence diagram.
2. Calculate:
i. Cycle time,
ii. Minimum number of workstations,
iii. Assign the work elements to
workstations.
SOLUTION 1:
1. Precedence diagram
5
10 11 C 3 7
A B F G
4
D 3
I
12 11
E H
SOLUTION 1:
2. Calculate :
S4
S1 S2 5 S6
10 11 C 3 7
A B F G
4
D 3
S3 S5 I
12 11
E H
EXAMPLE 2:
The company I engaged in the assembly of a wagon on a
conveyor. 500 wagons are required per day. Production time
available per day is 420 minutes. The other information is given
below regarding assembly steps and precedence relationships.
11 9 12
B C F
A 45
G 12
50 15 12 8 9
D E H J K
12
I
SOLUTION 2 :
ii) Cycle time.
N = Total time
Cycle time
= 191
50.4
= 3.79 ≈ 4 work stations
SOLUTION 2 :
iv) Group of work stations accordingly.
S3
S1
B C F
A
S4
G
S2
D E H J K
I
SOLUTION 2 :
1 Activityoriented Eventoriented
Usedwhentheactivity timesare
2 Usesaprobabilistictime.
deterministic.
Threetimeestimates; a)optimistic,
3 Onetimeestimate.
b)mostlikely, c)pessimistic.
Directlyintroducescostconcept
4 Indirectlycurrentsfor costs.
analysis.
5 Planningdevice. Controldevice.
CRITICAL PATH METHOD (CPM)
DuPont developed a Critical P a t h Metho d (CPM)
designed to address the challenge of shutting down
chemical plants for maintenance an d then restarting
the plants once the maintenance had been completed.
Complex project, like the above example, require a
series of activities, some of which mu st be performed
sequentially and others t h a t can be performed in
parallel with other activities. This collection of series
and parallel tasks can be modeled as a network.
CPM models the activities and events of a project as a
network. Activities are shown as nodes on the
network and events t h a t signify the beginning or
ending of activities are shown as arcs or lines between
the nodes. The Figure 1.0 shows a n example of a CPM
network diagram:
FIGURE 1.0 : CPM NETWORK
CRITICAL PATH METHOD (CPM)
Critical P a t h Met hod (CPM) is a procedure for
using network analysis to identify those tasks which
are on the critical path; (where any delay in the
completion of these tasks will lengthen the project
timescale, unless action is taken).
For all tasks off the critical path, a degree of
tolerance is possible (late start, late completion, early
start).
Network charts and CPM analysis used to be carried
out by hand.
Software is now available which requires the user
only to enter the tasks, duration of each task and
dependencies upon other tasks; a network chart
and CPM is then automatically created.
STEPS IN CPM PROJECT PLANNING
1. S p e c i f y t h e i n d i v i d u a l a c t i v i t i e s
All the activities in the project are listed. This list can be used
as the basis for adding sequence and duration information in
later steps.
2. D e t e r m i n e t h e s e q u e n c e of t h e a c t i v i t i e s
Some activities are dependent on the completion of other
activities. A list of the immediate predecessors of each activity
is useful for constructing the CPM network diagram.
3. D r a w t h e N e t w o r k D i a g r a m
Once the activities and their sequences have been defined, the
CPM diagram can be drawn. CPM originally was developed as
a n activity on node network.
4. E s t i ma t e activity c o m p l e t i o n t i m e
The time required to complete each activity can be estimated
using past experience. CPM does not take into account
variation in the completion time.
STEPS IN CPM PROJECT PLANNING
5. Identify t h e Critical P a t h
The critical pat h is the longest-duration path through the
network. The significance of the critical p at h is t h a t the
activities t h a t lie on it cannot be delayed without delaying the
project. Because of its impact on the entire project, critical
path analysis is a n important aspect of project planning.
The critical pat h can be identified by determining the
following four parameters for each activity:
• ES - earliest s t a r t time: the earliest time a t which the activity
can s t a r t given t h a t its precedent activities must be completed
first.
• E F - earliest finish time, equal to the earliest s t a r t time for the
activity plus the time required to complete the activity.
• LF - latest finish time: the latest time a t which the activity can
be completed without delaying the project.
• LS - latest s t a r t time, equal to the latest finish time minus the
time required to complete the activity.
STEPS IN CPM PROJECT PLANNING
The slack time for a n activity is the time between its
earliest and latest s t a r t time, or between its earliest
and latest finish time. Slack is the amount of time t h a t
a n activity can be delayed past its earliest s t a rt or
earliest finish without delaying the project.
The critical path is the path through the project
network in which none of the activities have slack, t h a t
is, the path for which ES=LS and EF=LF for all
activities in the path. A delay in the critical path delays
the project. Similarly, to accelerate the project it is
necessary to reduce the total time required for the
activities in the critical path.
6. U p d a t e CPM d i a g r a m
As the project progresses, the actual task completion
times will be known and the network diagram can be
updated to include this information. A new critical path
may emerge, and structural changes may be made in
the network if project requirements change.
CPM BENEFITS AND LIMITATIONS
CPM B e n e f i t s
Provides a graphical view of the project.
Predicts the time required to complete the project.
Shows which activities are critical to maintaining
the schedule and which are not.
CPM Limitations
While CPM is easy to understand and use, it does
not consider the time variations t h a t can have a
great impact on the completion time of a complex
project. CPM was developed for complex but fairly
routine projects with minimum uncertainty in the
project completion times. For less routine projects
there is more uncertainty in the completion times,
and this uncertainty limits its usefulness.
WHY THE CPM?
The formally identifies tasks which must be
completed on time for the whole project to be
completed on time.
Identifies which tasks can be delayed for a while if
resource needs to be reallocated to catch up on
missed tasks.
It helps you to identify the minimum length of time
needed to complete a project.
The CPM determines both the early st ar t and the
late s t a r t date for each activity in the schedule.
PERT
The P r o g r a m E v a l u a t i o n a n d R e v i e w Te c h n i q u e
(PERT) is a network model t h a t allows for randomness
in activity completion times. PERT was developed in the
late 1950's for the U.S. Navy's Polaris project having
thousands of contractors. It h as the potential to reduce
both the time and cost required to complete a project.
Hence there was a strategic emphasis on completing the
Polaris project as quickly as possible, cost was not a n
issue. However no one had ever build a submarine
launched intercontinental ballistic missile before, so
dealing with uncertainty was a key issue. PERT h as the
ability to cope with uncertain activity completion times
(e.g. for a particular activity the most likely completion
time is 4 weeks but it could be any time between 3
weeks and 8 weeks).
PERT (CONT.)
The N e t w o r k D i a g r a m
In a project, a n activity is a task t h a t must be performed and
a n event is a milestone marking the completion of one or more
activities. Before a n activity can begin, all of its predecessor
activities must be completed. Project network models
represent activities and milestones by arcs and nodes.
PERT is typically represented as a n activity on arc network,
in which the activities are represented on the lines and
milestones on the nodes. The Figure 2.0 shows a simple
example of a PERT diagram.
The milestones generally are numbered so t h a t the ending
node of a n activity has a higher number t h a n the beginning
node. Incrementing the numbers by 10 allows for new ones to
be inserted without modifying the numbering of the entire
diagram. The activities in the above diagram are labeled with
letters along with the expected time required to complete the
activity.
FIGURE 2.0 : PERT NETWORK
STEPS IN PERT PLANNING PROCESS
PERT planning involves the following steps:
1. Identify a ctiv it ie s a n d mi l e s t o n e s
The activities are the tasks required to complete the project. The milestones
are the events marking the beginning and end of one or more activities.
2. D e t e r mi n e a ctiv ity s e q u e n c e
This step may be combined with the activity identification step since the
activity sequence is known for some tasks. Other tasks may require more
analysis to determine the exact order in which they mu st be performed.
3. Co nstruct t h e N e t w o r k Dia g ra m
Using the activity sequence information, a network diagram can be drawn
showing the sequence of the serial and parallel activities.
4. E s t i ma t e a ctiv ity t i me s
Weeks are a commonly used unit of time for activity completion, but any
consistent unit of time can be used. A distinguishing feature of PERT is its
ability to deal with uncertainty in activity completion times. For each
activity, the model usually includes three time estimates:
Optimistic time (OT) - generally the shortest time in which the activity
LS - Latest St a rt time
These times are calculated using the expected time for the relevant
activities. The ES a nd E F of each activity are determined by working
forward through the network a nd determining the earliest time a t
which a n activity can st a rt a nd finish considering its predecessor
activities.
STEPS IN CPM PROJECT PLANNING
The latest s t a r t and finish times are the latest times t h a t a n activity
can s t a r t and finish without delaying the project. LS and LF are
found by working backward through the network. The difference in
the latest and earliest finish of each activity is t h a t activity's slack.
The critical path then is the path through the network in which none
of the activities have slack.
The variance in the project completion time can be calculated by
summing the variances in the completion times of the activities in
the critical path. Given this variance, one can calculate the
probability t h a t the project will be completed by a certain date.
Since the critical path determines the completion date of the project,
the project can be accelerated by adding the resources required to
decrease the time for the activities in the critical path. Such a
shortening of the project sometimes is referred to as project crashing.
6. U p d a t e a s project p ro g re s s e s
Make adjustments in the PERT chart as the project progresses. As
the project unfolds, the estimated times can be replaced with actual
times. In cases where there are delays, additional resources may be
needed to stay on schedule and the PERT chart may be modified to
reflect the new situation.
BENEFITS AND LIMITATIONS OF PERT
Be ne fi ts of PERT
PERT is useful because it provides the following information:
Expected project completion time.
Probability of completion before a specified date.
The critical pa t h activities t h a t directly impact the completion
time.
The activities t h a t have slack time a nd t h a t can lend resources to
critical pa t h activities.
Activities st a r t a nd end dates.
1 c 3
a f f
s
i
t d n
a
b g i
r
s
t e 4
2 h
SOLUTION 1 ( CONTINUED ):
ii. A completed sample AON network
a c
f
s f
i
t
n
a d i
r
s
t
b h
e g
DRAW DIAGRAM USING NODES
The node have 3 par t : NO., EST and LST
EST
NO.
LST
4 F 19
2 18 15 5 33
C
A D
4 6 3
36
0 B 8 G 20 H 9
1 4 6 36
0 8 8 12 20 10
E J 5
7
3
7 K 20 L 31
7 8
11 9 20 11 31
EXAMPLE 3 : CRITICAL PATH
Find the critical pat h and critical time
Table 2
Task Predecessor D u r a t io n (days)
A - 5
B - 4
C A 3
D A 4
E A 6
F B, C 4
G D 5
H E 6
I F 6
J G, H 4
SOLUTION 3 : CRITICAL PATH
9 G 14
4 7
12 5 17
D
4
5 E 11 H 17
2 6 5 11 6 8
5 17 J
A C 4
5 3
0 8 21
1 6 10 21
0 11
B I
4 6
3
8 F 12
9
11 4 15
Critical pa t h : A – E – H – J
Critical time : 21 days
FLOATS / SLACKS
Float (slack) - amount of time t h a t a task can be delayed without
causing a delay to:
subsequent tasks (free float)
project completion date (total float)
The slack of a n event is the difference between the latest a nd earliest
event times.
Slack = LST – EST
The events with zero slack time are known as critical events.
Example :
7 4 17
5 17
7 18
9 17
Slack event 5 = 17 – 7 = 10
Slack event 7 = 18 – 4 = 14
Slack event 9 = 17 – 17 = 0
Critical event / slack = 0 , so event 9 is critical event.
FLOAT / SLACKS (CONT.)
Total float is the spare time available on any given
activity if the tail event occurred a t its earliest time
and the head event a t its latest time.
Total float (TF) = Time latest a t head – Time earliest
a t tail – Activity duration
Example :
0 B 8
1 4
0 8 8
Example :
4
B 12
3 4
4 2 15
Activity Duration
1–2 20
1–3 25
2–3 10
2–4 12
3–4 6
4–5 10
SOLUTION 4 : FLOAT / SLACKS
The network diagram.
30
3
30
D
A
25 6
10 C
0 B 20 E 36 F 46
1 2 4 5
0 20 20 12 36 10 46
Critical p a t h : B – E – F
SOLUTION 4 : FLOAT / SLACKS (CONT.)
The floats and slacks for each activity.
Activity Duration Earliest Latest Float Slack
1–2 20 0 20 0 20 0 0 0
(Critical)
1–3 25 0 25 5 30 5 5
2–3 10 20 30 20 30 0 0 0
(Critical)
2–4 12 20 32 24 36 4 4
3–4 6 30 36 30 36 0 0 0
(Critical)
4 –5 10 36 46 36 46 0 0 0
(Critical)
SOLUTION 4 : FLOAT / SLACKS (CONT.)
The slack for each activity.
2 20 20 0 Critical
3 30 30 0 Critical
4 36 36 0 Critical
5 46 46 0 Critical
Critical p a t h : 1 – 2 – 3 – 4 – 5
EXERCISE :
Draw the network and compute the critical path.
SOLUTION :
7 c 13 g 16
a A C G h
7 6 13 3 16
7 2
S
T 0 18
A
R
H 18
T 0
b h
3 d 6 e 9
3 B D E 2
10 3 13 3 16
f e
5 8 3
F
13
Critical path: A– C – G –H
Total Completion Time: 7 + 6 + 3 + 2 = 18
Total slack: 4 + 7 + 7 + 8 = 26
THANK YOU
THE E N D