GATE PASS FOR POWER RECEIVING (VT4E)

Test Procedure (04/01~5/31) DC/UPS (05/14~5/29) FMS System (06/18~06/30)


● 500kV power receiving ● Temp EDG 설치 (Panel 포함) ● FMS Function & Alarm test
Note
● MV & LV SWGR ● UPS Function test
● GCB & IPB Air Pressurize unit ● Battery Charger Function test 미착수 (0)
● GSU TR & UAT TR ● Battery Discharge/Recharge test
Tariff Meter System (06/19~06/21) 진행 중(0)
● Fault Monitoring System ● Main DB & Local panel 가압
● SCADA system ● Tariff Meter Sealing 완료(60)
● 500 KV CT, PT (VMI) test 지연 (0)
● Step touch up voltage test Transmission (05/28~06/01)
● Primary injection test ● Gantry Tower & Overhead line
(Total=60,
Overall Interlock (06/25~06/27)
● Overall interlock test
● Protection relay test
Inspection with EVN
● Interlock & tripping test
완료율 100%)
● DCS (Electrical) test etc.

Protection Relay for TRs (05/28~06/06)


GSU TR & UA TR (04/10~04/25) ● Internal Wiring Check HVAC & Fire Fighting system
● CT & VT test ● GSUT Main & Backup (05/01~06/30)
● Secondary injection test ● UAT A Main & Backup ● HVAC (Temp A/C if permanent
● Primary injection test ● UAT B Main & Backup not ready
● Cooling Fans Auto operation test ● Overall ● Fire Fighting operation test
● Ground continuity test ● Line Protection Main & Backup
● Signals end to end test
● IR test Primary Injection Test (06/28~06/29) Power Receiving
● Stability Test
RTCC (06/07~06/11) ● Final Site inspection with EVN
● RTCC panel Function Test Power Receiving (7/17)
MV SWGR (05/02~05/24)
● CT & PT Test SCADA (06/25~06/29)
● VCB Test Ground Test (06/11~06/15)
● Meter & Transducer Test ● End to End communication test with
● Protection Relay Test ● Grounding Test (Step & Touch Up) EVN
● Secondary Injection Test
● Primary Injection Test
● Bus Bar Test IPB & GCB (06/01~06/15) Safety (07/01~07/05)
● IPB Test
LV SWGR (05/08~06/09) ● GCB Function Test ● Safety Sign & LOTO
● CT & PT Test
● ACB Test
● Meter & Transducer Test
● Protection Relay & EOCR Test DCS (06/11~06/25)
● Secondary Injection Test ● DCS Parameter Setting
● Mold TR & Dry TR Test ● DCS interlock & trip test
● Bus Bar Test