1. 1 Construction Manager
2. 1 Site Engineer
3. 1 Project Safety Officer
4. 1 Foremen
5. 2 Heavy Equipment Operator
6. 2 Drivers
7. 3 Carpenters
8. 4 Masons
9. 5 Laborers
D. Construction Proper:
• The road should be sub grade and compacted to the required density
• The Inspector Checks and Verify the Final Elevation for the Concreting of Road
• The concrete shall be Vibrated for the full width and depth of the strip of
pavement being placed
• The Concrete shall be placed with an approved slip – form paver designed to
spread, consolidate, screed and float finished
• A hand Finish will be necessary to provide dense and homogeneous pavement in
conformance with the plan and specification
• After the final Finish the concrete shall be broomed as part of road specification