Академический Документы
Профессиональный Документы
Культура Документы
Cost Estimation
• A cost estimate is the approximation of the cost of a program, project, or
operation.
• Four common types of cost estimates are:
1. Planning estimate: A rough approximation of cost within a reasonable
range of values, prepared for information purposes only.
2. Budget estimate: An approximation based on well-defined (but
preliminary) cost data and established ground rules.
3. Firm estimate: A figure based on cost data sound enough for entering
into a binding contract.
4. Not-to-exceed /Not-less-than estimate: The maximum or minimum
amount required to accomplish a given task, based on a firm cost
estimate.
Cost Estimation methods
1. Engineering estimates
2. Accounting analysis
3. Statistical methods
Engineering Estimates
• The Engineering Cost Estimating method builds the overall cost
estimate by summing detailed estimates done at different levels of
the Work Breakdown Structure (WBS).
• It is a technique where the system being costed is broken down into
lower-level components (such as parts or assemblies), each of
which is costed separately for direct labor, direct material, and
other costs.
• Engineering estimates for direct labor hours may be based on
analyses of engineering drawings and contractor or industry-wide
standards.
Accounting Analysis Method
• The accounting analysis approach requires that
each individual cost is examined, and based on
judgment is categorized as a fixed or variable
cost. Then all variable costs are totaled.
Examples are:
Chemical Engineering Plant Cost Index (CEPCI)
www.che.com/pci
McGraw-Hill Construction Index
www.construction.com
Segmenting Model
• Under segmenting model an estimate is
decomposed into its individual components,
estimates are made at those lower levels, and
then the estimates are aggregated (added) back
together.
• It is much easier to estimate at the lower levels
because they are more readily understood.
Power Sizing Model
Also called as Cost Capacity Equations (CCE)
x = 1, relationship is linear
x < 1, economies of scale (larger capacity is less costly than linear)
x > 1, diseconomies of scale
Cost-Capacity Combined with Cost Index
Multiply the cost-capacity equation by a cost index (It/I0) to adjust for time
differences and obtain estimates of current cost (in constant-value dollars)
Example: A 100 hp air compressor costs $3000 five years ago when
the cost index was 130. Estimate the cost of a 300 hp compressor
today when the cost index is 255. The exponent for a 300 hp air
compressor is 0.9.
Solution: Let C300 represent the cost estimate today
C300 = 3000(300/100)0.9(255/130)
= $15,817
Example Power-Sizing Exponent Values
Improvement and the Learning Curve
• Regardless of the task being performed, as the number
of repetitions increases, performance becomes faster
and more accurate.
• The learning curve captures the relationship between
task performance and task repetition.
• In general, as output doubles the-unit production time
will be reduced to some fixed percentage, the learning
curve percentage or learning curve rate.
Example
• .
Example
• Calculate the time required to produce the
hundredth unit of a production run if the first
unit took 32.0 minutes to produce and the
learning curve rate for production is 80%.
• T100 = T1 X 100Iog0.80/log2.0
Example:
Allocating
$150000
amongst 3
machines.
Allocation rates Machine 1: Rate = $50,000/100,000 = $0.50 per DL $
for $50,000 to Machine 2: Rate = $50,000/2,000 = $25 per DL hour
each machine Machine 3: Rate = $50,000/250,000 = $0.20 per DM $
ABC Allocation
Activity-Based Costing ─ Provides excellent allocation strategy and analysis of
costs for more advanced, high overhead, technologically-based systems
Cost Centers (cost pools) ─ Final products/services that receive allocations
Activities ─ Support departments that generate indirect costs for distribution to cost
centers (maintenance, engineering, management)
Cost drivers ─ These are the volumes that drive consumption of shared resources (#
of POs, # of machine setups, # of safety violations, # of scrapped items)
Solution:
ABC rate for accident basis = 200,200/560 = $357.50/accident
US allocation: 357.50(425) = $151,938
Europe allocation: 357.50(135) = $48,262
Example: Traditional Allocation Comparison
Solution:
Rate for employee basis = 200,200/1400 = $143/employee
US allocation: 143(900) = $128,700
Europe allocation: 143(500) = $71,500