FOR
CONCRETE PAVEMENT OF ACCESS ROAD 38 – 46
Issued April 2017 For Approval M. Rizki Fadly Jumhar Febriko Song, Sang Min
General
This method statement cover the general. Plan and producedur of rigid pavement at
Access Road 38 - 46
• Resources
Man Power
Safety officer =1 person
Security officer =1 person
Labor skill =1 person
Unlabor skill =6 Person
Driver = Person
• Equipment
Compressor =1 unit
Truck Mixer =2 unit
Vibrator =1 unit
Jidar (leveling tool) =1 unit
Grooving tool =1 unit
Vibro Roller =1 unit
PAGE 2
FLOW CHART
SCOPE OF WORK
The scope of the work is as below.
• Clearing and Stripping • Install Wiremesh
• Temporary Draingae System • Rigid Pavement
• Install Formwork
Flow of Work
Start
Clearing
Install Formwork
Install Wiremesh
Concrete Pavement
Finish
PAGE 3
SITUATION
PAGE 4
SITUATION
VIEW 2
VIEW 1
VIEW 3
WORK SEQUENCE
A
CONCRETE
MIXER
2,50
TO ANGKUP TRACK 1
>> PLAN
A CL
STEP 1 STEP 2
CONCRETE
MIXER
2,50
TRACK 1 TO ANGKUP
CONCRETE
MIXER
2,50 2,50
TRACK 1 TO ANGKUP
1. Initial concrete pavement work is carried out at the location of track 1 (directions to Angkup)
2. Then the concrete pavement is carried out at the location of Lane 2 (directions to Outdoor Switchyard)
3. The concrete pavement thickness is 20 cm and the road width is 5 m while the thickness of wiremesh is
8 cm
4. Concrete pavement length is approximately 352 m
PAGE 7
PAGE 8
CARE OF WATER
Concrete Pipe
Temporary Drain
Ditch
During construction at temporary repair of existing access road area, it will be constructed
temporary drain ditch around road plan (as shown in the figure) and will be streamed to the cliff.
PAGE 9
CONCRETE PAVEMENT WITH WIREMESH
• Dowel installation is performed on each cross-connections for the purpose of a load-bearing system so that adjacent plates
can work together without any significant decline
• Tie bar installed on longitudinal joints for the purpose of binding the concrete (plate) so as not to move horizontally.
• After that install wiremesh based on engineer’s instruction
• Concrete pavement casting is carried out by pouring fresh concrete directly from Mixer Truck which has
arrived at the location further spread / leveled by using hoe in casting area.
• Then the concrete compaction is carried out by Vibrator.
PAGE 10
CONCRETE PAVEMENT WITH WIREMESH
• The final touch of the concrete pavement is to re-level the concrete surface with a leveling tool and do ± 2 times for
smoothing concrete surfaces
• Then the concrete is still in plastic state (± 1 - 3 hours after casting) is given a texture to give the surface
roughness by grooving in the direction of crossing the road using a wire brush.
• Protect the concrete during the first few hours after casting and surface texture manufacture to minimize
evaporation by watering concrete with water or another curing method for concrete.
• Making slit with saw cutter as deep as 4 cm to prevent crack in concrete
• Application of joint sealant
1 2 3
4 5 6
7 8 9
10 11 12
TIME SCHEDULE OF TEMPORARY REPAIR OF EXISTING ACCESS ROAD TO NO.2 POWER HOUSE
Prepared by:
Jumhar Febriko
Planning Manager
SITE ORGANIZATION
PROJECT MANAGER
JV
Song Sang, Min
SITE ENGINEER
Jumhar Febriko
GSP / SUPERVISOR
Edi Sutrisno
PAGE 13
SAFETY PAGE 14
AUDIT Work
K3L SHE K3L INSPECTION & SHR K3L HOUSE
FATAL SHE TALK Safety,Health
TRAINING INDUCTION SHE PATROL MEETING TRAINING KEEPING
ACCIDENT & Env.
SAFETY PLAN TARGET : ZERO - New Worker EVERY EVERY DAY EVERY MONDAY - K3 BASIC - CLEAN,NEAT AND EVERY
ACCIDENT - COMPANY SATURDAY & EVERY AND -P3K HEALTHY WORK THREE
- SUBCONTRACT SATURDAY WEDNESDAY - FIRE BRIGADE ENVIRONTMENT MONTH
- FOREMAN - EMERGENCY - MASS CLEANING
EVERY SATURDAY
( ROUTINE )
-Safety Glass : Safety glasses protect your eyes against injuries for loose
material, dust and other particles.
- Helmet : A helmet protects your head against, for instance falling loose
material (rock, etc)
- Safety boots : Safety boots protect your feet against falling objects and
against penetration by projecting
PAGE 16
SAFETY CONSIDERATION PAGE 17
2. Noise Control
- All equipment shall be kept in good working order
- Equipment shall be operated within specifications and capacity
- Equipment shall be operated with appropriate noise abatement
accessories such as sound hoods and shall ensure that these accessories
are correctly maintained.
PAGE 18
TRAFFIC MANAGEMENT PAGE 19
Concrete Pavement
Work
FLAGMAN
TRAFFIC MANAGEMENT PAGE 20
FLAGMAN EQUIPMENT
1. Helm Project
A helmet protects your head against, for instance falling loose
material (rock, etc)
2. Mask
Used to protect from dust due to work execution
3. Safety boots
Safety boots protect your feet against falling objects and
against penetration by projecting
4. Rubber cone
Used as temporary traffic referrer signs
5. Flag
Helps traffic management work
6. Vest
Used as body armor workersand to reflect light at night so that
the existence of workers is known
TRAFFIC MANAGEMENT PAGE 21
Keterangan :
Sign equipment:
1. Signs:
Caution !
Reduce Speed now
Don’t go ahead
Watch out for
excavation
Road Narrowing
Maximum speed 40
km/jam
Maximum speed 20
km/jam
Instruction of
Direction
2. Officer / flagman uses
Red Flags.
3. Rubber Cone is placed to
Based on Regulation of the Minister of direct the direction of
Transportation no. 13 of 2014 on traffic controlled.
Traffic Signs