ART PROJECT DATA ENTRY

Phase - 1

States Covered :

 Delhi
 Maharashtra
 Andhra Pradesh
 Karnataka
State Summaries

Delhi Mahrshtra Andhra Karnataka Totals

Volumes 3,500 17,544 16,650 7,700 45,394

Teams 3 6 4 4 17

Operator 6 22 21 10 59

Days 22-25 31-40 30-37 30-34 40

Start Dt 01-Aug-07 01-Aug-07 01-Aug-07 01-Aug-07 01-Aug-07

End Dt 25-Aug-07 08-Sep-07 06-Sep-07 05-Sep-07 08-Sep-07


New Delhi – Data Entry Plan
S.N Reqd
o Data-Entry Location City Distance Records Team Qty Per Pax Per Day Workday Days Start Dt End Dt

1 RML Hospital DELHI 1,400 A 2 40 80 17.5 20 2-Aug-07 22-Aug-07

1A RML Hospital DELHI 200 C 1 40 40 5 7 16-Aug-07 22-Aug-07

2 AIIMS Hospital DELHI 750 B 3 40 120 6.3 13 1-Aug-07 13-Aug-07

3 LNJP Hospital DELHI 725 B 3 40 120 6 9 14-Aug-07 23-Aug-07

4 LR Inst of TB Resp Disease DELHI 80 C 1 40 40 2 2 3-Aug-07 4-Aug-07

5 DDU Hospital DELHI 100 C 1 40 40 2.5 3 5-Aug-07 7-Aug-07

6 GTB Hospital DELHI 120 C 1 40 40 3 4 8-Aug-07 12-Aug-07

7 Lady Hardinge Med College DELHI 20 C 1 40 40 0.5 1 13-Aug-07 13-Aug-07

8 Safderjung Hospital DELHI 25 C 1 40 40 0.6 1 14-Aug-07 14-Aug-07

Total : 3,420
Maharashtra – Data Entry Plan
S. Reqd
No Data-Entry Location City Distnc Qty Team Qty Per Pax Per Day Workday Days Start Dt End Dt

1 LTMG Hospital Sion MUMBAI 900 B 3 40 120 7.5 10 1-Aug-07 10-Aug-07

2 KEM HOspital Parel MUMBAI 1,270 B 3 40 120 10.6 13 11-Aug-07 24-Aug-07

3 Nair Hospital Mumbai Central MUMBAI 750 B 3 40 120 6.3 9 25-Aug-07 3-Sep-07

4 JJ Hospital, Byculla MUMBAI 4,000 A 4 40 160 25 30 1-Aug-07 31-Aug-07


5 Sassoon Hospital, Station Rd PUNE 2,650 C 3 40 120 22.1 26 3-Aug-07 28-Aug-07
6 Govt Medical College Hospital NAGPUR 16 hrs 1,800 D 2 40 80 22.5 26 1-Aug-07 26-Aug-07
7 Govt Hospital, Sangli PUNE 6 hrs 2,300 E 4 40 160 14.4 18 2-Aug-07 19-Aug-07
8 Govt Medical College, Aurangabad PUNE 4 hrs 560 E 4 40 160 3.5 6 20-Aug-07 26-Aug-07
9 Govt Medical College, Ambejogai PUNE 6 hrs 650 E 4 40 160 4.1 6 27-Aug-07 1-Sep-07
9A Govt Medical College, Ambejogai PUNE 6 hrs 250 C 3 40 120 2.1 2 1-Sep-07 2-Sep-07
10 Govt Medical College, Dhule MUMBAI 6 hrs 420 A 4 40 160 2.6 4 1-Sep-07 4-Sep-07
11 Govt Medical College, Yavatamal NAGPUR 3 hrs 340 D 2 40 80 4.3 3 2-Sep-07 4-Sep-07
12 Govt Medical College, Akola NAGPUR 4 hrs 250 D 2 40 80 3.1 6 27-Aug-07 1-Sep-07
13 Ntl AIDS Res Inst,MIDC Bhosari PUNE 1 hr 175 C 3 40 120 1.5 3 29-Aug-07 31-Aug-07

Total : 16,315
Andhra Pradesh – Data Entry Plan
Reqd
S.No Data-Entry Location City Distnc Qty Team Qty Per Pax Per Day Workday Days Start Dt End Dt

1 Osmania Hospital H'BAD 2,200 A 4 40 160 13.8 14 1-Aug-07 14-Aug-07

2 King George Hospital, Vizag VIZAG 1,560 B 3 40 120 13 16 2-Aug-07 18-Aug-07

3 Guntur Gen Hospital, Guntur VIJAYWD 2,300 C 4 40 160 14.4 17 3-Aug-07 19-Aug-07

4 Gandhi Gen Hospital, Secbad H'BAD 360 A 4 40 160 2.3 4 16-Aug-07 20-Aug-07
5 MGM Hospital, Warangal H'BAD 360 A 4 40 160 2.3 4 21-Aug-07 25-Aug-07
6 Govt Dist HQ Hosp,Karimngr H'BAD 200 A 4 40 160 1.3 3 26-Aug-07 28-Aug-07
7 Govt Chest Hosp, Erragadda VIZAG 215 B 3 40 120 1.8 3 28-Aug-07 31-Aug-07
8 Govt General Hosp, Ananthapur TIRUPATI 700 D 2 40 80 8.8 10 4-Aug-07 14-Aug-07
9 Govt General Hosp, Kadapa TIRUPATI 340 D 2 40 80 4.3 6 16-Aug-07 21-Aug-07
10 Govt General Hosp, Tirupati TIRUPATI 500 D 2 40 80 6.3 8 22-Aug-07 31-Aug-07
11 Govt General Hosp, Kakinada VIZAG 760 B 3 40 120 6.3 8 19-Aug-07 27-Aug-07
12 Govt General Hosp, Vijaywada VIJAYWD 800 C 4 40 160 5 6 20-Aug-07 25-Aug-07

12A Govt General Hosp, Vijaywada VIJAYWD 160 A 2 40 80 2 3 29-Aug-07 31-Aug-07


13 Govt Dist HQ Hosp, Ongole VIJAYWD 1,000 C 4 40 160 6.3 8 26-Aug-07 2-Sep-07

Total : 11,455
Karnataka – Data Entry Plan
S.N Distanc Tea Per Reqd
o Data-Entry Location City e Records m Qty Pax Per Day Workday Days Start Dt End Dt

1 Curzon Hospital, Shivaji Ngr BLORE 1,900 A 2 40 80 23.8 26 1-Aug-07 26-Aug-07

2 Krntk Inst of Med Sciences HUBLI 1,400 B 3 40 120 11.7 13 2-Aug-07 14-Aug-07

3 K R Hospital MYSORE 840 C 2 40 80 10.5 12 3-Aug-07 14-Aug-07

4 Chigateri Dist Hospital, Devangere HUBLI 470 B 3 40 120 3.9 5 16-Aug-07 20-Aug-07
5 Dist Hospital, Belgaum HUBLI 470 B 3 40 120 3.9 5 21-Aug-07 25-Aug-07
6 Dist Hospital, Bijapur RAICHUR 370 D 1 40 40 9.3 11 4-Aug-07 14-Aug-07
7 Dist Hospital, Mangalore MYSORE 500 C 2 40 80 6.3 8 16-Aug-07 24-Aug-07
8 Dist Hospital, Kolar BLORE 180 A 2 40 80 2.3 4 27-Aug-07 30-Aug-07
9 Dist Hospital, Raichur RAICHUR 170 D 1 40 40 4.3 5 29-Aug-07 2-Sep-07
10 Vijayngr Inst of Med Scn, Bellary RAICHUR 500 D 1 40 40 12.5 13 16-Aug-07 28-Aug-07
11 Dist Hospital, Gulbarga RAICHUR 250 C 2 40 80 3.1 3 26-Aug-07 30-Aug-07
12 Dist Hospital, Bagalkot HUBLI 375 B 3 40 120 3.1 5 26-Aug-07 30-Aug-07
13 IG Inst of Child Health BLORE 200 A 2 40 80 2.5 3 31-Aug-07 2-Sep-07

Total : 7,625
Network Configuration
Steps to Ensure Data Quality :

 Each team will be headed by a Senior Data Entry


Operator who will be responsible for overall team
management
 Data will be checked on sample basis at the end of
each day for each team member
 In addition, the team leader will do random checks
and will be available for resolving any queries or
data-issues
 After completion of data entry for each location,
results of these checks will be tabulated & shared.
Steps to Ensure Data Confidentiality :

 All data entry operators to carry ID cards


 Team leader to carry proper authorization letter
 All data transfer to client via data-cable only
 Other USB drives & removable media disabled
 All data-entry wiped off from local drives daily
 No paper records/ files to be taken out of area
 Checklist for same to be filled up and monitored by
team leader and documented
Why - Turnaround Systems ?

 More than 15 yrs old Data Processing Firm


 Based in New Delhi for instant feedback
 Offices in A.P. with adequate local resources
 Trained and Experienced Data Operators
 Knowledge of banking sector confidentiality
norms
 Adherence to Information Security guidelines
 Minimum ramp-up time for project start
 Cost-efficient
Infrastructure & Resources
 Multi-locational offices with overall 5,000 sqft
of area dedicated to client servicing
 Trained manpower with efficient supervisory
staff
 Adequate field experience having already
completed similar project in 2007
 End-to-end solutions for client satisfaction
Clientele
 Financial Sector
Citibank N.A., TCS, e-Serve International
 Social Sector
ACN-ORG Marg, PSI, Clinton Foundation
 IT/ ES Sector
Indiamart, Majestic IT, Clickindia Infomedia
 Market Research Sector
Vendor2web, Delhi-Help, Bizexchange.in
Thank you !!!