0 оценок0% нашли этот документ полезным (0 голосов)
19 просмотров11 страниц
The document summarizes a project to construct a manufacturing plant within a 67 week deadline and $5.4 million budget. It was determined that crashing the critical tasks could deliver the project in 68 weeks at best. To meet the deadline, a compromise of delivering the plant in 6 weeks late and $10,000 over budget was selected. Crashing tasks and leveling resources helped lower the resource peak from 17 to 15 resources. A penalty of $300,000 for missing the deadline poses a large risk and influenced the decision to compromise on time and budget. Recommendations include ensuring fair timelines and accepting small losses on large projects to support growth.
The document summarizes a project to construct a manufacturing plant within a 67 week deadline and $5.4 million budget. It was determined that crashing the critical tasks could deliver the project in 68 weeks at best. To meet the deadline, a compromise of delivering the plant in 6 weeks late and $10,000 over budget was selected. Crashing tasks and leveling resources helped lower the resource peak from 17 to 15 resources. A penalty of $300,000 for missing the deadline poses a large risk and influenced the decision to compromise on time and budget. Recommendations include ensuring fair timelines and accepting small losses on large projects to support growth.
The document summarizes a project to construct a manufacturing plant within a 67 week deadline and $5.4 million budget. It was determined that crashing the critical tasks could deliver the project in 68 weeks at best. To meet the deadline, a compromise of delivering the plant in 6 weeks late and $10,000 over budget was selected. Crashing tasks and leveling resources helped lower the resource peak from 17 to 15 resources. A penalty of $300,000 for missing the deadline poses a large risk and influenced the decision to compromise on time and budget. Recommendations include ensuring fair timelines and accepting small losses on large projects to support growth.
‣ To fulfil our vision, several independent tasks must be
completed, as the success or failure of this venture is embedded in the timely completion of these tasks. Success is measured against whether the construction of the plant is completed within the 67 week deadline.
‣ Microsoft Project and Microsoft Excel are employed to
quantify and juxtapose numerical values, as well as produce diagrams and charts.
‣ The analysis is concluded by citing room for improvement in
relation to subsequent affairs. OUR VISION
‣ Our company’s vision is to have the development of the manufacturing
plant delivered to our client inside the time span of 67 weeks, while staying within the $5.4 million fund granted to us to produce this assembly plant.
‣ To achieve this, we are obliged to:
‣ Decide the duration, cost and assets required for the project to be feasible.
‣ Summarise objectives and interpret the Critical Path Method (CPM).
‣ Crash and level the project duration and resources, limiting the length and adjusting asset usage of the project’s agenda.
‣ Regulate and discipline finances utilising processing software
THE PROBLEM
‣ The time allotment provided to have the project complete is 67
weeks; however, our company has discovered that this is a lacking measure of time to develop the plant.
‣ To adjust to this issue, the length of the plan must be
consolidated, the initial and final dates must be altered, and disbursement must be limited.
‣ A fine of $300,000 will be dealt to our organisation if we fail to
deliver this project within 67 weeks. This is challenging as the the critical path comprises of most of the projects’ tasks, limiting room for levelling, and ultimately the company’s reputability is at serious risk. OUR DIRECTION AND LACK OF TIME
‣ A fully crashed project will last 68 weeks, thus being delivered
1 week late at best
‣ We decided that damage control and making a compromise
was the best direction
‣ Our budget from the beginning is effectively 5.1 million
‣ We effectively break even, 0.2% over budget ‣ Client's plant is delivered 6 weeks late, $10,000 over budget CRASHING
‣ Prioritising critical path
‣ Found activities with best "weeks/$" and crash them first ‣ After 6 crashes, we have 3 critical paths TASK 6 - HISTOGRAMS
EARLY START - R/S PEAK 17
LATE START - R/S PEAK 20
LEVELLED ES - R/S PEAK 15
TASK 6
LEVELLING SUMMARY The goal was to lower the resource peak
This was achieved by using the method of splitting activities I,
G&M
This pushes more resources to the end of the project timeline
Achieving a lowered peak to 15
Increasing our RUF from 57.63% with the ES to 65.32%
An increase difference of 7.69%
THE PENALTY
‣ A large hurdle when delivering the project
‣ We are a medium sized company, reputation matters!
‣ With our penalty, the best compromise is 6 weeks late and $10k over budget
‣ Without the penalty, we can do a lot better
‣ Delivered 2 weeks late to the client
‣ $50k over budget, which is only 0.9%
THE PENALTY
‣ A relatively linear line up until a project duration of 69 weeks
CONCLUSION AND RECOMMENDATIONS
‣ Sticking with a compromise is the best course of action.
‣ In the future, more time and resources within our company should be spent to ensure a fair timeline is given for any project
‣ As the company grows, our reputation will also need to grow
‣ Small losses on a large project may be acceptable is the outcome is favourable