Вы находитесь на странице: 1из 6

REPORT GENERATION

GAJENDHIRAN.V
M.E-CAD/CAM
The function of the report generator is to print a human-readable

report of the results

The report includes :

a) Part name

b) Part number

c) Material code

d) Material specification

e) Planner name

and so on
The contents of the report generation include :

a) Surface identification

b) Dimensions

c) Processes

d) Tool diameter

e) Feed

f) Speed

g) Machining time,etc.,
PROCESS PLAN

LAKHSMI MACHINE WORKS LTD., COIMBATORE

PROCESS PLAN

PART NO. : 30010123 MTL. CODE : 2004 BATCH QTY. : 100

PART NAME : BRACKET MTL. SPEC. : 12Cr

PLANNED BY : DATE :

CHECKED BY : DATE :

APPROVED BY : DATE :

Opn. Surface Qty. Remarks


Description M/c name Spl.tools,jigs/fixtures Feed (mm/min.) Speed in rpm Time (min.)
No. No. produced

Rough face mill & top


10 1 Bottom rough mill & grind 1.5 & 0.3 250 & 400 0.5 & 2 100
grind
FN2V Vertical milling
&Surface grinder(S.G.)

20 2 Top mill & grind FN2V Rough face mill & 1.5 & 0.3 250 & 400
grind 100
30 3 Side mill - 4 sides
FN2V Finish face mill 0.5 300 100
40 4 Step mill
FN2V Ø16 end mill 2 & 0.3 230 100

50 5 Drill & C.bore RM63 Radial drilling Ø7 twist drill, Ø11 0.25 150 & 200
m/c c.b.cutter 100

60 6 Slot mill FN2V 2 150


Ø8H7 end mill cutter 100

70 7 Slot finish grind S.G. 0.2 900


Ø200 Al2O3 wheel 100
Aspects of process plan :

The process plan is generated automatically

The plan can be improved with a bit of “refining”

Ex. : Since TIPPS generates process sequence,the

sequence of operations does not make tool

changes or fixturing changes into account. By

simply inspecting the process plan one can see

that if operations are interchanged, tool setup

time can be eliminated


The processing time reflected in the plan does not include set-

up or tool change time

These times are system dependant i.e., if the part is being

machined on a CNC machining center, only one set-up is

required. Depending on the machine,the tool change time

may be negligible

On the other hand, in the conventional machines,set-up and

tool change time may contribute the largest portion of the

processing time