SEWERAGE MANAGEMENT

IN BANDUNG CITY
Meyor
Audit Internal
Supervisor
R & D
Board
Sekcretary Pres Direct
Information Tech

General Affair Sewerage Direct Water Supply


Direct Direct

Planning Sub Public Service Operation Sub Treatment Sub


Div Sub Div Div Div

Planning Section Customer Data North Bandung Treatment


Section

Eastern Bandung
Vaccum Tanker Quality Control
Construction Sec
Section
West Bandung Pumping Station
Marketing Section
Documentation
Sec South Bandung

Local Reg. no. 5 / 2009 Sew. Meintenance


HUMAN RESOURCES ON THE SEWERAGE
DIVISION

NO SUB DIVISION NUMBER OF NUMBER OF


EMPLOYES
SECTION

1. Technical Planning Sub Div 3 16

2. Operational Sub. Div 5 36

3. Treatment Sub Div 3 31

4. Costumer Service Sub Div 3 22

TOTAL 14 105
SEWERAGE MANAGEMENT
IN BANDUNG CITY

1. OFF SITE SYSTEM

- BUILD OF SEWERAGE SYSTEM IN UNSERVED AREA


- INCREASING OF CONNECTION HOUSE (HC)
- SEWERAGE CONNECTION FOR COMERCIALS BUILDING
- SEWAGE TREATMENT

2. ON SITE SYSTEM
-
- Septic Tank Desludging by PDAM and Privat Company
- Build of Communal Tank
- Build of MCK +
- IPLT Programme
SANITATION SYSTEM
IN BANDUNG

 Sewerage

 Septic Tank

 Open Chanel / River


DOMESTIC WASTE DISPOSAL
IN BANDUNG CITY

Domestic Waste

Sewerage Septic Tank River

Treatment Plant Environment


OFF SITE SYSTEM
SEWERAGE CATCHMENT AREA
IN KOTA BANDUNG

Trunk Sewer Bdg


Barat III
OPEN CHANEL TRUNK SEWER II
TRUNK SEWER I
IPAL
SEWERAGE FACILITIES
IN BANDUNG

Total SEWERAGE : 521,2 Km

 Dutch Sewer : 164 Km


 BUDP I & II : 304 Km
 PDAM : 53,2 Km

SEPTIC TANK : 200.000 Units

PUMPING STATION : 2 Units

Treatment Plant : 1 Unit


SEWERAGE SERVICES AREA

North Area
Citepus River

West Area

2012

East Area

Treatment

Central / South Area

Coverage 65.35 %
EXISTING CONDITION
OF SEWERAGE MANAGEMENT IN BANDUNG

NO PARAMETERS VOLUME UNIT

1. Maksimum capacity 243,000 M3

2. Design Capacity 80,835 M3/day

3. Flows Capacity 82,935 %

4. Idle Capacity + 2.6 %

5. House Connection 104,539 HC

6. Coverage 65.35 %

On 2014
CONNECTION SYSTEM
FOR SEWERAGE IN KOTA BANDUNG

House House

Brandgang
IC

SOF

MH

Treatment Plant
CONNECTION HOUSE
BUILD OF WEST TRUNK SEWER
R O M VEHICLE

Sewer Meintenance
SEWAGE SERVICE

 Household
 Hotel
 Restorant
 Hospital
 Mall etc.
STABILIZATION PROCESS

FACULTATIVE PONDS
ANAEROBIC PONDS

MATURATION POND
ON SITE SYSTEM
EXISTING CONDITION OF ON SITE FACILITIES

NO FACILITIES UNIT REMARKS

1. Septic Tank Private 200.000 Units

2. Comunal Septic Tank 14 Units

3. MCK Plus 2 Units


Hospital, Factories,
4. Industrial Septic Tank I > 100 Units Building. , Office etc.
VEHICLE FACILITIES
( FOR SEPTIC TANK SERVICES)

NO VEHICLES UNIT REMARKS

1. PDAM Vehicles 3 Units 5 units existing

2. Private Company 30 Units 32 private company


Vehicles collaborate with PDAM
COVERAGE SERVICES BY ON SITE SYSTEM
IN KOTA BANDUNG

NO PARAMETERS VOLUME TOTAL


PERSON

1. Septic Tank 200.000 Units 1.000.000

2. Communal Septic Tank 14 Units 12.250

3. Total Services - 1.012.250

Total Inhabitant 2.390.120

Coverage Services 42,3 %


DESLUDGING TRUCK PDAM TIRTAWENING
SMALL SLUDGE TANKER

Sludge Tanker Capacity 600 liters


SLUDGE DISPOSAL LOCATION
KOTA BANDUNG

 Jl. Taman Sari


 Jl. Elang
 Jl. Sukarno Hatta
 Jl. Taman Cibeunying
 Jl. Ahmad Yani
 Jl. Cijaura