RCC FRAMED BUILDINGS (COMMUNITY HOUSING)

Apartment Block A Apartment Block B Apartment Block C Club House/Common Facility Building

Civil Work Electrical Work Plumbing Work Mechanical Work

Sub Structure Super Structure Finishes

Earth Work 1. Line out 1st Floor 2nd Floor 3rd Floor 4th Floor 1st Floor 2nd Floor 3rd Floor 4th Floor
2. Excavation
3. Timber logging / Soil Nailing
4. Leveling of surface RCC for Column 1. Reinforcement Brick Work 1. Up to Lintel level
& Lift Walls 2. Formwork & Scaffolding 2. From Lintel to bottom of
3. Concreting slab above
Footing & 1. PCC Base for the footings 3.1 Batching 3. Curing at intervals
Retaining wall 2. Reinforcement 3.2 Mixing
3. Formwork for the footings 3.3 Placing
4. Concreting 3.4 Vibrating RCC Work for Lintel, Chhaja & Loft
4.1 Batching 4. De shuttering
4.2 Mixing 5. Curing 1. Frame Placement
Door –
4.3 Placing 2. Shutter placement
Window/Vent
4.4 Vibrating 3. Safety Grill installation
RCC for Beam 1. Formwork & Scaffolding Placement
5. De shuttering 4. Glass & Accessory
& Slab 2. Reinforcement
6. Curing
3. Provision for electric outlet
and concealed piping Plastering 1. Wire Meshing at RCC-Brick
Anti Termite Treatment & Water Proofing 4. Concreting junctions
4.1 Batching 2. Internal Plaster
4.2 Mixing 3. External Plaster
1. Lineout 4.3 Placing Wall Cladding 4. Water Proof plaster in toilets
Brick Masonry
2. Foundation / Base courses 4.4 Vibrating 5. Curing at intervals
3. Masonry work up to Plinth 5. De shuttering
6. Curing
Flooring 1. Internal Flooring
2. Bath / Toilet Flooring
Back Filling 1. Earth filling
RCC for Stair 1. Formwork & Scaffolding 2.1 Water proofing
2. Compacting & Leveling
2. Reinforcement 2.2 Light weight concrete
3. BBCC for Ground Floor
3. Provision for anchor bolts filling
for railing 2.3 Tiling
4. Concreting 3. Terrace Flooring
4.1 Batching 3.1 Water Proofing
4.2 Mixing 3.2 BBCC base for slope
4.3 Placing 3.3 China mosaic or other
4.4 Vibrating False Ceiling terrace flooring
5. De shuttering
6. Curing
Painting
PROJECT MANAGEMETN - 01

Mitul Ruparelia CP 1610 RCC FRAMED BUILDING


HIGHWAY PROJECT

PHASE 1 (0 – 50 km) PHASE 2 (51 – 90 km) PHASE 1 (91 – 130 km) PHASE 4 (131 – 180 km)

Subgrade / Grannualar Sub Prime Coat / Base Tack Coat / Seal Coat /
Earthwork (150 mm) base (115 mm) course (100 mm) DBM (75 mm) BC (50 mm)

1. Laying of Wetmix Macadem


2. Rolling by Steel wheel 1. Providing the camber slope
vibrating tendum roller 2. Providing proper super
3. Leveling the surface elevation
3. Rolling by vibrated tendum
1. Earthwork for embankment roller 1. Clean the dust on prepared
2. Preparation of existing surface 4. Rolling by pneumatic tyred base coarse
- Cutting, Trenching roller 2. Application of tack coat by
- Rolling of foot roller 1. Clean the dust on 5. Verify the road level bitumen spreader
- Surface leveling prepared sub base 3. Providing the final camber
3. Porous Pipes Installation 2. application of tack coat by slope and super elevation
bitumen spreader 4. Rolling by steel wheel roller
5. Application of fine sand on
prepared surface
6. Curing

PROJECT MANAGEMETN - 01

Mitul Ruparelia CP 1610 HIGHWAY PROJECT


BRIDGE PROJECT

FOUNDATION MID STRUCTURE SUPER STRUCTURE

PILING Pile Cap Pier Bearing Construction of Approaches Girder Deck Surface
Const. Const. Const.
Pier Cap

1. Line out Abutment Wall Wing (GSR*) 1. Procuring Precast


2. Positioning tripod / winch
Pedestal
Wall pre-stressed girder
3. Permanent liner driving / 2. Shuttering
boring 3. Reinforcement
4. Chiseling 4. Concreting
5. Cage lowering 1. Cutting and bending of 5. De-shuttering
6. Tremie Pipe lowering / flushing reinforcement 1. Cutting and bending of 6. Erecting in place
7. Concreting 2. Preparation of reinforcement 7. Post tensioning
8. Removal of tripod / winch reinforcement cage 2. Preparation of reinforcement 8. Grouting
3. Erection of staging and cage 9. Vertical Joints
simultaneously fixing 3. Casting abutment starter
shutters 4. Erection of staging and
4. Concreting simultaneously fixing shutters
5. De-shuttering and 5. Concreting of abutment 1. Shuttering for RCC Deck
dismantling staging 6. De-shuttering and dismantling 2. Reinforcement
6. Curing staging 3. Concreting
1. Clear area for excavation
7. Curing 4. Curing
2. Excavation up to pile cap
bottom level 5. De-shuttering
1. Testing of Bearing
3. Chippling of pile
2. Surface Cleaning
4. Preparation of bed with PCC
3. Placing 1. Bituminous Concrete on prepared
5. Cutting and bending and
preparation of reinforcement surface
cage 2. Reinforced cement concrete railng
1. Construction of Concrete Leveling Pad 3. Galvanised iron drainage spouts
6. Shuttering for pile cap 2. Installation of Concrete facing panels
7. Concreting 3. Application of Joint Material
8. De shuttering 4. Installation of Geogrids
9. Curing of pile cap 5. Backfill

GSR* WALL: Geosynthetic Soil Retaining Wall PROJECT MANAGEMETN - 01

Mitul Ruparelia CP 1610 BRIDGE PROJECT