Construction Training
Comprehension of Construction
Ⅰ. Plant Concept and Characteristic
플랜트공사중
- Plant Life Cycle 토목/건축공정이
왜 중요한가?
철골,기계,배관,
- Various Process technology and long period Construction 전기,계장등의 공정
에 선행되어, 현장
여건에 따른 공기의
변동폭이 커서 전체
공기에 가장 많은
영향을 준다.
- 2 -
1-3 Plant Construction Work Flow
1) Receipt ITB
2) Review
4) Estimation
5) Bidding
6) Award
9) Construction
10) Pre-Commissioning
-5 -
2. Project Definition
1) FEED / Product
-6 -
2) PROCESS
-7 -
3) PROJECT
-8 -
4) DOCUMENTS
-9 -
5) CODE
-10 -
ESTIMATION
○
社內限
총○부
-11 -
Plant Cost Structure
Material Cost
• Piping Material
Construction Cost • Elect. & Inst. Material
• Steel Structure, etc.
• Material Cost
• Labor Cost Mechanical Work
• Expenses
• Overhead/Profit Piping Work
Electrical Work
Indirect Cost Engineering Fee
• License Fee Instrument Work
• Basic Design Fee CAS Work
• Detail Engineering Fee
• Project Management Fee HVAC/Fire Protection
• Consulting Fee, etc. Work
Insulation/Painting Work
General
• Administrative Overhead • Escalation
• Construction Interest • Financing Cost
• Startup Cost • Tax and Duties
• Working Capital • Contingency
-12 -
ENGINEERING
○
社內限
총○부
-13 -
1. CAS (Civil. Architecture. Steel structure )
CAS Engineering shall provide Structure Plan, Structure Analysis, & Schedule for Civil, 요점정리
-14 -
2) CAS Engineering Procedure.
PROJECT SPECIFICATION
(ENGINEERING & CONSTRUCTIION) DESIGN CRITERIA
SCHEMATIC DESIGN
PLOT PLAN &
ELEVATION
-GENERAL ARRANGEMENT
STRUCTU -THERMAL LOAD
-PIPE LOAD
-WEIGHT OF EQUIPMENT
* EMPTY
RAL -ANCHOR FORCE
-CABLE DUCT LOAD
-OTHERS
* OPERATING
* TEST ANALYSIS
* ERECTION DRAWINGS
* OTHERS & DESIGN
MATERIAL TAKE-OFF
CHECKED
BY QC
DRAWING ISSUE
-15 -
2. Piping
요점정리
-16 -
1) Piping Basic Design
-17 -
2.1 Definition of Pipe Line
요점정리
1) connection Between Equipments
-18 -
3.1 Definition of Plot Plan
요점정리
1) Drawing for all Instrument & Piping of Process
package.
-19 -
Construction
○
社內限
총○부
-20 -
1. General
Plant construction are include Civil/ Building , Mechanical/Steel structure, Piping, Electrical/Instruement.
Insulation/Painting.
요점정리
Building works are comprised of Substation, Control Building, Administration Building, Warehouse
기계, 배관, 전기,
Shelter. Maintenance Shop , etc 계장공사등과 연계
되어 있어 타공정
담당자와 협의하여
공사를 수행한다.
- 21 -
2. Mechanical / Steel Structure
Mechanical works are comprised of Erection of Equipments , Tanks & Pump . Etc
요점정리
Steel Structure works means erection of steel Structure for Pipe, Equipments 플랜트 곡사 진행
순서는?
일반적으로 토목/건
축의 기초/빌딩공사
→ 철골/기계설치
→ 배관설치
→ 전기/계장공사
→ 보온/도장공사
→ 시운전 이나,
현장여건에 맞게
Furnace Erection Steel Structure Erection
Steel Structure Erection 일부공종은 동시
수행되거나, 순서가
3. Piping 바뀌어 수행되기도
한다.
Piping works comprised under ground & above ground.
Piping works are same as blood vessel in the human body
5. Insulation/Painting
Insulation work for Consist of temporary & painting work for Rustproof.
1. Survey
2. Piling
3. Foundation
Spread Footing Type ( General)
Table Top Type ( Special Type such as Compressor Foundation)
Ring Wall Type (Tank Foundation)
6. Drainage System
Surface Drainage system :Storm Water Sewer
Oily Sewer system
Chemical Sewer system
Sanitary Sewer system
- 24 -
1. Survey work
수준측량이란 ?
2. Piling work
표고(높이)차를 측정
(H 높이)
- Piling work to be provided where the unsatisfied soil area.
좌표측량이란 ?
- Piling work will be done for all kind of Foundation
평면위치를 측정
- Materials of pile can be used Steel & concrete (X,Y좌표)
Tremie Pipe
- 25 -
3. Foundation work
1) Excavation work
터파기시 유의점은 ?
Excavation work to be done before foundation work.
1. 터파기 경사면의
The Area , Depth ,size of Excavation to be decided by the size of Foundation. 각도를 준수하여야
한다.
. 2. 작업공간을 확보
하여야 한다.
(기초작업 좌우공간)
(U/G배관: 하부공간)
- 26 -
2) Blind concrete
Blind concrete calls ‘’ lean concrete’’ “ blind concrete” or “leveling concrete” and strength is
normally 135 Kg/cm2.
Blind concrete is not a Structural concrete but make a leveling to the bottom of Foundation. 요점정리
공사특성상 양생이
3) Footing work 절대적으로 필요하며
그 기간동안 후속공정
을 진행할 수 없으므로
Footing concrete will be located on the blind concrete.
공정계획수립시 양생
Footing size will be designed by load. 기간을 공정에 반영
The strength of footing is generally 210kg/m2 - 하여야 한다.
280 kg/m2
4) Pedestal work
- 27 -
5) Curing & Removal of form work
Form to removed after concrete curing.
After form is removed , Concrete surface shall be Moisture Curing using Burlap or vinyl covering
with water spray.
6) Backfilling work
- 28 -
4. Water basin
Plant has Two type of water basin, one is for flush water the other one is for waste water.
5. Trench 주요Point
콤프레셔 구조물인
The purpose of trench is for pipe & cable where pipe & cable are laying through Shelter는 공정상
underground. 많은 공기가 필요
착수전 충분한 검토
6. Drainage system
Pipe for drainage shall be used Hume Pipe, Carbon Steel Pipe, HDPE Pipe
PVC Pipe, FRP Pipe.
7. Paving work
- 29 -
Paving work
2.1 Plant Building divided for Process & Non Process area.
Concrete work for Building is similar to the Civil works
요점정리
2.2 Type of building
건축 구조물의 종류?
(1)Process Building
Substation
- Control Building Control Building
Administration
- Substation Building Operator Shelter
Car Parking Shelter
- Process Building
- Shelters
- Laboratory Building
- Pump/Blower House
- Turbine Building
- 31 -
- Vehicle Shed
2.3 Function of Building
-32 -
3. Steel Structure works
Steel structure activities are divided as a shop fabrication & site erection.
1. Steel structure Work Procedure
요점정리
Welding Bolting
Painting Grouting
Issue Painting
-33 -
2. Steel Structure Photos
-34 -
Concrete
foundation
Pipe rack
-35 -
Erection of steel str.
Concrete + Steel
Str. Combined
-36 -
Steel str. factory
Manufacturing of
steel str.
-37 -
4. Mechanical Works
2. Major Activities
1) STATIONARY EQUIPMENT
① REACTOR
② COLUMN
③ DRUM/VESSEL
④ HEAT EXCHANGER
2) ROTATING EQUIPMENT
① AIR COOLER
② PUMP
③ COMPRESSOR
3) SPECIAL EQUIPMENT
① FURNACE
② FLARE STACK
③ PACKAGED ITEMS
-38 -
3. Purpose of machine
● Reactor
Pressure vessel for chemical
reaction.
● Column
Pressure vessel for segregation
● Heat Exchanger
Main purpose is for Heat exchange.
The type of H/E is Shell & tub ,
double pipe, Plate type ,etc
● Filter
Pressure for strains of foreign
substance.
● Storage Tank
storage for product
-39 -
5. Piping works
- Shop fabrication
- Field erection
C. Pressure test
D. PWHT/NDE
E. Flushing
F. Reinstatement
G. Leak test
- 40 -
3. Piping works
A. U/G Piping
a . Piping work installed to the underground such as COOLING WATER, FIRE WATER,
SEA WATER, DRAIN LINE 요점정리
B. A/G Piping
- Piping Work installed to the above ground.
a. Shop fabrication
- Procedure
Drawing review – Review material/issue – painting--- Shop welding – Tagging –
NDE/PWHT – Locating.
b. Field Erection
- Procedure
Drawing Review – Delivery Spool – Fit-up – Fielding Welding – Support install –
NDE/PWHT
- 41 -
C. PRESSURE TEST : Test with Pressure such as water, Air
E. FLUSHING
After piping work, Inside of Piping shall be cleaned using Power Brush, Water, Oil, Air or Steam.
Flushing Blowing
Application Water Line, Lube Oil Line All line Except Lube Oil, F/F, CW Line
F/F Line
- 42 -
F. REINSTATEMENT
2. Procedure
1) Remove Temporary line / Blind
2) Install Counter valve
3) Install Orifice
4) Install Chemical Injection Nozzle
5) Install Pump suction discharge line – Alignment
6) Replace Temporary Strainer
7) Install PSV
- 43 -
H. FINAL JOB REPORT
Site Engineer shall prepare Final Job Report to use for Next Project.
요점정리
Final Job Report shall include…
- 44 -
6. Insulation works
-45 -
Insulation Photo – (Elbow)
-46 -
D
-47 -
7. Electrical Works
7) Telecommunication System
1) Fire Alarm : A fire alarm is a device that makes a noise, for example with a bell, to warn people
when there is a fire
7. Grounding/Lightening
1) Overall-1
-72 -
9. Pre-Commissioning 1. 개 요
1. overall
주요Point
Construction PRECOMMISSIONING
시운전단계 중
Precommissioning
과 Commissioning
단계는 M.C를
전후로 하여 구분
된다.
COMMISSIONING
Commissioning
START-UP
PERFORMANCE TEST
-73 -
2. Overall Completion Logic
-74 -
3. Pre-Commissioning 3. Precommissioning
http://www.youtube.com/watch?v=plO7d1uQSxw&feature=related
http://www.youtube.com/watch?v=prOksl7oVOk&feature=related
http://www.youtube.com/watch?v=7NxG84silYE&feature=related
-75 -
2) Chemical Cleaning
요점정리
Preservation이란,
Catalyst 등 충진물
이 Loading 된 이후,
외부로부터 산소나
습기로부터 부식이
일어나지 않도록
보존하는 것
-76 -
3) Pig Cleaning
주요Point
Pig Cleaning은
Water Flushing,
Air Blowing을
적용해야 하나
여건이 어려울 때
적용하는 기법이다.
2. Procedure
1) Remove Temporary line / Blind
2) Install Counter valve
3) Install Orifice
4) Install Chemical Injection Nozzle
5) Install Pump suction discharge line – Alignment
6) replace Temporary Strainer
7) Install PSV
- 78 -
5. Installation of packing
주요Point
• Charcoal
• Send / Gravel
• Packing Material
• Filter Internal
-79 -
Catalyst packing photo
http://www.youtube.com/watch?v=Wm6oY08_R9Q&feature=related
-80 -
10. Examination