Академический Документы
Профессиональный Документы
Культура Документы
Debopam Roy
Changes
CONTRACT CHANGE PROCEDURE
• Constructive change
– A change that is not acknowledged by the owner as such
when it occurs but which, nonetheless, is a change
– Owner takes a stand that, what the contractor was ordered to
do, was not a change, but required by the original contract
– In such cases contractor is required to proceed according to
owner’s instructions but is free to assert his claim to a change
– If contractor is correct:
• courts will deem that a constructive change has occurred
• contractor be awarded incurred costs plus a reasonable
profit
SPECIFICS IN CHANGES CLAUSE
2 months
4 months early
14 months faster work 4 months faster
Case 2
delay work
Complete
DELAY IN EARLY COMPLETION
SITUATION
• Many owner will take the stand in the second case that, since the contractor
finished the contract early, there was no damage caused by the delay
• Owner’s consider that the contractor’s bid should be based on taking the
full allowable time for contract completion
• The weakness of owner’s view is that the contractor accepted all risk of
performance of the contract and, in the absence of an owner-caused delay,
would be liable for all extra-time related costs if the contract was not
finished on time as well as liquidated damages
• Therefore the contractor should be entitled to save costs by finishing the
work earlier than required by contract, if able to do so
• The owner causing a 4 month delay is liable for the resulting extra costs to
the contractor even though the contractor finishes the contract work early
CAUSES FOR DELAY AND SUSPENSIONS
OF WORK
• Defective specifications
– Result from the application of the Spearin Doctrine
– When specs and drawings contain errors, the delay often
result due to:
• Attempting to comply with the error
• Waiting for the errors to be corrected and revised specs to be issued
• Site availability problems
– Site availability at the time of issue of NTP
– Unless stated in contract, contractor is entitled to full use of
site at the time of NTP
– Owners failure to provide reasonable means of access to
the work or interruption of access previously provided
CAUSES FOR DELAY AND SUSPENSIONS
OF WORK
• Changing and Differing site conditions
– Changes directed by the owner
– Changes because of problems associated with DSC’s
– The requirement to perform added work can cause a delay
• Constructive notice
– If an act of god shuts down the work or the owner issues a
written directive to suspend all work, the owner has
constructive notice of delay
– Constructive notice means, that even though not
specifically notified formally, the owner knows that the
work is being delayed
– But still, the contractor should always give prompt written
notice of delay to the owner
LIQUIDATED DAMAGES
• Bonus/Penalty clauses
– Liquidated damages provisions can’t be applied in reverse
if contractor finishes early
– There need not be benefits from every day’s early
completion because owner may not have planned to occupy
in the event of early delivery or due to other reasons as well
– Occasionally bonus/penalty clause provides monetary
benefit for early completion
– Daily rate for early completion is usually less than the rate
for late completion
– Bonus/Penalty clauses - more commonly found in private
sector contracts
FORCE MAJEURE
• When dispute over extensions arise and lead to court cases, the
first problem is that of allocating delays to each party
• Excusable delays
– Delays that are not fault of either the owner or contractor
– If they result in project duration being extended, contractor
is entitled to time extension only
• Acts of god, war, riot, etc
• First principle
– Owner cannot properly assess liquidated damages for
periods of time when he was concurrently delaying the
project
• Second principle
– A contractor cannot be properly paid delay damages for
periods of time when the contractor was concurrently
delaying completion
• Third principle
– To determine the exclusive effect of any one class of delays
on overall project completion
PRELIMINARY POINTS AND DEFINITIONS
30 Months
Time Extension
Extended Completion
Date
6 months time
extension
Completion
6 months accelerated
12 months normal work 6 months delay work
Case 2
6 months early
6 months accelerated
12 months normal work work
Case 3 6 months early
Acceleration directive
A CONSTRUCTIVE ACCELERATION
EXAMPLE
• Case 1 – Delay with time extension
– The contractor is delayed after 12 months for 6 months and
is entitled to an extension of time
– The owner promptly issues extension
– Having been granted the time extension, the contractor
continues with normal pace and completes the contract in
30 months
– No acceleration has occurred
– If the 6 months delay was compensable also, the contractor
would be entitled to monetary damages
A CONSTRUCTIVE ACCELERATION
EXAMPLE
• Case 2 – Delay with no time extension
– The owner denies or refuses to act on the contractor’s claim
for a six month extension
– Therefore, the contractor works at an accelerated pace for
the next 6 months (at added expense) and completes the
contract in 24 months
– The contractor also finishes the project 6 months earlier
than the date to which the completion should have been
extended
– This is a classic case of constructive acceleration
A CONSTRUCTIVE ACCELERATION
EXAMPLE
• Case 3 – Accelerated performance without delay
– After 12 months, even though there is no delay, the owner
issues an acceleration directive to the contractor
– The contractor works at an accelerated pace for the next 6
months and finishes the project in 18 months as according
to the directive
– Contractor is entitled to be paid for the cost of acceleration
effort
– If the delay is also compensable, the contractor is also
entitled to recover the extra time related costs
A CONSTRUCTIVE ACCELERATION
EXAMPLE
– It is not necessary in the constructive acceleration situation
to finish the contract by the original completion date as
depicted by case 2
– Consider Figure 2
30 Months
24 Months
NTP Extended Completion
Original Completion Date Date
6 months time
extension
Actual Completion
3 months
early
Although the contract work is not finished until three months after the
original contract completion date, the contractor finishes 3 months earlier
than the date to which the contract should have been extended
This is also a valid constructive acceleration situation and the contractor is
entitled to acceleration costs
PROVING CONSTRUCTIVE
ACCELERATION
• Entitlement to time extension
– The contractor must prove that performance was delayed
by some event or condition for which the contract promises
that time extension will be granted
– A properly documented claim for time extension must have
been properly submitted to the owner after the event giving
rise to the claim
• Failure of owner to issue extension of time
– The owner must not have issued a time extension
– If time extension was issued, the owner must have failed to
issue it within reasonable period of time
PROVING CONSTRUCTIVE
ACCELERATION
• Proof of extra costs
– The contractor must prove that extra costs were incurred in attempting
to finish the project by the unextended completion date
• Completion before date to which contract should have been extended
– The actual completion date need not necessarily be as early as the
original completion date as long as it is earlier than the date to which
the contract should have been extended
• Effect of an owner’s directive to accelerate
– The contractor does not have to have been directed by the owner to
meet the original date in order to have a valid case
– If it can be proved, the case becomes stronger as the owner not only
refuses to time extension for a valid claim but also compounds the
breach by pressuring the contractor to complete the contract by the
original completion time
CONTRACTOR’S PROPER CONTRACTUAL
PROCEDURE
• First, promptly file a properly supported claim for an extension
of time for a definite number of days as soon as possible
• Second, if a change order granting the time extension is not
received within a reasonable period of time, the contractor
should protest in writing and advice the owner in writing that
the operations are being accelerated
• Third, the owner should be advised in writing the details of the
acceleration effort and the contractor’s expectation for the
additional payments. The contractor must then ensure that the
contract is completed within the date to which the contract
should have been extended
• Finally, the contractor must carefully document all acceleration
costs actually incurred to be able to prove conclusively
DOCUMENTATION