Академический Документы
Профессиональный Документы
Культура Документы
Benefits:
- Identify the timeframe
- Identify theresource requirement
- identifythe key milestones
- Identify the key stakeholder engagement
points
- Assess impact of resource constraints
- Determine your commitment and obstacles
Network-logic
Estimates - times
Project
Scheduling
Schedule
Resource capability
Resource capacity
• Most common:
J
Dr. B. B. Das, National stitute of Technolo y Karnata ka, kal
In g Surath
Assume, for the sake of simplicity, that there are three activities, A, B
and C, which must be carried out in sequence and that the duration
times are:
Activity A: 4 weeks
Activity B: 6 weeks
Activity C:5 weeks
J
Dr. B. B. Das, Natio al ute of Techno gy nataka Surathkal
n Instit lo Kar ,
TIME (WEEKS)
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
TIME (WEEKS)
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
– it will be up to you to decide in what order you will list (“sort”) the
variousActivities in the left column.
Time Units
The Bar Chart Schedules for Large, Long-Duration, Complex Projects
tend to become very extensive.
1 12 2 13 3
a b
Burst nodes:
Events that have one (or more) entering activities
generating a number of emerging activities.
3
Dr. B. B. Das, National Institute of Technology Karnataka, Surathkal
When an event is common to two or more
subnetworks it is said to be an ‘interface’
event between those subnetworks and is
represented by a pair of concentric circles.
11 13
aa
ab 12 ac
22
ba bc
21 24
bb bd
24
Dr. B. B. Das, National Institute of Technology Karnataka, Surathkal
Events which have been identified as being of
particular importance in the progress of the
project.
Identified by an inverted triangle over the
event node (occasionally with an imposed
time for the event)
1/1/2016
1 2 3
a b
h
(hammock)
4
1 a 3
3
b
2
b d f h
3 6
2 c 4 e 6
a g
1 8
b h
3 d 5 f 7
Dr. B. B. Das, National Institute of Technology Karnataka, Surathkal
If a delay must occur after the competition of
an activity before the successor activity can
start.
2 2 4
2 c1
a
1 5
2 2
b d
3
3 7
1 2 3
a1 a2
15
5
Dr. B. B. Das, National Institute of bTechnology Karnataka, Surathkal
Activity Preceding Succeeding Remark
A NIL B,H
B A G,J
C NIL H
D NIL E,G
E D F
F E NIL LASTACTIVITY
G B,D NIL LASTACTIVITY
H A,C J
J B,H NIL LASTACTIVITY
The total project time (TPT) is the shortest time in which the
project can be completed, and this is determined by a
sequence (or sequences) of activities known as the critical path
(or paths).
S.urathkal
So, which one is the critical path in this network
diagram ofthree paths?
NO . LET
Earliest event time (EET):- It is the earliest time an event can take place,
assuming that all the event prior to it also occur at the earliest time.
EETJ = EETi +d
Latest event time (LET):- It is the latest time by which an event can occur, if the
project is to be completed within the specified time.
LETi= LETj-d
Dr. B. B. Das, National Institute of Technology Karnataka, Surathkal
Since activities cannot start until their tail events
are complete, and must not finish later than the
time at which their head events must occur, the
head and tail events can be considered to fix
boundaries between which activities can 'move'.
Description Code
TASK DURATION
3 5
F
2
Dr. B. B. Das, National Institute of Technology Karnataka, Surathkal
0 7 7 13 13 16
A C G
0 (7) 7 7 (6) 13 13 (3) 16 16 18
S H
16 18
F
(2)
0 3 3 D 6 6 E 9
B
7 (3) 10 10 (3) 13 13 (3) 16
3 5
F
11 (2) 13
Dr. B. B. Das, National Institute of Technology Karnataka, Surathkal
0 7 7 13 13 16
A C G
0 (7) 7 7 (6) 13 13 (3) 16 16 18
S 0 0 0 H
16 (2)18
F
0
B
3 3
D
6 6
E
9 0
7 (3) 10 10 (3) 13 13 (3)16
7 7 7
3 5
F
11 (2) 13
8
Dr. B. B. Das, National Institute of Technology Karnataka, Surathkal
THANKYOU