Methods
Earthwork
Get SUNYIT email account
Construction Order
• There is an order to all projects
– What activities get done first
– What activities need to be done in a specific
order
– What activities can be done at any point in
time
Start at beginning
• Earthwork
– Moving rock or soil from one location to
another
– Processing it to meet location, elevation,
density moisture content, etc
– Efficient earthwork requires: accurate
estimating of work quantities and conditions,
proper equipment, competent job mangement
Equip Selection
• Proper equipment has major impact on
efficiency and profitablility
• Can equipment perform required work
• Also look at profitablility, other uses for
equipment, return on investment,
availability of parts and services, effect of
downtime on other construction equip
Equipment planning
• Need to plan to effectively use equipment
• Production of equipment
– Production = Volume per cycle/cycles per
hour
– Cycles per hour is based on efficiency of
equip
• Swing angle and elevation to truck bed
• Soil hardness and Soil type
• Room to manuever
Equipment planning
• Cost per production unit = equip cost per
working hour/equip production per hour