METHOD OF ACCES ROAD WORK BATANG TORU 3

OWNER COMPANY: PT. BERKAH ALAM LESTARI ENERGI


CONTRACTOR : PT. Barata Indonesia
PROJECT NAME : EPC Mini Hydro Electric Power Plant Batang Toru 3
SCHEDULE : 630 Days Calendar

Jakarta, Jun 01 2018


MOBILIZATION & SCHEDULLE

EMPLOYEE WORK FOR CURRENTS


AND WATER CHANNELS

SOIL EXCAVATION

BACK FILL SOIL SELECTION

STEP PREPARATION ROAD

INSTALLATION METODE
ASPHALT

INSTALATION CONCRETE
MOBILIZATION EQUIPMENT

• The equipment used in this work is transported from the


poll/garage equipment to the job.

• The manufacture facilities contractor in the form of Office and


base camp as well as the Board of Directors of keet in job sites
to support the smooth execution of the job.

• Documentation and reporting, as well as testing materials in the


laboratory that all of these costs go into mobilization items.

• Demobilization was done after all the implementation work .


MOBILIZATION EQUIPMENT
SCHEDULLE EQUIPMENT, MAN POWER & MATERIAL
SCHEDULLE EQUIPMENT, MAN POWER & MATERIAL
SCHEDULLE EQUIPMENT, MAN POWER & MATERIAL
SCHEDULLE EQUIPMENT, MAN POWER & MATERIAL
SCHEDULLE ACCES ROAD
SCHEDULLE BRIDGE 1
SCHEDULLE BRIDGE 2
LAY OUT ACCESS ROAD AREA
EMPLOYEE WORK FOR CURRENTS AND WATER CHANNELS

• Retting was carried out to make the holes left and right drain channels on the road.

• Prior to the excavations carried out measurements and installation bouwplank.

• Excavation was done by mechanically i.e. using excavators

• The Excavator to load the results of excavations and to dump truck

• Excavator loading hase. Dump truck dump the results of excavations and to place that
allows or at a place approved by the Board of directors so as not to interfere with the
smooth running of the work of the other minerals to il dump truck.

• a bunch of workers spruce up the results of the excavations


EMPLOYEE WORK FOR CURRENTS AND WATER CHANNELS
EMPLOYEE WORK FOR CURRENTS AND WATER CHANNELS
EMPLOYEE WORK FOR CURRENTS AND WATER CHANNELS
EMPLOYEE WORK FOR CURRENTS AND WATER CHANNELS
SOIL EXCAVATION

• The usual digs done at Work places have been determined in accordance with the
instructions of the Board of Directors as well as consultant supervisor.

• Retting implemented using mechanical excavators.

• Excavators do minerals and accumulate the results of excavations at one place is


possible. Excavator digs into the results throw dumpsites around job sites.

• For the quarry cliff, prior to excavations made deposits and slope limits the results
of excavations and customized with a picture of a plan.
SOIL EXCAVATION
SOIL EXCAVATION
SOIL EXCAVATION
SOIL EXAVATION
• We use cut soil model in cliff area with installation safety factor drainage .
BACK FILL SOIL SELECTION

• This works back fill soil the road by using a material of choice that have been approved
by the Superintendent and the Board of Directors.

• Material back fill choice from the quarry or retrieval of material that has been prepared
with the use of a dump truck or use originaly material in site.

• Material disposal soil choice after arriving in location work stacked ( disposal area ) on a
regular basis with the adjusted distance, so that it will ease the process of layered at the
time we need that.

• Further material in overlay using a motor grader so that the material is not wasted and
retrieved the same thickness at each partial as well as in accordance with a specified
slope.

• After in overlay before using the compactor machine compacted material first flushing of
water by using the water tank truck.
BACK FILL SOIL SELECTION
STEP PREPARATION ROAD

• Motor graders and flatten the surface of the road so that the retrieved surface road
flat.

• The Road Surface which has been compressed by using the mean machine tamping
roller vibrators so retrieved surface road that fits the specifications of engineering and
the worker moved to cleaning a& finish that works.
INSTALLATION METODE LIQUID ASPHALT

• The road surface will be coated cleaned from dust and dirt with the use of air
compressor.

• Asphalt and pertamina asphalt sprayer entered into the composition of which has
been determined, then is heated so that it becomes a liquid asphalt mixture that is
sprayed onto the surface is ready for the road.

• Mix liquid asphalt sprayed up into the road surface with clean asphalt sprayer or
manualy liquid asphalt pertamina .
INSTALLATION METODE LIQUID ASPHALT WITH AMP READY ASPHALT
• Aggregate coarse and fine aggregate and sand with the specified comparison put into
cold from AMP.

• Aggregate and asphalt is mixed and heated with AMP.

• A mix of aggregate and asphalt that has developed is loaded into dump trucks and
taken to the location layered.

• After arriving at the site entered into the machine, the vast mixed finisher finisher hot
hrs base above the surface of the road which has been coated with a layer of liquid
asphalt.

• Further solidified with tandem roller followed by Pneumatic tyre roller and compacted
back with tandem roller.

• During work, workers smoothed edge parts overlay using the tools.
INSTALLATION METODE LIQUID ASPHALT WITH AMP READY ASPHALT
RIGID PAVEMENTS WORKS
• Builders and workers creating the formwork corresponds to the image of the plan.
Formwork should be made in such a way that it is able to withstand the weight of the
concrete is on top/inside .
• Materials cement, sand, pebbles and water in comparison with corresponding JMF and
according to specifications in the mixed and stir into the concrete using concrete mixer
and installation of threaded steel bars/ plain steel bars.
• Mix concrete poured in a bucket and transported by the worker to the concrete mix,
further casting in the cast right into the formwork has been prepared
• concrete mix is compacted using a vibrator and a flattening and smoothing the concrete
mix
• Finished casting to keep the quality of concrete is done watering regularly until the
concrete has been really strong
• Constructed from cement concrete or reinforced concrete slabs. Grouted concrete roads
are in the category of semi-rigid pavements. The design of rigid pavement is based on
providing a structural cement concrete slab of sufficient strength to resists the loads from
traffic.
RIGID PAVEMENTS WORKS
RIGID PAVEMENTS WORKS
THANK
YOU

Coming Together, is a Beginning


Keeping Together, is a Progress
Working Together, is a Success