Академический Документы
Профессиональный Документы
Культура Документы
By:
ADJUNCT PROFESSOR
DATO Sr ZULKEFLI MOHD ZAIN
DIMP, FRISM, MRICS, CQS
INTRODUCTION
DEFECT FORENSIC SCIENCE is the application of engineering
sciences for the investigation of failures or defects problems.
From a legal perspective, it is a mission to find facts and learn the most
probable causes of a failure.
INTRODUCTION (Cont’d)
THE INVESTIGATION will be carry out by Forensic
Engineer or Specialist Engineer. They will investigate what
is the causes of the defects or failure.
https://www.iaea.org/newscenter/multimedia/videos/non-destructive-testing-
technique
GENERAL INVESTIGATION
PROCESS
1. Defining objective of the investigation.
2. Collecting background information and documents.
3. Site visit.
4. Forming an investigation plan and project team.
5. Formulating initial failure hypotheses.
6. Reviewing comprehensive documents.
7. Field testing and sample collection.
8. Analysis of structure and laboratory testing.
9. Revising failure hypotheses.
10. Final conclusion.
11. Report.
SHARING OF EXPERIENCE
SUBANG OLIVES RESIDENCE
SUBANG OLIVES RESIDENCE
Subang Olives is a classic condominium situated in strategic location.
Its central position facilitates easy and efficient access to first-rate
amenities, facilities and infrastructure such as highways.
The subject property ‘Subang Olives Residences’ located in Jalan SS16/1, Subang
Jaya, Selangor. North view is facing Federal Highway and KTM Railway track while
south view are Subang Jaya business district.
CASE STUDY
We will discuss 3 major defects issue related to Subang
Olive Residence.
1. Severe Water Ponding at basement 2 and 3
2. Reinforced concrete slab crack at Carpark Floor
3. Crack line appear at external facade wall.
INVESTIGATION OF CAUSES
1.0 WATER PONDING – The existing basement floor slab at
Basement 2 and 3 is not functioning well and cause severe water
ponding.
Layout Plan shows the flow and the gradients of Invert Level constructed for Dewatering
System.
ANALYSIS & RECTIFICATION WORK
RECTIFICATION WORK PROCESS
WATER PONDING – Subsoil Piping Installation method
for dewatering system consist the following steps:
1. Saw cut by cutter or hacking by using breakers through the
existing Basement slab at 600mm wide
RECTIFICATION WORK PROCESS (Cont’d)
2. Cut the existing rc slab steel bars and to replace the precut
steel bars using A7 wire mesh upon completion of the
subsoil pipes installation work
RECTIFICATION WORK PROCESS (Cont’d)
3. Dig by using labour to remove the existing hardcore stones
and soil at 600-800mm deep depending on the flow
gradient from the existing rc slab.
RECTIFICATION WORK PROCESS (Cont’d)
4. Construct new brickwall sumps with reinforced concrete
base and to install precast cover as per detailed sketch
drawings.
RECTIFICATION WORK PROCESS (Cont’d)
5. Core by using electrical coring machine on the existing rc
sump to received 150mm dia. pvc perforated sub soil pipes.
RECTIFICATION WORK PROCESS
(Cont’d)
6. Lay 200mm thick size 20mm dia. Aggregate stones to the
base of pvc perforated pipes
RECTIFICATION WORK PROCESS (Cont’d)
7. Install 150mm dia. pvc subsoil pipes on top of the 200mm
thick aggregates, the subsoil pipes are to be laid with
natural fall gradient. The subsoil pipes to be covered with
one layer of geotextile fabric to prevent soil from entering
into the subsoil pipes and subsequently block the water
passage.
RECTIFICATION WORK PROCESS (Cont’d)
8. Lay a final layer of the 20mm dia. aggregates stones on top
of the geotextile fabric until the soffit of the rc slab level
RECTIFICATION WORK PROCESS (Cont’d)
9. Install additional layer of brc A7 wiremesh to replace the
precut rc slab bars.
RECTIFICATION WORK PROCESS (Cont’d)
10. The subsoil pipes is able to alleviate or reduce ground water
pressure. It helps to channel and discharge the underground
water into the existing drainage sump.
RECTIFICATION WORK PROCESS (Cont’d)
11. Cast and make good the prehacked rc slab with Grade 30
concrete and finish the concrete surface with steel trowel
and floor hardener.
RECTIFICATION WORK PROCESS (Cont’d)
REINFORCED CONCRETE SLAB CRACK– Method use in
overcoming this defect.
1. Typical RC Slab Crack lines repairing work
2. Steel Plates Installation into RC Slab
ANALYSIS & RECTIFICATION WORK
2.0 REINFORCED CONCRETE SLAB CRACK – From the visual inspection carried by
Forensic Engineer/ Specialist Engineer, crack defect were found to severed
Location of Repair to Extensive Surface Crack on Top of Concrete Slab (Level G & Level B1)
Crack pattern
RECTIFICATION WORK PROCESS (Cont’d)
• The following process were applied to overcome the crack issue.
1. To saw cut 20mm deep x 20mm wide (i.e. 10mm on both sides of
the rc slab cracklines) by using concrete cutter.
RECTIFICATION WORK PROCESS (Cont’d)
2. Hack by using electrical breakers along the precut cracks to
form 20mm x 20mm U grooves to receive epoxy resin grout
RECTIFICATION WORK PROCESS (Cont’d)
3. Clean and remove loose materials, dust and laitance in
prehacked grooves.
4. Grout to fill cracklines by using Sikadur 52 epoxy resin
grout.
RECTIFICATION WORK PROCESS (Cont’d)
5. Mix the 3 components of the StoPox EPG Epoxy resin grout
which comprises of epoxy resin grout, epoxy hardener and
silica sand.
6. Pour by gravity pouring method the premixed StoPox epoxy
resin grout into prehacked crack lines.
RECTIFICATION WORK PROCESS (Cont’d)
7. Smooth the epoxy grout surface by using steel trowel before
gel time.
RECTIFICATION WORK PROCESS (Cont’d)
8. The finish level of the epoxy resin grout surface shall be the
same level with the existing rc floor slab.
9. Allow the epoxy resin grout to set at least 6 hours and touch
up paint to affected carpark line after grouting work.
RECTIFICATION WORK PROCESS (Cont’d)
The installation of steel plate into RC slab:
1. To saw cut and hack to form 10mm deep x 50mm wide channel by
using diamond concrete cutter and pneumatic electrical breakers
respectively as per locations specified in the layout drawing. The
steel plates at driveway shall be 3 metres in length and at 500mm
centre to centre. The length of the steel plates at carpark in
between the columns shall varies but to be extended 300mm after
the crack lines and to be at 500mm centre to centre.
RECTIFICATION WORK PROCESS (Cont’d)
2. Clean and remove loose materials, dust and laitance in
prehacked groove/channels by using electrical blower or
vacuum cleaner.
3. Cut 38mm wide x 3mm thick steel plates to size
RECTIFICATION WORK PROCESS (Cont’d)
4. Mix the 3 components of the StoPox EPG Epoxy resin grout which
comprises of epoxy resin grout, epoxy hardener and silica sand.
5. Pour a thin layer of 3mm thick of the premixed epoxy resin grout
into the prehacked channel, install 3mm thick x 38mm wide steel
plates and top up the epoxy resin grout until the rc slab surface,
the total thickness of steel plates and epoxy resin grout shall be
10mm thick
RECTIFICATION WORK PROCESS (Cont’d)
6. Smooth the epoxy grout surface by using steel trowel before gel
time.
RECTIFICATION WORK PROCESS
(Cont’d)
7. The finish level of the epoxy resin grout shall be the same level
with the existing RC Floor Slab
8. Allow the epoxy resin grout to set at least 6 hours.
9. Touch up paint to affected carpark line after grouting work.
ANALYSIS & RECTIFICATION WORK
CRACK LINE PROBLEM
1. Hairline cracks – cracks below 2mm width
2. Cracks within 2 -4 mm width
3. Distinct cracks – cracks within 6mm to 10mm width