Вы находитесь на странице: 1из 40

Design and drawing of RC

Structures
CV61

Dr. G.S.Suresh
Civil Engineering Department
The National Institute of Engineering
Mysore-570 008
Email: gss_nie@yahoo.com
Mob: 9342188467

1
WATER TANKS

2
Learning out Come
• REVIEW
• DESIGN OF CIRCULAR WATER TANK
RESTING ON GROUND WITH RIGID
BASE

3
• When the joints at base are flexible,
hydrostatic pressure induces
maximum increase in diameter at base
and no increase in diameter at top
• When the joint at base is rigid, the base
does not move

4
Tank with flexible base

Tank with rigid base

5
Design of Circular Tanks resting on
ground with Rigid base

6
• Due to fixity at base of wall, the upper
part of the wall will have hoop tension
and lower part bend like cantilever.
• For shallow tanks with large diameter, hoop
stresses are very small and the wall act more
like cantilever
• For deep tanks of small diameter the
cantilever action due to fixity at the base is
small and the hoop action is predominant

7
• The exact analysis of the tank to
determine the portion of wall in which
hoop tension is predominant and the
other portion in which cantilever
action is predominant, is difficult
• Simplified methods of analysis are
1. Reissner’s method
2. Carpenter’s simplified method
3. Approximate method
4. IS code method
8
IS code method
• Tables 9,10 and 11 of IS 3370 part IV
gives coefficients for computing hoop
tension, moment and shear for various
values of H2/Dt
• Hoop tension, moment and shear is
computed as
T= coefficient ( wHD/2)
M= coefficient (wH3)
V= coefficient (wH2)
9
• Thickness of wall required is computed
from BM consideration
M
d
Qb
where,
Q= ½ cbcjk
j=1-(k/3)
m cbc
k
m cbc   st
b = 1000mm
10
IS code method
• Over all thickness is then computed as
t = d+cover.
• Area of reinforcement in the form of
vertical bars on water face is computed
as A  M
st
st jd

• Area of hoop steel in the form of rings is


computed as A st1  T
 st
11
IS code method
• Distribution steel and vertical steel for
outer face of wall is computed from
minimum steel consideration
• Tensile stress computed from the
following equation should be less than
the permissible stress for safe design
T
c 
1000t  (m  1)A st
the permissible stress is 0.27 fck

12
IS code method
• Base slab thickness generally varies
from 150mm to 250 mm and minimum
steel is distributed to top and bottom
of slab.

13
Design Problem No.1 on Circular Tanks
resting on ground with Rigid base

14
A cylindrical tank of capacity 7,00,000 liters is
resting on good unyielding ground. The depth
of tank is limited to 5m. A free board of 300
mm may be provided. The wall and the base
slab are cast integrally. Design the tank using
M20 concrete and Fe415 grade steel .
Draw the following
Plan at base
Cross section through centre of tank.

15
Step 1: Dimension of tank
H= 5-0.3 = 4.7 and volume V = 700 m 3
A=700/4.7 = 148.94 m2
D= (4 x 148.94/) = 13.77 14 m

16
Step 2: Analysis for hoop tension and
bending moment
One meter width of the wall is considered
and the thickness of the wall is estimated
as t=30H+50 = 191 mm.
The thickness of wall is assumed
as 200 mm.
Referring to table 9 of IS3370 (part IV), the
maximum coefficient for hoop
tension = 0.575
17
Step 2: Analysis for hoop tension and bending
moment (Contd.)
Tmax=0.575 x 10 x 4.7 x 7 =189.175 kN
Referring to table 10 of IS3370 (part IV),
the maximum coefficient for
bending moment = -0.0146 (produces
tension on water side)
Mmax= 0.0146 x 10 x 4.73=15.15 kN-m

18
Step 3: Design of section:
For M20 concrete cbc=7, For Fe415 steel
st=150 MPa and m=13.33 for M20
concrete and Fe415 steel
The design constants are: k  m cbc  0.39
m cbc   st
j=1-(k/3)=0.87
Q= ½ cbcjk = 1.19
Effective depth6 is calculated as
M 15.15x10
d   112.94mm
Qb 1.19x1000
19
Step 3: Design of section: (Contd.)
Let over all thickness be 200 mm with effective cover
33 mm
dprovided=167 mm

M 15.15x10 6
A
Spacing  
st of 16 mm diameter bar =  695. 16 mm 2

 st jd 150 x 0.87 x167

201x1000
(Max spacing 3d=501mm)
 289.23mmc / c
695
Provide .16
#16@275 c/c as vertical reinforcement on
water face

20
Step 3: Design of section: (Contd.)
Hoop steel: T 189.275x103
A st1    1261mm 2
st 150

113x1000
Spacing of 12 mm diameter bar =  89.mmc / c
1261

Provide #12@80 c/c as hoop reinforcement on water face

Actual area of steel provided 113 x1000


A st   1412.5mm 2
80

21
Step 4: Check for tensile stress:
T 189.275x10 3
c    0.87 N / mm 2
1000t  (m  1)A st 1000x 200  (13.33  1) x1412.5

Permissible stress = 0.27fck=1.2 N/mm2 > c Safe

22
Step 5: Distribution Steel:
Minimum area of steel is 0.24% of concrete area
Ast=(0.24/100) x1000 x 200 = 480 mm2
50.24x1000
 104.7.mmc / c
Spacing of 8 mm diameter bar = 480

Provide #8 @ 100 c/c as vertical and horizontal


distribution on the outer face.

23
Step 5: Base slab:
The thickness of base slab shall be 150 mm. The base
slab rests on firm ground, hence only minimum
reinforcement is provided.
Ast=(0.24/100) x1000 x 150 = 360 mm2
Reinforcement for each face = 180 mm2
50.24x1000
 279.mmc / c
Spacing of 8 mm diameter bar = 180

Provide #8 @ 250 c/c as vertical and horizontal


distribution on the outer face.

24
25
Design Problem No.2 on Circular Tanks
resting on ground with Rigid base

26
Design a circular water tank to hold
5,50,000 liters of water. Assume rigid
joints between the wall and base slab.
Adopt M20 concrete and Fe 415 steel.
Sketch details of reinforcements.

27
Step 1: Dimension of tank
Volume of tank V=550 m3
Assume H= 4.5
A=550/4.5 = 122.22 m2
D= (4 x 122.22/) = 12.47 12.5 m

28
Step 2: Analysis for hoop tension and
bending moment
One meter width of the wall is considered and
the thickness of the wall is estimated as
t=30H+50 = 185 mm. The thickness of wall is
assumed as 200 mm.
H2 4.5 2
  8.1  8
Dt 12.5  0.2
Referring to table 9 of IS3370 (part IV), the
maximum coefficient for hoop
tension = 0.575
29
Step 2: Analysis for hoop tension and bending
moment (Contd.)
Tmax=0.575 x 10 x 4.5 x 6.25 =161.72 kN
Referring to table 10 of IS3370 (part IV), the
maximum coefficient for bending moment
= -0.0146 (produces tension on water side)
Mmax= 0.0146 x 10 x 4.53=13.3 kN-m

30
Step 3: Design of section:
For M20 concrete cbc=7, For Fe415 steel st=150 MPa
and m=13.33 for M20 concrete and Fe415 steel
The design constants are:
m cbc
k  0.39
m cbc   st

j=1-(k/3)=0.87
Q= ½ cbcjk = 1.19
Effective depth is calculated as
M 13.3x10 6
d   105.7 mm
Qb 1.19x1000
31
Step 3: Design of section: (Contd.)
Let over all thickness be 200 mm with effective
cover 33 mm
dprovided=167 mm
M 13.3x10 6
A st    610.27 mm 2
 st jd 150x 0.87 x167
Spacing of 16 mm diameter bar =
201x1000
 329.36mmc / c
610.27
(Max spacing 3d=501mm)
Provide #16@300 c/c as vertical reinforcement
on water face
32
Step 3: Design of section: (Contd.)
3
Hoop steel: T 161.72x10
A st1    1078.13mm 2
 st 150
113 x1000
Spacing of 12 mm diameter bar =  104mmc / c
1078.13

Provide #12@100 c/c as hoop reinforcement on water


face
113 x1000
Actual area of steel provided A st   1130 mm 2
100

33
Step 4: Check for tensile stress:
T 161.72x10 3
c    0.76 N / mm 2
1000t  (m  1)A st 1000x 200  (13.33  1) x1130

Permissible stress = 0.27fck=1.2 N/mm2 > c Safe

34
Step 5: Distribution Steel:
Minimum area of steel is 0.24% of concrete area
Ast=(0.24/100) x1000 x 200 = 480 mm2
50.24x1000
 104.7.mmc / c
Spacing of 8 mm diameter bar = 480

Provide #8 @ 100 c/c as vertical and horizontal


distribution on the outer face.

35
Step 5: Base slab:
The thickness of base slab shall be 150 mm. The base
slab rests on firm ground, hence only minimum
reinforcement is provided.
Ast=(0.24/100) x1000 x 150 = 360 mm2
Reinforcement for each face = 180 mm2
50.24x1000
 279.mmc / c
Spacing of 8 mm diameter bar = 180

Provide #8 @ 250 c/c as vertical and horizontal


distribution on the outer face.

36
37
A TYPICAL DRAWING

38
39
Dr. G.S.Suresh
Civil Engineering Department
The National Institute of Engineering
Mysore-570 008
Mob: 9342188467 Email: gss_nie@yahoo.com

40

Вам также может понравиться