BILLINGS AND REQUIREMENTS

ALL VALUE TECHNICAL GROUP


CONTENTS
• DP/CONTRACT
• PROGRESS BILLING
• FINAL PROGRESS BILLING
• RETENTION
• ADDITIONALS/CHANGE ORDER
DP/CONTRACT
• TYPICAL DOWN PAYMENT FOR ALL VALUE
PROJECT CONTRACTS ARE AT 30%, WITH 10%
RETENTION.
• CONTRACT PREPARATION WILL BE C/O THE
DESIGNATED PURCHASING.
PROGRESS BILLING
• FORWARD TO PRODUCTION
• REQUIREMENTS
– GROSS BILLING STATEMENT
– BILLING COST BREAKDOWN SUMMARY
– ATTACHED PICTURES
FINAL PROGRESS BILLING
• FORWARD TO PRODUCTION
• REQUIREMENTS
– GROSS BILLING STATEMENT
– BILLING COST BREAKDOWN SUMMARY
– APPROVED & SIGNED COPY OF ISSUED PUNCHLIST
– AS-BUILT PLANS, BOQ, AND SIGNED TEST RESULTS (1 SET
ORIGINAL AND 9 SETS BLUE PRINT HARD COPY + E-FILE )
– CERTIFICATE OF COMPLETION
– WARRANTY CERTIFICATE
– ATTACHED PICTURES
FAILURE TO ISSUE SIGNED PUNCHLIST AND AS-BUILT PLAN WILL RESULT TO 90% COMPLETION ON THE PROGRESS
BILLING ONLY.
RETENTION
• FORWARD TO PRODUCTION
• REQUIREMENTS
– APPROVED “REQUEST FOR RETENTION RELEASE”
ADDITIONALS/CHANGE ORDER
• REQUIREMENTS
– GROSS BILLING STATEMENT
– BILLING COST BREAKDOWN
– SITE INSTRUCTION(OSI) AND/OR VERBAL
INSTRUCTION(CVI) ISSUED BY DEVELOPER OR
CONFIRMATION OF VERBAL INSTRUCTION SIGNED
BY DEVELOPER
– ATTACHED PICTURES
ADDITIONALS/CHAGE ORDER BILLINGS ARE SUBJECT FOR ASSESSMENT AND NEGOTIATION.