Академический Документы
Профессиональный Документы
Культура Документы
Contract Management
Contract management
Objectives
Ensure Project Completion
• On Time,
• Quality,
• Minimum cost
• Without any Disputes
• Manage Changes in Scope
Major events in contract management
• Post bid conference
• Work plan & schedule
• Progress & quality monitoring
• Reporting
• Interim payment
Contract management
• Variation Order
• Cost price adjustment
• Time extension
• Claim
• Conflict management
• Contract termination
• Liquidated damage (@ 0.05 % per day but not more than 10 % of
contract amount)
• Prize (@ 0.05 % per day but not more than 10 % of contract
amount)
• Taking over certificate
• Defect liability period
• Work completion report (As built drawing
• Final payment
• Work completion certificate
Disputes : Causes and Resolutions
Claim
• Claims arise when the Contractor believes he has been impeded
in some way from executing the works according to the contract.
• Common causes of claims, whether justified or not, are :
Cause Responsibility
Delay in obtaining possession and access to Employer
the site
Delay in obtaining work permits, customs Employer
clearance
Delay in obtaining drawings and instructions Consultant
Disputes : Causes and Resolutions
Causes of claim cont…
Cause Responsibility
Delay of commencement or completion of Employer
works by others
Mediation…
• Format – mediation is essentially a flexible process with no fixed
procedures. At an opening joint meeting each party briefly sets out
its position. This is followed by a series of private and confidential
meetings between the mediator and each of the teams present at the
mediation. This may lead to joint meetings between some or all
members of each of the teams. If a settlement is reached, its terms
should be written down and signed.
• The mediator – the mediator’s role is to facilitate negotiations. The
mediator will not express views on any party’s position.
Disputes : Causes and Resolutions
Mediation…
• Participants – the team attending the mediation should be kept as
small as possible but must include a lead negotiator, preferably a
senior executive or official within the organisation, with full
authority to settle on the day without reverting to others not
involved in the mediation.
• Preparation – each party usually prepares a brief summary of its
position for the mediator and the other party, with the key
supporting documents. These are exchanged between the parties,
and sent to the mediator, at least a week before the mediation. The
parties should enter into a mediation agreement once the details of
the mediation (e.g. place, time, name of mediator) have been
agreed.
Disputes : Causes and Resolutions
Types of Delay
Delay
Compensable Delay
NonCompensable Delay
Types of Delay …
• Excusable delay: delay beyond the fault of either the Contractor or the
owner; or not caused by Contractor’s negligence for which Time
compensation possible
Delay not caused by either party
Delay caused by Owner
Delay caused by Engineer
• Non-excusable delay: delay reasonably foreseeable and within control
of the contractor for which no monetary compensation or time extension
will be granted.
E.g. Slow progress, faulty workmanship, inadequate labor force, late
delivery of materials, failure to coordinate subcontractors
• Compensable delay: Excusable delay for which the Contractor may be
entitled Monetary compensation and Time extension
Types of Delay
E.g. Unforeseen ground conditions, Delay caused by Owner, Delay
caused by Engineer
• Non-compensable delay: excusable delay for which the contractor
may be entitled to an extension of time but no additional monetary
compensation.
– E.g. Adverse weather
• Concurrent delay : Concurrent delay is experienced when two or
more separate delay events occur during the same time period and
each, independently, affects the completion date.
• Several combinations of delays
• Resultant delay
– Detailed analysis of updated schedule
– Dominant cause, etc.
– The claimant has the proof of burden
Compensation Events
• Delayed possession of sites
• Delayed issuance of drawings, specifications, instructions
• Employer instructs to uncover or to carry out tests upon work
which is then found to have no defect
• Employer unreasonably delays to approve subcontract to be let
• Unforeseeable ground conditions
• Delayed caused by other Contractors and Public authorities
• Delayed advance payment
• Effect of Employer’s risk
• Delayed issue of Taking Over Certificate
• Variations etc.
Liquidated Damages for Delay
Extension of Time: Provisions of PPA &PPR
• The Contractor to give notice at least 7 days prior to intended
completion date
• Analysis of situation (reasons of delay) by employer
• The employer shall give extension of time (EOT) if a
Compensation Event occurs
Authority to extend time
• Up to six month by tender approving authority
• Above six month by head of department
Priced acceleration proposal from contractor
• Only if there is provision in bidding document & EOT have to
be awarded
• If accepted, they are incorporated in contract & treated as
variation
Termination of contract