Академический Документы
Профессиональный Документы
Культура Документы
Presentation on
Submitted by:
AVINASH. P. CARNEIRO
(01FE15MES004)
2. Problem statement
4. Literature review
5. Project execution
7. Conclusions
Oil remains the world's leading fuel, accounting for one-third of the world's energy
consumption with around 1.6 million barrels per day consumed globally making its
transportation an important concern due to environmental issues.
Oil consumption has increased at 3.3 per cent over the period 2008-2016 with
consumption of 4.0 Mb/d during 2016 on account oil imports continuously
increasing.
India has proven oil reserves of 5.7 billion barrels and 1.4 trillion m3 of gas
reserves, but India remains a net importer of energy, due to the low production base.
The petroleum transportation through pipelines over the long distance requires well
designed pump sets, highly equipped dispatch station and control station. The large
amount of money has to be spent towards the heavy electricity bills incurred at
dispatch station due to continuous running. An alternative option to reduce the high
power consumption costs can be through adoption of green energy.
The photovoltaic system is a reliable and clean source of electricity that can
be adopted to a variety of applications. Photovoltaic plants are one of the most
important renewable sources of energy, as they are an effective solution to
environmental problems.
The demand for electricity in the country has risen rapidly and is expected to
rise further in the coming years. To meet the growing demand of electricity in
the country, a massive addition to the installed generating capacity is required.
India increased its solar-generation capacity for almost four times from 2,650
MW on 26 May 2014 to 12,289 MW on 31 March 2017.
The petroleum dispatch center requires enormous amount of energy to run the pumps
for over a long period of time. The power required for these pumps results in the large
amount of electricity bills.
There is no alternative for the energy consumption in the cross country petroleum
dispatch stations. But however we can provide an alternate source of energy to run the
majority of the equipment in the dispatch station.
The proposed solar power plant at the dispatch stations can be made to provide power
to the control room, lighting of the building, street lighting, all the other major
machineries and equipment up to the rating of 440 volts installed at the pump house and
other stations.
The use of renewable energy not only caters the gap between demand and supply but
also does not contribute to the global carbon foot print unlike conventional source of
energy.
3. To assess feasibility of Grid tied SPV power plant for L.T side of the station
using the PVSyst tool and simulate its operation.
To perform MATLAB computational analysis on the H.T and L.T side power
consumption.
To design and propose SPV power plant for L.T side of the station using the
PVSyst tool and simulate its operation.
Formulate Single Line Diagram of SPV power plant for the dispatch center
using AUTOCAD.
Brandon J. Murrill et al., describe the Pipelines are a relatively safe means of
transporting oil and gas compared to other modes of transport but have the
potential to damage the environment by the dangerous substances they carry.
Abarasi Hartet al., describes that an enormous energy or high pumping power
required to overcome the high pressure drop in the pipeline due to its high
viscosity in the reservoir conditions. The review provides direction for
improvement and development of new technologies for the transport of bitumen
and heavy oil by pipelines.
Conrado Borraz-Sanchez et al., his research covers several approaches that help
to a better understanding of the topic for the future research and the study of the
mathematical formulations and difficulties of the equivalent optimization
problems.
LiuXu Wang Xiaoyu et al., describes the corrosion mechanism of oil and
gas pipeline improved protection technology. This document presents the
mechanism of corrosion of the pipelines and the current corrosion technique
has been analyzed.
Shruti Sharma et al., describes the development of thin films, dye-sensitized solar
cells and organic solar cells improved the solar cell efficiency. Development is
generally hindered by costs and efficiency.
Sharma B.D. et al., describes the acquisition and simulation of data is a complex
process and may have inaccuracies of 3 to 20%. The most reliable data is measured
with accurate instruments.
K.H. Husseinet al., briefs about comparing the incremental and instantaneous
conductance of the PV array for developing a new Maximum Power Tracking (MPT)
algorithm to track Maximum Power Operating Point (MPOP). A new type of lower
power photovoltaic (PV) system with simple structure has been designed.
S. Yuvarajan et. al., briefs about the proposing of MPPT for a photovoltaic (PV)
panel using the open circuit voltage and short-circuit current of the PV array, a fast
and accurate maximum power point tracking (MPPT) algorithm.
Hemakshi Bhoye et al., describes that how to establish PV solar power plant
design as well as calculation of power generation, based on that to further
recommendation and techniques to reduce the cost of PV solar power plant.
M. H. Albadi et al, explains Retscreen software was used to provide the necessary
data on cost and financial analysis to determine the annual output and the amount
of greenhouse gas reduction corresponding to the clean energy generated from solar
PV system.
1. Pumping station
2. Metering Stations
3. Valve Manifolds
4. Valves
5. Piping Manifolds
6. Pigging
8. Telecommunication Towers
Motor Running hours for April 2017 from daily reports Petronet MHBL,
Single pump (1 Main line pump + 1 Booster pump) = 376 h
Dual pump (2 Main line pump + 1 Booster pump) = 215 h
Total L.T. side units = Total units consumed for April 2017 (Ref. MRPL bill) -
Total H.T. units consumed for April 2017
(By subtracting the calculated H.T side Energy consumption units from the Total
number of unit consumption for the month, we will get the L.T side units.)
Demand charges for per unit = Total demand charges for April 2017
Total units Consumed for April 2017 (Ref. MRPL bill)
= 3, 76,314.2 /200
= 0.47 Rs./unit
L.T side demand charges for April 2017 = Total L.T. side units × Demand charges per unit
Total L.T charges for April 2017 = L.T side demand charges + Total Energy charges
of the L.T side + Electricity Tax + Fuel Escalation charges
=12,803.72 + 1, 77,072.74 + 17,707.27 + 1634.51
= 2, 09,218.24Rs.
CONTINUED
TOTAL L.T CHARGES, TLTC=
L.T. & H.T. SIDE KVA CHARGES, DEMAND (LTDC+TECM+AETD+TEEC)
CHARGE, TOTAL UNITS CONSUMED,
(MRPL BILL) = TU, DC, KVA
B
TOTAL DEMAND CHARGES, TDC= (KVA*DC)
STOP
POWER CONSUMPTION STUDY OF PETRONET MHBL
The power consumption of the L.T side for the last 3 months is as follows.
March 2017 - 27,146.51 Units/Month
April 2017 - 25,814.48Units/Month
February - 27,787.92 Units/Month
As per the calculation it can be seen that the L.T side consumption varies from the
25,000 units to 28,000 units per month.
The highest L.T side consumption has been taken into the considerations for the
SPV design.
I.e. 27,787.92 = 28,000 units/month (round figure)
Total estimated L.T side units per month = 2, 80, 00,000 Wh (28,000kWh)
Total estimated units used per day = 934.333 kWh or 39 kWh per hour
Multiplying the total units Watt-hours per day with 1.3 (the energy lost in the
system to get the total Watt-hours per day which must be provided by the panels.)
availability and the design of the system the 316kWh plant has been proposed for
1 2 3 4 5 6 7 8 9
10 11 12 13 14 15 16 17 X
4/27/2019 31
SOLAR PV ARRAY WITH INVERTER
=1020 x 13600
= 1, 38, 72,000
= 6 x 5, 50,500
= 33, 03,000
10% extra on total cost of the system (wires, electrical materials for wiring, civil
Total cost of the system = 1, 71, 75,000 + 17, 17,500 = 1, 88, 92,500
Figure shows the array losses for 800W/m2, at the module temperature of
25o C the Pmpp = 42.3kW and module mismatch loss is 2.9% and at module temp
of 50.8o C the loss is calculated as 11.3%. With the considerations of the global
losses of 14.5% the resultant Pmpp array is considered as 36.2kW
200
150
kWh/m2
100
GlobHor in kWh/m²
GlobInc kWh/m²
50
GlobEff kWh/m²
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
• The horizontal global irradiation reaches the highest point of 208.2kWh/m2 in March where
the solar irradiance is expected to be at the peak level.
• Global incident in collector plane again increases after August it reaches around
1742kWh/m2in December.
4/27/2019 SCHOOL OF MECHANICAL ENGINEERING 40
MONTHLY BASIS BALANCES AND RESULTS OF
GENERATED ENERGY
60000
50000
40000
kWh
30000
20000
10000
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Earray kWh 52280 47893 52755 45717 42560 30932 29754 33452 39995 45386 45806 51123
E_Grid kWh 50877 46597 51329 44550 41528 30293 29161 32742 39061 44260 44634 49783
• The highest tracked effective energy of the array (EArray) is 52755 kWh in March
where the lowest tracked energy is 29754 kWh in July.
• The highest tracked energy injected into grid (E_Grid) is 51329 kWh in March
where the lowest tracked energy is 29161 kWh in July.
4/27/2019 SCHOOL OF MECHANICAL ENGINEERING 41
MONTHLY BASIS BALANCES AND RESULTS OF EFFECTIVE
ENERGY OUTPUT
13.4
13.2
13
12.8
12.6
Percentage %
12.4
12.2
12
EffArrR %
11.8
EffSysR %
11.6
11.4
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
250
200
150
kWh/m2
100
GlobHor in kWh/m²
50
GlobInc in kWh/m²
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
3.5
2.5
2
m/s
1.5
WindVel in m/s
0.5
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
• The normalized production of the plant with the produced useful energy of Yf =
4.37kWh/kWp/day
• The normalized production graph highlights the system losses occurred in the plant, theSystem
loss (Ls) = 0.11kWh/kWp/day
• The normalized production graph also highlights the collection losses occurred in the plant, the
Collection loss(Lc) = 1.22 kWh/kWp/day
NORMALIZED PRODUCTION AND NORMALIZED LOSS FACTORS
600
MisLoss in kWh
500
OhmLossin kWh
EACOhmL in kWh
400
kWh
300
200
100
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
1400
1200
1000
800
kWh
600
400
200
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Inv Loss 1253 1159 1278 1050 931 579 540 641 837 1008 1049 1197
IL Oper 1247 1153 1272 1044 926 574 534 635 831 1002 1043 1191
98.3
98.2
98.1
98
97.9
Percentage %
97.8
97.7
97.6
97.5
EffInvR in %
97.4
97.3
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
A normal traditional system without solar PV emits 936g of CO2 per kWh. So for the
duration of the 10 years total amount of 3912.771 tons carbon emissions can be stopped from
emitting into the atmosphere by adopting the green energy.
The PV simulation tools used for analysis (PVSyst) is effective means for SPV system design. The
result indicates that proposed 315kW plant generates the 300kWac and requires 1957m2 of module area
for the proposed plant.
From the PVSyst simulation results the energy fed to the grid for the different months have been
calculated. The energy generated in March the total generated power of 51329kWh makes it highest
amount of energy to be fed to the grid. The energy fed to the grid in January and December stands second
and third respectively in the table with the total amount of power 50877kWh and 49783kWh respectively.
The proposed plant contributes towards the green energy of the system which contributes in stopping of
carbon emissions. For the duration of the 10 years total amount of 3912.771 tons carbon emissions can be
stopped from emitting into the atmosphere from the proposed solar plant.
SCOPE FOR FUTURE IMPROVEMENT
Real time implementation of the designed system and its experimental study
A n alternative plan can be taken into consideration in order to compensate the H.T side power
consumption charges. The different site of land can be acquired and larger grid connected solar
plant of 3MW can be proposed. The revenue generated can be utilized for the energy charges of the
petroleum dispatch center (Petronet MHBL).