Вы находитесь на странице: 1из 36

Bayu Pinasthika (1200960234)

Friska Oktaviana (1200986681)


1. Project Spesification 9. Half Slab Construction
Documentation
2. Project Location
10. Safety, Health &
3. Project Site Plan
Environment
4. Project Organization
11. Quality Control
5. Structure Coordination
12. Half Slab Price
6. Management Comparision
Construction
13. Conclusion
7. Half Slab Construction
14. Recomendation
Method
8. Half Slab Spesification
 Project Name : Puri Parkview Apartement
(Tower C)
 Build Type : Apartement
 Location : Jl. Pesanggarahan No. 88
Kebon Jeruk, Jakarta Barat
 Number of Floors : 24th Floors
 Floor Area : 18.945 m2
 Number of Basement : 1st Floor
Jl. Pesanggrahan No. 88
Kebon Jeruk, Jakarta Barat

Jalan Tol
Jakarta - Tangerang

Jl. Pesanggrahan SMA 112

Sungai
Pesanggrahan
Tower C
• KSO PT. Pelaksana Jaya Mulia
Owner
• PT. Alam Jaya Perkasa
Construction
• PT. Perentjana Djaja
Management
Architect
• PT. Megatika International
Consultant
Landscape
• PT. Elvolver
Consultant
Design & Built
• PT. Catur Bangun Mandiri
Contractor
Foundation
• PT. Geotechnical Engineering Service
Planner
Structure
• PT. Baganusa Dayaprima
Planner
MEP Planner • PT. Metakom Pranata
Owner
Consultant
Architect KSO PT. Pelaksana Jaya Mulia
PT. Alam Jaya Perkasa

Consultant Supervision Contractor

PT. Perentjana Djaja PT. Catur Bangun Mandiri

Planning Consultant
Quality

Management
Construction

Time Cost
 Production
 Erection
 Preparation
 Move
 Installation
 Time Back
 Topping
 Wire Mesh Installation
 Concrete Pouring
 Area : 18.945 m2
 Volume Foundry Plans : 1.326,15 m3
 Steel Bar Quality : BJTD 40
 Thick : 7 cm
 Concrete Quality : K-300 / 24.900 MPa
 Concrete Slump : 10 cm ± 2 cm
 Thick Concrete Cover : 3 cm
 Admixture (Fly Ash) : Maximum 15%
Production Process
Erection : Preparation Process
Erection : Moving Process
Erection : Intallation Process
Erection : Time Back Process
Topping : Preparation Process
Topping : Wire Mesh Installation
Topping : Preparation Concrete Pouring
Topping : Concrete Pouring
 Provide personal safety tools such as hats, shoes, work
clothes, etc. for workers and guests.
 Provide safety facilities such as barrier for holes, signs,
railings, etc.
 Provide fire extinguishers for emergency situation.
 Provide first aid include auxiliary equipment,
medicines, etc.
 Keep the project clean by provide trash, periodically
dispose off the project, etc.
 Check on the tensile strength of steel every material.
 Examination of rebar installation before casting.
 Testing slump value of concrete before casting.
 Testing the value of concrete compressive strength test
every concrete mixer came to the project site.
 4 cylinder concrete mold every 1 concrete mixer
 1 concrete mixer has a volume 7 m2 and 9 m2.
 All activities related to concrete casting is controlled.
 Check every concrete curing process.
 Physical inspection of the finished concrete.
Unit Price Analysis

Price Per Component Analysis

Half Slab Method Conventional Method

Topping Analysis

Total Price Analysis


Materials to Make Concrete 1 m3
Description Unit Indeks Price Material Work
3
Material Concrete m 1,000 Rp 716.800 Rp 716.800
Sub-Total Rp 716.800 Rp -
Total Rp 716.800

Rebar Installation 1 m2 Wiremesh M6


Description Unit Indeks Price Material Work
Material Wiremesh m2 1,000 Rp 43.200 Rp 43.200
Sub-Total Rp 43.200 Rp -
Total Rp 43.200
2
Make 1 m Formwork for Concrete Slab Precast
Description Unit Indeks Price Material Work
Material 3
Plate 10 cm m 0,008 Rp 9.155 Rp 73
Hollow Steel 50x50x3 Kg 9,394 Rp 9.155 Rp 86.002
Kaso 5/7 m3 0,005 Rp 50.860 Rp 254
Formwork Oil Liter 1,155 Rp 8.200 Rp 9.471
Labor Worker OH 0,007 Rp 45.000 Rp 315
Carpenter OH 0,076 Rp 60.000 Rp 4.560
Foreman OH 0,008 Rp 65.000 Rp 520
Overseer OH 0,001 Rp 100.000 Rp 100
Sub-Total Rp 95.801 Rp 5.495
Total Rp 101.296
Installation Cost + Open Formwork 1 Unit Component for Precast Slab
Description Unit Indeks Price Material Work
Labor Worker OH 0,053 Rp 45.000 Rp 2.385
Carpenter OH 0,018 Rp 60.000 Rp 1.080
Overseer OH 0,005 Rp 100.000 Rp 500
Sub-Total Rp - Rp 3.965
Total Rp 3.965

Cost of Pouring Concrete 1 Unit Component for Precast Slab


Description Unit Indeks Price Material Work
Labor Worker OH 0,064 Rp 45.000 Rp 2.880
Stonemason OH 0,244 Rp 60.000 Rp 14.640
Vibrator Worker OH 0,128 Rp 60.000 Rp 7.680
Foreman OH 0,034 Rp 65.000 Rp 2.210
Overseer OH 0,073 Rp 100.000 Rp 7.300
Sub-Total Rp - Rp 34.710
Total Rp 34.710
Installation / Erection 1 Unit Component for Precast Slab
Description Unit Indeks Price Material Work
Material Tower Crane Rental Unit/Day 0,067 Rp 250.000 Rp 16.750
Solar Liter 6,676 Rp 9.000 Rp 60.084
Labor Crane Operator OH 0,067 Rp 100.000 Rp 6.700
Worker OH 0,067 Rp 45.000 Rp 3.015
Erection Worker OH 0,134 Rp 60.000 Rp 8.040
Overseer OH 0,067 Rp 100.000 Rp 6.700
Sub-Total Rp 76.834 Rp 24.455
Total Rp 101.289
3
Concrete Topping 1 m
Description Unit Volume Unit Price Total
Concrete m3 1 Rp 751.510 Rp 751.510
2
Wiremesh Installation m 20 Rp 43.200 Rp 864.000
3
Pouring Concrete m 1 Rp 34.710 Rp 34.710
Total Price Rp 1.650.220
Calculate cost of 1 unit production concrete component.

 Concrete (m3)
 Pouring Concrete (unit)
 Wire Mesh Installation (m2)
 Formwork Production (m2)
 Formwork Installation (unit)

The calculation according the volume of floor plate.


Example : Half Slab S1

Pekerjaan Produksi 1 Buah Komponen Beton Plat Lantai S1


Description Unit Volume Unit Price Total
Concrete m3 0,6314 Rp 716.800 Rp 452.587,52
Pouring Concrete buah 1 Rp 34.710 Rp 34.710,00
Wiremesh m2 18,04 Rp 43.200 Rp 779.328,00
Formwork Production m2 0,903 Rp 106.791 Rp 96.431,92
Formwork Installation buah 1 Rp 3.965 Rp 3.965,00
Total Rp 1.367.022,44
Example : Part S1

Pekerjaan Produksi 1 Buah Komponen Beton Plat Lantai S1


Description Unit Volume Unit Price Total
Concrete m3 1,0824 Rp 716.800 Rp 775.864,32
Poruing Concrete buah 1 Rp 34.710 Rp 34.710,00
Wiremesh Installation m2 18,04 Rp 43.200 Rp 779.328,00
Formwork Production m2 10,568 Rp 106.791 Rp 1.128.563,15
Formwork Installation buah 1 Rp 3.965 Rp 3.965,00
Total Rp 2.722.430,47
No. Description Unit Quantity Unit Price Total
1 Half Slab Concrete Component Production
Concrete Plate S1 Each 5 Rp 1.367.022,44 Rp 6.835.112,20
Concrete Plate S2 Each 8 Rp 1.490.199,46 Rp 11.921.595,65
Concrete Plate S3 Each 1 Rp 1.551.787,96 Rp 1.551.787,96
Concrete Plate S4 Each 2 Rp 1.397.816,69 Rp 2.795.633,39
Concrete Plate S5 Each 21 Rp 1.459.405,20 Rp 30.647.509,24
Concrete Plate S6 Each 9 Rp 1.798.142,00 Rp 16.183.277,99
Concrete Plate S7 Each 1 Rp 2.106.084,54 Rp 2.106.084,54
Concrete Plate S8 Each 8 Rp 2.381.378,15 Rp 19.051.025,22
Concrete Plate S9 Each 1 Rp 899.912,22 Rp 899.912,22
Concrete Plate S10 Each 1 Rp 2.266.672,48 Rp 2.266.672,48
Concrete Plate S11 Each 2 Rp 1.463.732,78 Rp 2.927.465,56
Concrete Plate S12 Each 1 Rp 899.912,22 Rp 899.912,22
Concrete Plate S13 Each 3 Rp 1.166.457,70 Rp 3.499.373,11
Concrete Plate S14 Each 1 Rp 1.213.051,17 Rp 1.213.051,17
Concrete Plate S15 Each 1 Rp 507.576,45 Rp 507.576,45
Concrete Plate S16 Each 1 Rp 419.233,37 Rp 419.233,37
Concrete Plate S17 Each 1 Rp 999.278,46 Rp 999.278,46
Concrete Plate S18 Each 1 Rp 930.519,72 Rp 930.519,72
Concrete Plate S19 Each 1 Rp 804.776,82 Rp 804.776,82
Concrete Plate S20 Each 1 Rp 1.082.188,80 Rp 1.082.188,80
2 Half Slab Installation Each 70 Rp 101.289,00 Rp 7.090.230,00
3 Toping Concrete Work m3 35,796 Rp 1.650.220,00 Rp 59.071.275,12
Total Price Rp 173.703.491,69
No. Description Unit Quantity Unit Price Total
1 Concrete Plate S1 Each 5 Rp 2.722.430,47 Rp 13.612.152,33
2 Concrete Plate S2 Each 8 Rp 2.973.258,23 Rp 23.786.065,84
3 Concrete Plate S3 Each 1 Rp 3.098.672,11 Rp 3.098.672,11
4 Concrete Plate S4 Each 2 Rp 2.785.137,41 Rp 5.570.274,81
5 Concrete Plate S5 Each 21 Rp 2.910.551,29 Rp 61.121.577,06
6 Concrete Plate S6 Each 9 Rp 3.600.327,64 Rp 32.402.948,76
7 Concrete Plate S7 Each 1 Rp 4.227.397,05 Rp 4.227.397,05
8 Concrete Plate S8 Each 8 Rp 4.787.227,78 Rp 38.297.822,27
9 Concrete Plate S9 Each 1 Rp 1.775.397,43 Rp 1.775.397,43
10 Concrete Plate S10 Each 1 Rp 4.553.964,98 Rp 4.553.964,98
11 Concrete Plate S11 Each 2 Rp 2.921.125,34 Rp 5.842.250,68
12 Concrete Plate S12 Each 1 Rp 1.775.397,43 Rp 1.775.397,43
13 Concrete Plate S13 Each 3 Rp 2.316.850,64 Rp 6.950.551,92
14 Concrete Plate S14 Each 1 Rp 2.408.895,76 Rp 2.408.895,76
15 Concrete Plate S15 Each 1 Rp 973.283,74 Rp 973.283,74
16 Concrete Plate S16 Each 1 Rp 795.074,39 Rp 795.074,39
17 Concrete Plate S17 Each 1 Rp 1.967.432,54 Rp 1.967.432,54
18 Concrete Plate S18 Each 1 Rp 1.827.360,31 Rp 1.827.360,31
19 Concrete Plate S19 Each 1 Rp 1.573.260,81 Rp 1.573.260,81
20 Concrete Plate S20 Each 1 Rp 2.135.201,71 Rp 2.135.201,71
Total Price Rp 214.694.981,91
 Calculation of Price Efficiency

Price Difference
 Efficiency = × 100%
Largest Price

Rp 214.694.981,91−Rp 173.703.491,69
 Efficiency = × 100%
Rp 214.694.981,91

 Efficiency = 19,091 %
 All members of the organization do the work according
to the position.
 Construction project use the half slab method because
the cost more efficient.
 During the construction period in the field, quality
assurance looks very good.
 From the analysis, concrete plate with half slab method
is more efficient until 19,091% than convetional price.
 Quantity of workers must be calculated correctly.
 Use safety straps should be done when working on the
high level.
 Ban on smoking at work must be done properly.
 Perform a quality selection of tower crane.
 Addition of tower crane because the project has
reached a high level.
 Because half slab method is more efficient than
conventional method, then this method can be an
alternative in future projects.
Bayu Pinasthika (1200960234)
Friska Oktaviana (1200986681)

Вам также может понравиться