Академический Документы
Профессиональный Документы
Культура Документы
Presented by :
Norsyakilah Romeli
(Provisional QS, RISM, BQSM)
Dip Qs, Bsc Qs, Msc Project Mgmt,
PhD Built Environment
Main Categories:-
CONTRACTUAL
EXTRA-CONTRACTUAL OR EX-CONTRACTUAL
Other Categories:-
QUASI – CONTRACTUAL (obligation as per
according to the parties)
EX – GRATIA (moral obligation)
2
CONSTRUCTION CONTRACT CLAIMS
Those claims which arise out of the express
provisions of the contract.
7
CONSTRUCTION CONTRACT CLAIMS
Fundamental Terms
• Direct : a direct and natural consequences of a
breach of contract and does not cover any
indirect or consequential loss or damage
• Loss – Loss of money which ought to have been
received and expenditure of money which ought
not to have been expended
• Expenses : the actual disbursement
8
Ground for claim for loss and
expense
• Suspension of works
• Direction regarding disputes with neighbor's
• S.O’s instructions
• Contractor not receiving instruction on time
• Delay in executing work by others
• Suspension of Works
9
DIRECT LOSS AND/OR EXPENSE
Clause 24 in PAM
Clause 31 in CIDB
Clause 44 in PWD/JKR
Recovery of loss and/or expense by the contractor is
equivalent to damages at common law (Wright Ltd
v PH & T (Holdings) Ltd (1968)
The term used in PAM and PWD/JKR contract
reflects the various heads of claim which are
available at common law (FG Minter Ltd v Welsh
Health Tech Serv Organisation (1980)
10
CONSTRUCTION CONTRACT CLAIMS
PAM FORM
Clause 24.1 to be discussed.
12
CONSTRUCTION CONTRACT CLAIMS
PAM FORM
A claim under clause 24.1 can only arise as a direct
consequences of one of the fourteen (14) specified
matters including defaults by the employer
generally (clause 24.3 (g)).
The loss and/or expense must be have been
caused directly by the event relied on.
In Saintline v Richardson, Westgarth & Co (1940),
Atkinson, J. stated that “direct damage is that
which flows directly from the breach without
intervening cause and independently of special
circumstance while indirect damages does not so
flow”.
13
CONSTRUCTION CONTRACT CLAIMS
PAM FORM
14
CONSTRUCTION CONTRACT CLAIMS
PWD FORM
• This provision is under clause 44; Claim for Loss and
Expense. The events for compensation are as stated under
sub-clause 43.1(c),(d),(e),(f),(i).
15
HEADS OF CLAIMS
16
CONSTRUCTION CONTRACT CLAIMS
HEADS OF CLAIMS
18
The Actual Cost Approach
This approach simply identify the cost of the actual head
office overheads affected by the delay. Only the additional
cost actually incurred as a result of the delay on the
project are claimed.
global claim
19
Case : Global Claim
In Mid-Glamorgan Country Council v J Devonald Williams
& Partner [1992] 8 Const LJ 61, after considering Crosby
(J) & Son v Portland UDC [1967], Merton London
Borough Council v Stanley Hugh Leach Ltd [1985] and
Wharf Properties Ltd v Eric Cumine & Associaties (No 2)
[1991] the judge conclude that:
20
Case : global claim (cont’d)
Use of formula
22
In recent years, some of the more fundamental criticisms
levelled at the Hudson formula have been that:
It assumes the profit budgeted for by the contractor in his prices
was in fact capable of being earned by him elsewhere had he
been free to leave the delayed contract at the proper time.
At best it requires adjustment to be made for the various factors for
which recovery is not permitted, e.g. the contractor's own
inefficiency.
It ignores the contractor's duty to make realistic attempts to deploy
his resources elsewhere during any period of delay.
The value of the final account may well exceed the contract sum.
Thus, any proper valuation for variations must include an element
of reimbursement for overheads and profit and hence there is risk
of duplicating recovery.
The use of the formula as it stands results in profit being added to
the profit already in the contract sum so that, at the very least, the
Hudson formula as first set out should read `Contract sum less
overheads and profit' rather than `Contract sum'.
The formula can also produce under-recovery where inflation
during the period of delay increases the overhead costs envisaged
at the time of tender. 23
CONSTRUCTION CONTRACT CLAIMS
1. Head office overheads and profits
Wraight Ltd v PHT (Holdings) Ltd (1968)
The loss of establishment charges i.e. head office
overheads and profit were considered as direct
losses.
Where a project is delayed due to default of the
employer, the contractor’s is not earning anything
from the contract during the delayed period and thus
entitled to claim damages arising from being
prevented from earning elsewhere.
Common formulae used:
Hudson formula
Emden
Eichleay
24
CONSTRUCTION CONTRACT CLAIMS
HUDSON FORMULA
First so called because it appears in the 10th edition of
Hudson’s Building And Engineering Contracts (p.599), the
formula has since been much critised. The formula was
expressed as:
This formula has the advantage of using the Contractor’s actual head office/ profit percentage
rather than the one contained in the Contract and has received judicial support in a number of
cases, notably Whittal Builders Co Ltd v Chester-le-Street District Council [1985] and in J F
Finnegan Ltd v Sheffield City Council [1988] where Sir William Stabb QC, said:
“However, I confess that I consider the plantiffs’ methof of calculation of the overheads on the basis
of a notional contract valued by uplifting the value of the direct cost by the constant of 3.51 as
being to speculative and I infinitely prefer the Hudson (‘Emden’ was intended*) formula which, in
my judgement, is the right one to apply in the case, this is to say, overhead and profit percentage
based upon a fair annual average, multiplied by the contract sum and the period of delay in weeks,
divided by the contract period.
*the percantage based upon actual head office costs is Emden’s and not Hudson’s formula.
26
2. Site overheads
These are direct expenses. These claims are
allowed on time variable components, for
instance:-
27
CONSTRUCTION CONTRACT CLAIMS
3. Idle plant and equipment
on site
a) Evidence of employment elsewhere, if no
delay, is necessary.
b) Absence of the above, assessment can be
made on the following basis:
Depreciation during idling period.
Financing cost of machine.
Cost of maintenance.
Wages thrown away.
28
CONSTRUCTION CONTRACT CLAIMS
Example of calculation
Depreciation (example)
Cost of machine : RM 100,000
Interest on purchase : 10% p.a
Cost of maintenance : negligible (not in use)
Wages wasted : 1 operator @ RM 80/day
Idling period : 30 days
Assuming operator must continue and on standby:
Depreciation : say 20% per annum (if working)
or 15% per annum (when idle)
= 0.15 x RM 100,000
= RM 15,000 per annum
Depreciation over 30 days = 30 x RM 15,000 = RM 1,233
365
• Interest (financial cost) = 0.10 x RM 100,000 x 30
365
= RM 822.00
• Cost of maintenance = negligible
• Wages thrown away = RM 80 + insurance, say RM 82/day
~ for 30 days = 30 x RM83 = RM 2, 460
• Total claim = RM 1,233 + RM 822 + RM 2, 460
= RM 4,515
29
5. Interest and financial charges
(cases)
There is now no doubt that a contractor is entitle to relief, by way of loss/or
expense, for the costing of financing. In the Malaysian case of Newacres
Sdn Bhd v Sri Alam Sdn Bhd [2000] 2 MLJ 353, Chong Siew Fai CJ of the
federal Court recognised a party’s right to interest. He held that “it is only
fair that interest be awarded against the person who wrongfully deprives
another from the use of the latter’s money”. Mere replacement of the
money after more than a decade is insufficient compensation. As such, the
landowner should be compensated by an award of interest for the loss
thereby occasioned to them.
This principle is further enunciated in the English case of F.G Minter Ltd v
Welsh Health Technical Services Organisation [1980] 13 BLR 1
30
When ascertaining the cost of financing, the following should be taken into
account:
• The appropriate rate of interest is the actually paid by the Contractor provided it
is not unreasonable. In the event of the Contarctor paying well above or well
below prevailing market rates it seems from Tate & Lyle v GLC [1983] 1 CLD-08-07,
that appropriate rates are those “at which (Contractors) in general borrow
money”.
• Where the Contractor is self-financed or financed from within its corporate group
the appropriate rate of interest is that earned by the Contractor (or its group) on
monies it has placed on deposit;
• Account should be taken of actual negative cash flows by way of primary expense,
i.e. expenses are incurred progressively.
31
6. Cost of preparing the claim
Right to claim
The question often asked is whether the cost is recoverable as part of the
claim ascertainment and payment. There is no definitive “yes” or “no”
answer to question. Few examples in practice can be identified where cost
of preparing a claim have been certified and paid.
There is however, one reported case where court hade to decide whether a
claims consultant’s fees should be reimbursed to a successful claimant. The
case being James Longley and Co Ltd v South West Regional Health
Authority [1983] 25 BLR 56.
32
6. Cost of preparing the claim
(cont’d)
It would seem that when approaching the matter of matter of recovery of the
costs of preparing a claim, a number of questions should be addressed:
• It would seem unlikely that in the absence of express terms in the contract
which given an entitlement to payment, the cost of producing documents in
support of a claim as required by the conditions of contract will be covered. In
providing this information the contractor of sub-contractor is merely complying
with the requireements of the contract.
• Where the condition of the contract require the architect or engineer having
received notice and details from the contractor or sub-contractor to ascertain
loss and expense, any failure to so ascertain will constitute a breach of contract.
33
Cost of preparing the claim (cont’d)
Vincent Powell Smith in an article appearing in Contract Journal dated 30
July 1992 had this to say on the matter with regard to claims under JCT
80:
“if the contractor invokes Clause 26 and does what is required, the
architect is under a duty to ascertain to instruct the quantity surveyor to
ascertain whether loss or expense is being inccured and its amount. This
follows from the wording of Clause 26.1 which uses the word “shall” and
which thus imposes a duty on the architect, provided that the architect
has formed a prior opinion that the contractor has been or is likely to be
involved in direct loss and/or expense as a result of the specified event(s)
and which is not recoverable under any other provisions of the contract.
34
INTEREST CLAIM
ON DETENTION
OF DEBT
35
CONSTRUCTION CONTRACT CLAIMS
It is established in common law that interest is
recoverable for the late payment of debt as
special damages but not under general
damages.
36
CONSTRUCTION CONTRACT CLAIMS
A. MONEY DUE AND NOT PAID UP TO THE
COMMENCEMENT OF ARBITRATION/
COURT
Section 3 of IEM rules “…the date when the request of
arbitration is received by the respondent”]. This agree in
principle with common law in Nea Agrex SA v Baltic Shipping
Co Ltd & Anor (1975).
Although common law is against the granting of interest on late
payment of debts under general damages, interest may still be
payable, where appropriate, as special damages occurred as
a direct loss and/or expense (Wadsworth v Lydell [1981] CH).
Financial charges qualify as special damages. Interest awarded
shall only be simple interest and not interest on interest i.e.
compound interest.
37
CONSTRUCTION CONTRACT CLAIMS
B. MONEY DUE BUT PAID BEFORE
COMMENCEMENT OF ARBITRATION/COURT
38
CONSTRUCTION CONTRACT CLAIMS
The Medina Princess (1962)
Facts
The plaintiffs were seamen of the Medina
Princess who claimed for unpaid wages.
No defence was made and the defendants
paid the wages.
The plaintiffs then submitted claim for interest
upon the sums claimed from the date when the
sums became due to the date of payments.
Held
Interest cannot be paid on sums which have
already been paid or which have not been
awarded by the court / arbitrator.
39
CONSTRUCTION CONTRACT CLAIMS
CONCLUSION
40
CONSTRUCTION CONTRACT CLAIMS
41
CONSTRUCTION CONTRACT CLAIMS