Вы находитесь на странице: 1из 67

SCHEDULE OF

DIMENSIONS

PRESENTED BY
N.R.KALE/Lecturer (works)
What is SOD ?
 Schedule of dimension is nothing but a
schedule, which lays down :-
 Limiting values, recommended values,
and infringement to limiting values,
which can be continued over entire
Indian railways system for various track
parameters.
 Goods wagon and coaching stock
parameters.
 Horizontal and vertical clearances to be
followed on Indian railways.
Necessity of S O D
 It is absolutely essential to ensure safety of
traveling public as well as goods over entire
Indian railways system.
 To adopt uniform system of track tolerances,
location of structures and construction
standard all over the Indian railways.
 To permit different types of coaching and
goods stock owned by different railways to
ply on entire railway system with same level
of degree of safety.
Brief Introduction
 1913 - First schedule of maxm & minm
dimension.
 1922 – SOD with Maxm. Minm & recommended
dimension was published.
 1929 – Amendment in order to introduce some
improvement and additions of clearances
required for electric traction.
 1936 – Financial stringency on railway therefore
amendment to restrict capital expenditure to
minimum.
Contd. ….
 1939 & 1958 reprinted with some modifications.
 1973 – Reprinted with conversion to metric
system, introduction of dimensions for 25KV AC
traction.
 1990 – Recommendations of 64th Track
Standard Committee for revision of SOD of
1939 reprinted in 1973.
 2004 – Revised version published with some
modifications.
MAIN FEATURES OF SOD-2004

 Dimensions are given only for 1676 mm


gauge.
 Consists of only metric units.
 Only two schedules – schedule I & schedule II
 Extra clearances required for curves are
modified to suit speed of 160 kmph and SE of 165
mm
 Additional appendix for extra clearances required
for 200 kmph is also given with 185 mm SE
SCHEDULE - I
 Schedule I of SOD-2004 consists of those
items which are mandatory and have to be
observed on all 1676 mm gauge Railways in
India.
 Contains the items of Schedule- I and certain
selected items of Schedule- II of 1973 Version
Contd. …
DIMENSIONS given in Schedule-I are classified
under two heads :-
‘Existing works’ – The works which were
existing before issue of SOD ( 2004 ).
‘New works’ – Include new constructions,
additions of new lines/structure, gauge
conversion and doubling
Contd. …
However following works will not be included in
‘New works’-
Shifting of Points & Crossings.
Extension of siding.
Extension of building, etc.
SCHEDULE - II
 Schedule – II contains the existing
infringements of Schedule – I.

 These are items, which were included in


Schedule – III of 1973 version.
CONTENT OF S.O.D.
SCHEDULE I :-i) ESSENTIAL FOR SAFETY
ii) PRIOR SANCTION FOR
DEVIATION
CHAPTER DETAILS

I GENERAL Spacing, ,Curves, Br.Bldg Structure,


Tunnel, Sig Gear, locking etc.

II. STN YARD Pts.& Crossing, P/F, Bldg/St,


Tr.Spacing etc.
Contd. …
III –W/Shop & Tr,Spacing, O/Head
Sheds Girder Structure.

IV –(A) Rolling Wheels /Axles, Wheelbase,


stock (C&W) Buffers / Couplings,Floor
height Max.moving
dimensions
IV-(B)- Rolling Max. future moving
Stock (3660 mm) - dimensions.
Contd. …
IV-©-Rolling Stock Wheels & Axles,Buffers/
(Loco) Couplings,Max. moving
Dimensions.

V-ELECT.TR.(D.C.) Elect.Equipment Clearances .

V-(A)----------(A.C.) -------DO-----------
SCHEDULE I CHAPTER I
MIN. DIST. C/C OF TRACK .
As per CS No.9 dated.16.10.2012
i) For existing works 4265 mm
ii) For new works/additions
to existing works 5300 mm
Note: OHE mast and Signal post shall not
preferably be provided in between tracks.
However, under unavoidable circumstances, the
clearance shall be increased by equal to width
of such structure/foundation.
SCHEDULE I CHAPTER I
 MIN. DIST. C/C OF TRACK
(Tunnel, Semi-through/Through girder bridges)
As per CS No.9 dated.16.10.2012
i) For existing works 4495 mm
ii) For new works/additions
to existing works 4725 mm
Contd. …
 Minimum Radius of curves -175 m (10 degree)

Note: Check rails to be provided in curves having


radius 218 meters(8 degree) and sharper.
Check rails may also be provided in flatter
curves, if high speed is contemplated.
Contd. …
A) Maximum clear distance bet. two sleepers on
bridge:-

i) on existing Bridges 510 mm

ii) New construction & on existing bridges 450 mm


during regirdering /TSR
B) Maximum distance between Joint 200 mm
sleepers on Bridges.
Contd. …
Minimum thickness 150 mm
of Bridge timber,
exclusive of
notching.
Minimum length of 305 mm + (subject to
bridge sleeper. dist. from out min.2440
side to mm)
outside of
girder flange
SCHEDULE I CHAPTER I
CONTD…
 Minimum clearance of

check rail on curve. 44 mm.


 Minimum clearance of
check rail on level crossing. 51 mm.
 Maximum clearance of check
rail on level crossing. 57 mm
 Minimum depth for wheel flange. 38 mm
Schedule I chapter I contd. …
BULDING AND STRUCTURE
Minimum horizontal distance from center
of track to any structure from RL to
305 mm above RL
i) For existing works 1675 mm
ii) For new works or alterations
to existing works 1905 mm
Minimum horizontal distance from C/L of track to
any structure except a platform.

i)For existing works. 2135 mm


From 305 mm to 4420 mm
above RL.
ii) For new works or alterations 1905 mm
to new works increasing to
From 305 mm to1065 mm 2360 mm
above R L
From 1065 mm to 3355 mm 2360 mm
Contd. …

From 3355 to 4420 mm 2360 mm


above rail level decreasing to
2135 mm

From 4420 to 5870 mm 2135 mm


above rail level decreasing to 915
mm
Contd. …
Below the rail level up to the 2575 mm
formation level on the straight
track and curve up to 875 m

Below the rail level up to the 2725 mm


formation level on the curve
Radius< 875 m
Schedule I Chapter I contd. …
Minimum horizontal distance of any telegraph
post from C/L of nearest track

i) For existing works - Ht of the post +


2135 mm.
ii) For new works - Ht of the post +
2360 mm.
Height of ROB & FOB (C.S.No.7/13)
 Min. ht. above rail level for a dist. Of 1600
mm on either side of the centre of track.
Where 25 K.V. A.C. traction is likely to be
used.
 F.O.B. 6250 mm (5270 mm)*

 R.O.B./ Fly over 5870 mm (5070 mm)*


* For 4.80 M height of contact wire
C.S.No.10 Dated 08.11.12
Note for overhead structure-
 For existing overhead structures, wherever
feasible, the ht. of contact wire shall be as high as
possible to allow passage of ODC of 4.8 m height.
 If any T/out or X/over is within 40m or any LC is
within 520m, the ht. shall be 6250m
 On lines proposed for electrified, provision shall be
made in OHE structure to permit an allowance of
275mm for raising of track
Contd. …(CS No.13 dt. 21.10.13 )
Minimum height above rail level for 6100 mm
telegraph, telephone and other such
low tension wires crossing a railway
The minimum horizontal distance from Height of
centre of nearest track to structure structure +
carrying electrical conductors crossing 2.135M
a railway (For existing work)
----------do------------(For new work) Height of
structure + 6
meters
Schedule I chapter I contd. …
Safety Refuges :-
Max. distance in tunnels 100 m
On bridges with
a)span less than 100 m 100 m
b)spans of 100 m or more - On each pier
Provision of Trolley refuse as per CS No 116
of IRPWM
Location Distance
Maximum distance should not be more than 1Km subject to
following
Cutting in straight 200M
Cutting in curve 100M
High Embankment 200M
Tunnel 100M
Bridges with span less than 100 m 100M
Bridges with spans of 100 m or more On each pier
On Ballasted deck bridges 50M
Interlocking and signal gear
Description Dimension
Maximum height above rail level of any part of 64 mm
inter locking or signal gear for a width of 1600 mm
or 1830 mm in case of tunnels, through and semi-
through girders on either side of centre of track
Note: 1. For a distance of 229 mm outside and 140mm inside
the gauge faces of the rail, no gear or track fitting must project
above rail level
2. Metal covers with ramps on both sides must be provided
over interlocking gear to prevent hanging coupling from
damaging the gear.
Schedule I chapter I contd. …
Formation width :- (Considering formation slope of
1 in 30 and track distance 5300mm and straight track)
For single line straight track –
Min. width in embankment 6850 mm
Min. width in cutting 6250 mm
For Double line straight track –
Min. width in embankment 12150 mm
Min. width in cutting 11550 mm
Formation width as per CS No.16 of
LWRM and CS No.135 of IRPWM
For Single Line Formation Width
For Embankment 7850 mm
For cutting 7850 mm
For Double Line
For Embankment 13160 mm
For cutting 13160 mm
Gauge on straight and curves
Alignment Gauge tolerance
Straight including curves of -5 mm to +3 mm
350 M (1671 to 1679mm)
Curves less than 350 M Up to +10 mm
(Up to 1686 mm)
Schedule I chapter II
(Station yard)
Min. dist. Centre to centre of track :-
(i) For existing works 4265 mm
(ii) For new works / Alt. 5300 mm
Max. gradient in Station yard :-
(i) For existing works 1 in 400
(ii) For new works / Alt. 1 in 1200
Note: There must be no change of grades
within 30 meters of any points & crossings.
The power of condonation for gradient
steeper than 1 in 1200 in case of new work
(As per Corrigendum to C.S. No.12)
Gradient Authority
Steeper than 1 in 1200 and Personal approval of G. M.
up to 1 in 400 through COM of the zonal
Railway after making efforts for
providing grade as flatter as
possible
Steeper than 1 in 400 and C.R.S.
up to 1 in 260
Steeper than 1in 260 Railway Board through C.C.R.S.
Chapter ii contd. …
Horizontal dist. From C/L of track to
Max. Min.
Face of platform 1680 mm 1670mm
coping
Face of goods 1680 mm 1670 mm
platform coping
Face of any platform 1905 mm 1675 mm
wall
New platform wall should be built to maximum
dimensions and the coping corbelled out to 1675mm.
Platform on curved track
 No passenger platform in case of new line,
would be constructed on a curve having
radius less than 875 M
 Extra allowance to be reduced by 51mm for
platform, inside of curve.
 Extra allowance to be reduced by 25mm for
platform, outside of curve.
Chapter ii contd. …
Height above rail level –

Max. Min.
For high level 840 mm 760 mm
passenger platform
For medium level 455 mm -
passenger platform
For goods platform 1065 mm -
Railway Board’s directives for
Mumbai suburban section
 Vide letter No.2007/CEDO/SD/O dated
19.02.14, Railway Board has conveyed Board’s
approval to change the height range of platform
in Mumbai suburban section from 760-840mm
to 840-920mm.
 RDSO has been asked to submit draft
correction slip for Board’s approval which is yet
to be issued.
Chapter II Contd. (Buildings and structures)
 Minimum Horizontal distance of any building on
a passenger platform from center of track.
Height of the structure Distance
From P/F level to 305 mm above P/F level 5180mm
5330mm
From 305mm above P/F level to 3430mm 5330mm
above RL
From 3430 to 4115mm above RL for existing 5330mm
work and 3810mm
From 3430 to 4610mm above RL for new work
Contd. ….. (CS No. 11)
 Min. horizontal distance of any bldg. or
longitudinal boundary fence from centre line
of track of passenger platform which is not
an island (For New works)
 Minimum 6830mm
 Recommended 12130mm
Note: Recommended dimension is for setting back
the platform to make room for an additional track
in future, without infringing minimum distance.
Chapter No. 2 contd. ….
 Minimum horizontal distance from center line of
track to a pillar, column, lamp of similar isolated
structure on a passenger platform.
Height Distance

From platform level to 4570mm increasing


305mm above platform level uniformly to 4720mm
From 305mm above 4720mm
platform level to 3705mm
above rail level
CHAPTER II CONTD…
POINTS & CROSSINGS :- Clearance of
Max. Min.
Check rail opposite nose of 48 mm 44 mm
crossing
----------------Do------------------ 45 mm 41 mm
(In case of PRC T/O )
Wing rail at nose of crossing 48 mm 44 mm
------------------Do--------------- 45 mm 41 mm
(In case of PRC T/O )
Chapter ii contd. …
Points & Crossings :-
Clearance bet. Toe of open switch and
stock rail.
(i) For Existing work 95 mm
(ii) For new work or alteration to existing 115 mm
work
Minimum Radius of curvature for Slip 218 m
points, Turn outs, Cross over.
Chapter ii contd. …
Points & Crossings :-
Minimum angle of crossing. (ordinary) 1 in 16
Crossing as flat as 1 in 20 will usually be sanctioned
if recommended by CRS.
Minimum length of Tongue Rail. 3660 mm

Diamond crossing not to be flatter than 1 in 8 1/2

Diamond crossing as flat as 1 in 10 will usually be


sanctioned if recommended by CRS.
Length of siding for New work (C.S. No.8)
Condition Length of siding
Where the ruling gradient is 750 Meters
1in 100 and flatter
Steeper than 1 in 100 Length of longest train permitted
in the section + 35 M

Clear available length denotes :


1. Distance between foot of signal and FM in rear on the same
line in case of main line and Directional loop at station yard
2. In case of common loop, distance between two starter
signals of opposite direction on the same line.
Maximum Moving Dimensions
Description 3250mm 3660mm
wide stock Wide stock
Max. width over all projections, at 3135mm 3505mm
305mm above RL, when fully
loaded
Max. width over all projections 3250mm 3660mm
from 305mm to 1082/1145mm
above RL when fully loaded 3135mm 3505mm
Max. width with over open doors, 4265mm 4725mm
including all projections for goods
vehicle
Max. height above RL for a width 4265mm 4725mm
of 760mm on either side of the
centre of unloaded vehicle
SCHEDULE I CHAPTER IV (A)
 Wheel Gauge 1599mm-1602mm.

 Tread Dia of new wheel 914mm-1092mm.

 Flange Projection 28.5mm-35.0 mm

 Flange Thickness 16 mm- 29.4 mm*

* As per CS No.14
Contd. …
 Tyre width 127mm minimum.
Floor height above RL
 Passenger 1345mm-1220mm.
 Goods 1345mm-1145mm.

 Buffer height above RL 1030mm-1105mm

 Maxim Wheel Base for 4-Wheeler - 6100mm


SCHEDULE I CHAPTERIV(A) CONTD…
Min.Wheel base for bogie truck 1830mm.
Min. Wheel base for pass. Bogie 2440mm.

Min. Dist. Bet bogie centres 2/3 vehicle


length
Max. Dist bet. Bogie centres: 14.900m.*
* CS No.14
Max. Lenth of body or roof: 8540mm.
4-Wheeler (3200mm wide ) 21340mm
Bogie vehicles (3250mm. Wide)
SCHEDULE V (A) A.C.
 MIN. HT. OF UNDERSIDE OF LIVE WIRE:
BRIDGES & TUNNELS 4800mm
IN OPEN 5500mm
SHEDS 5800mm
LEVEL CROSSINGS 5500mm
 MAX. VARIATION OF LIVE WIRE EITHER SIDE :
STRAGIHT 200mm
CURVES 300mm
 MAX. WITDTH OF PENTOGRAPH 1800mm
SCHEDULE-II
 Min. dist C/L to C/L of track
i)for 3250mm wide stock 3660 mm
ii) for 3660mm wide stock 4040 mm
 Min. clear dist. From C/L
of Track to any fixed structure
From RL to 1065 mm above
Rail level 1675/1905mm
Contd. …
 From 1065mm to 3505mm
above R/L 1980/2135mm
 4265 mm above R/L 2055 mm
( with SR 16 kmph ) 1980 mm
 Min. clear height above R/L
for a dist. of 305 mm/915 mm on either
of centre of track 4420 mm / 5030 mm
Over-dimensioned consignment
 When a consignment whose length,width and
height are such that one or more of them
infringe the standard moving dimension at any
point during the run from start to destination,
then the consignment is called O.D.C.
Class ‘A’ O.D.C.
(Permitted out of gauge loads)
Which exceed the maximum moving
dimensions but do not infringe any fixed
structure on the route by a net clearance of 150
mm and above and gross clearance 225 mm
and above.
Contd. …
Class ‘B’ O.D.C.(Exceptional out of gauge load)
– Net clearance not less than 75 mm but less
than 150 mm, gross clearance 150 mm to 225
mm.
Class ‘C’ O.D.C.-(Extraordinary out of gauge
loads) Net clearance are less than 75 mm and
gross clearance less than 150 mm
Speed Restrictions for ‘A’ Class
O.D.C.
Gauge Speed Restriction Escort Sanctionin
g authority
B.G Sectional speed of Not COPS
four wheeler required
30 kmph where gross
clearances is less
than 380 mm.
Movement by
day/night
Speed Restrictions for ‘B’
Class O.D.C.
Gauge Speed Restriction Escort Sanctionin
g authority

B.G. 40 kmph by day and SSE CE


night During night stop (C&W)
dead and proceed T.I.
slowly at approach of
structure having gross
clearance less than 225
mm.
Speed Restrictions for ‘C’
Class O.D.C.
Gauge Escort Sanctioning
Speed authority
Restriction
B.G. 25 kmph SSE/SE CRS
Movement (C&W)
by day T.I.
only SSE/SE
(P.Way)
TRD staff
THANKS

Вам также может понравиться