Академический Документы
Профессиональный Документы
Культура Документы
Generating
Station
2x 67.5
6x135
RENGALI S/Y
C
C
JAYANAGAR UTKAL AL
C
INTRODUCTION
‘Transmission’ and ‘Grid Management’ are essential functions for smooth
evacuation of power from generating stations and delivery to the consumers.
Transmission function : Construction and maintenance of the transmission
infrastructure
1. day ahead,
2. real-time
3. post-facto functions.
1. day ahead functions are more in the nature of planning for the day of
operation. It involves estimating the future load and generation scenarios,
planned outages of transmission elements, evaluating options and making
elaborate plans to meet the anticipated as well as unforeseen events.
2. real time functions are primarily balancing the dynamically varying supply
and demand of electrical energy in the control area and power flow through
the interconnected system.
GRID MANAGEMENT FUNCTION
Vital grid parameters such as frequency, bus voltages, transmission line
loading, transformer loading, electrical (angular) separation between
generation pocket and load centre etc. are monitored round the clock and
suitable instructions are passed on to the SLDCs / Discoms / Field
engineers or generating stations, in case, the values of the above
parameters are seen to be outside the permissible bands.
The operating band has been specified in the Indian Electricity Grid Code
(IEGC) / State Electricity Grid Code as the case may be. All this requires
extensive coordination with the operating personnel positioned at
switching stations, generator control rooms and other load dispatch
centres. Critical decisions have to be taken at the spur of the moment.
Communication System acts like the sensory organs of the grid operators
and helps them to diagnose the system condition and to take corrective
measures.
U. SILERU
GAJUWAKA 15.04.2018
KOLAR HVDC
OPERATIONAL FUNCTIONS OF SLDC
Facilitates: Integrated Grid operation for Quality, Security & Reliability of
power supply in the State of Odisha in coordination with
ERLDC.
Coordinates: Drawal schedule from State sector generators, CGPs,
Bilateral trading and Open Access.
Provides : A venue for intra and regional power exchange.
Telemeters : Live data from major generating plants and sub-stations in
the State
Issues : Clearance for outage of elements for maintenance work
including State sector Generators
Supplies : Management information about performance of system
operation
Monitors: Generation, power flow in major lines & tie lines frequency
and voltage & complies ISGS drawal schedule.
Endeavors: To maintain network security and grid discipline.
Ensures: Compliance of all directions issued by RLDC to STU /
Generating companies / any other licensee of the State
FREQUENCY CONTROL & LOAD GENERATION BALANCING
These congestions are well identified. The anticipated power flow pattern
along these flow gates has a direct impact on the Total Transfer Capability
(TTC) in different seasons. While carrying out the system studies for arriving
at the TTC and ATC figures anticipated flow pattern along these flow gates
need to be checked under and in real time require to be monitored for a
secured operation.
The various flow gates and their characteristics and actions required to be
taken by the system operators during congestions in these flow gates are
being monitored by the System Operator on real time basis
CONSTRAINTS IN TRANSMISSION NETWORK
It is imperative that the power exchanges of the state contained to a level of ATC
and in no case exceed the TTC of the state. All the users of state network and / or
neighboring state(s) will adhere to their levels of net interchanges as advised by
SLDC/ERLDC whenever such breach in TTC level among the states takes place
to ensure the grid security irrespective of frequency and schedule.
The assessed TTC, TRM and ATC shall be posted on SLDC website.
The detailed procedure for assessment of TTC, monitoring and invoking
congestion conditions in real-time, application of Congestion Charge and
Congestion Charge accounting and settlement shall be as per the regulation /
procedure issued / approved by CERC
Critical Flow gates
CSG/ISGS BSA
ABT
DISTCOS
OHPC PPA OPTCL
[TRANSMISSION LICENSEE]
PPA GRIDCO
OPGC [POWER PURCHASE & BULK SUPPLY]
PPA
OTHER STATES
IPP
LoI
CGP
CENTRAL POWER SECTOR
PANDIABIL(PG) I MENDHASAL
O MERAMUNDALI KANIHA
II
P MERAMUNDALI ANGUL (KANIHA)
PANDIABIL(PG) DUBURI (N)
BARIPADA (PG) DUBURI (N)
T MERAMUNDALI ANGUL (BOLANGIR)
BISHRA I TARKERA
C ATRI PANDIABILI
SAMANGARA PANDIABILI
II
L JODA (JSPL) JAMSEDPUR
KANIHA RENGALI PH
KORBA
II
I BUDHIPADAR
Y II
KANIHA
MERAMUNDALI I
RAYGARH II
III
BUDHIPADAR S MERAMUNDALI II KANIHA
KATAPALI BOLANGIR PG
BARIPADA (PG) I
II
BALASORE T BOLANGIR NEW BOLANGIR PG
LEGEND:
400 kV -
220 kV -
132 kV -
MONITORING OF DRAWAL
CENTRAL SECTOR
POWER
STATE
~
DEMAND GENERATION
32
POWER FLOW MECHANISM
Mapping from Financial Sector
•Money may be
deposited at any
location
•Withdrawal from
nearest source of
money
33
INSTALLED CAPACITY All Figures in MW
SL.NO. NAME OF POWER STATION INSTALLED CAPACITY FIRM POWER (MW)
1 O.H.P.C.
HIRAKUD POWER STATION
(a)BURLA 2x49.5 = 99 134
2x32 = 64 220.5 Combined capacity of # 5&6 has been
derated to 20 MW as per OERC order
20+1x37.5 = 57.5
(b)CHIPLIMA 3x24 72
BALIMELA POWER HOUSE 6x60 + 2x75 510 135
RENGALI POWER HOUSE 5x50 250 60
UPPER KOLAB POWER HOUSE 4x80 320 95
INDRAVATI POWER HOUSE 4x150 600 224
MACHHKUND POWER HOUSE 3x17 = 51.00 36 30
( Orissa Share 30%, Purchase upto 20% extra) 3x23= 69
TOTAL HYDRO (A) 2008.5
2 N.T.P.C.(TAKEN OVER)
TTPS STAGE-I 4x60 = 240 160.2 160.2 (Auxilliary 10.5 %, Avalability
(Auxilliary 80%)
10.5 %,
Avalability
80%)
TTPS STAGE - II 2x110 = 220 146.85 146.85 (Auxilliary 10.5 %, Avalability
(Auxilliary 80%)
TOTAL TTPS 460
3 O.P.G.C.
IB TPS 2x210 = 420 342.09 342.09 (Auxilliary 9.5 %, Avalability
(Auxilliary 90%)
TOTAL THERMAL (B) 880
CENTRAL SECTOR SHARE
CENTRAL SECTOR GENERATION
SL.NO. NAME OF POWER STATION INSTALLED CAPACITY OPTCL’S SHARE OF AUX. % AGE
INSTALLED CONS. AVAILABILITY
CAPACITY 0N (excluding UA)
REALTIME BASIS.
% age MW % %
1 CHUKHA (BHUTAN) 4 x 84 = 336 15.19 41.00
(Considering 270 MW, 85
total availability )
2 TALA(BHUTAN) 6 x 170 = 1020 4.25 43.40
3 FARAKKA (WEST BENGAL) 3 x 200 = 600 14.18 226.88 7.5 77.91
2 x 500 = 1000
1 x 500 = 500 17.06 85.75 85
4 KAHALGAON (BIHAR) 4 x 210 = 840 15.24 132.47 9 53.98
3 x 500 = 1500 2.05 39.30 9 62.11
5 TSTPP, KANIHA (ORISSA) 2 x 500 = 1000 32.26 323.40 7.5 85
5000
4500
4000
DEMAND IN MW
3500
3000
2500
2000
1500
1000
500
0
Apr'16 May'16 June'16 July'16 Aug'16 Sept'16 Oct'16 Nov'16 Dec'16 Jan'17 Feb'17 March'17
Peak 4082 4025 4049 4124 4166 3969 4051 3921 3984 3896 3960 4551
Average 3258 3159 3205 3253 3173 3147 3066 2800 2740 2859 2951 3237
PEAK & AVERAGE DEMAND
FOR FY 2017-18 (3317 MW)
5000
4500
4000
DEMAND IN MW
3500
3000
2500
2000
1500
1000
500
0
Apr'17 May'17 June'17 July'17 Aug'17 Sept'17 Oct'17 Nov'17 Dec'17 Jan'18 Feb'18 March'18
Peak 4281 4203 4008 4271 4225 4472 4685 4122 4236 4260 4277 4617
Average 3489 3451 3177 3318 3385 3593 3607 2961 2929 3113 3282 3498
ELECTRICITY GRID IN INDIA
‘Electricity grid’ in India evolved from small state system in 1960s to regional
grids in 1980s and finally to a national grid in 2013.
Five electrical regions in the country namely, Northern, Eastern, Western, North
Eastern and Southern, divided geographically. All the states and union territories
in India comes under either of these regions.
Grid Management in India is carried out on national / regional / State basis. All
the regions except Southern region were operated in a synchronous mode prior
to 31st December 2013 forming NEW grid.
Southern region was synchronized to the NEW grid on 31st December 2013
through 765 kV single circuit Sholapur-Raichur line. Thus, the mission of ‘One
Nation – One Grid – One Frequency’ has been successfully accomplished.”
Electricity can flow seamlessly across all the regions as per the relative load
generation balance.
ELECTRICAL REGIONS
States under-
WR – Gujrat, Maharastra,
Goa, M.P, Chatisgarh
SR – Karnataka, A.P,
Tamilnadu, Kerala,
Pandicheri
ER – Orissa, Bihar,
Jharkhanda, W.B, Sikkim.
NER- Meghalaya,
Arunanchal Prades, Assam,
Nagaland, Manipur,
Mizoram, Tripur
FORMATION OF NATIONAL GRID
CAPACITY- 3,44,002.39 MW
3,916.63 MW
AS ON 31.03.2018
92,967.45 MW 33,402.16 MW NE
N
Power Supplier
1,11,148.99 MW
W ISLANDS- 52.61 MW
S
1,02,514.57 MW
CAPTIVE- 40,726 MW
250000
ALL INDIA INSTALLED CAPACITY
222906.59
200000
150000
MW
100000
69022.39
45293.42 40726
50000
6780
0
Thermal Nuclear Hydro RES Captive
REGIONAL LOAD – CHARACTERISTICS
NLDC
RLDC
RLDC
RLDC
RLDC RLDC
(g) Coordination with Regional Load Dispatch Centres for the energy
accounting of inter-regional exchange of power.
(h) Coordination for restoration of synchronous operation of national grid
with Regional Load Dispatch Centres.
(i) Coordination for trans-national exchange of power.
(j) Providing Operational feedback for national grid planning to the
Authority and Central Transmission Utility.
(k) Levy and collection of such fee and charges from the generating
companies or licensees involved in the power system, as may be specified
by the Central Commission.
(l) Dissemination Of information relating to operations of transmission
system in accordance with directions or regulations issued by Central
Government from time to time.
JURISDICTION OF LOAD DESPATCH CENTERS
NLDC:
Apex body to ensure integrated
operation of National Power System
RLDC:
Apex body to ensure integrated
operation of power system in the
concerned region
SLDC:
Apex body to ensure integrated
operation of power system in a state
LDCs AS SYSTEM OPERATOR
• Responsible for Secure and Reliable operation
• Increased complexity due to
– Fast growth - Interconnection size
– System inadequacies - Deployment of new technology
– Diversity - Increased frequency of natural calamities
– Number of Utilities
• Future challenges
– Deployment of new technology
– Wide Area Measurement - Intelligent grid
– Distributed Generation - Sabotage
– Cyber security
• Essential requirements at LDCs
– Technical know how - Experience
– Situational Awareness - Precision -Response time
LDCs AS MARKET OPERATOR
• Energy scheduling
• Open Access, Market Information System
• Metering, Energy Accounting, Settlement
• Pool account administration
• Increased complexity due to
– Increased number of players, Freedom and choice
– Evolving market mechanisms, regulations
– Commercial consciousness and Time constrained activity
• Vital elements
– Non-discriminatory and transparent approach
– Efficient and professional handling of market mechanisms
OTHER ROLES OF LDCs
• LDCs as agent for economy and efficiency
– Merit order scheduling
– Energy conservation, Demand Side Management
– Reactive power management, Transmission loss optimisation
– Exploiting arbitrage opportunities
• LDCs as change agents in reform process
– Implementation of new mechanisms
– Proposals for system improvement
– Consensus building
• LDCs for feedback to
– Policy makers, Regulators, Planners, Technologists, Educational institutions
COMPLIANCES OF SLDC DIRECTIONS
(1) The State Load Despatch Centre in a State may give such directions
and exercise such supervision and control as may be required for
ensuring the integrated grid operations and for achieving the maximum
economy and efficiency in the operation of power system in that State.
(1) The Regional Load Despatch Centre may give such directions and
exercise such supervision and control as may be required for ensuring
stability of grid operations and for achieving the maximum economy and
efficiency in the operation of the power system in the region under its
control.
100.00
50.00
0.00
49.66 49.68 49.70 49.72 49.74 49.76 49.78 49.80 49.82 49.84 49.86 49.88 49.90 49.92 49.94 49.96 49.98 50.00 50.02 50.04 50.06
Highlights of deviation charges
Charges for deviation for each 0.01 Hz step is equivalent to 35.60 Paise/kWh in the
frequency range of 50.05-50.00 Hz, and 20.84Paise/kWh in frequency range below
50 Hz to below 49.70 Hz
Provided that
(i) The charges for the Deviation for the generating stations regulated by
Commission using coal or lignite or gas supplied under Administered Price
Mechanism (APM) as fuel, when actual injection is higher or lower than the
scheduled generation, shall not exceed the Cap Rate of 303.04 Paise/kWh.
(ii) Provided that no cap rate shall be applicable with effect from the date of
revision of price of APM gas by Govt. of India on the charges for the Deviation
for the generating stations regulated by consumer using gas supplied under
Administered Price Mechanism (APM) as the fuel.
(iii) the charges for the Deviation for the under drawal by the buyer in a time block
in excess of 12% of the schedule or 150 MW, whichever is less, shall be zero.
(iv) the charges for the Deviation for the over-injection by the seller in a time block
in excess of 12% of the schedule or 150 MW, whichever is less, shall be zero,
except in case of injection of infirm power by a generating station during
testing prior to COD for a period not exceeding six months.
Limits on Deviation volume
(1) The over-drawals / under drawals of electricity by any buyer
during a time block shall not exceed 12% of its scheduled
drawal or 150 MW, whichever is lower, when grid frequency
is “49.70”Hz and above"
Over drawal / under injection in excess of 20 % 100 % of the charges for deviation corresponding
to the block frequency. 100 % of cap rate of
303.04 paise/ Kwh for sellers whichever is less.
(ii) Any drawal of power by a generating station prior to COD of a unit for
the start up activities shall be exempted from the levy of additional
Charges of Deviation.
132 kV
33 kV
Transmission
System 33 kV
220 kV 11 kV
11 kV
m
m
440V
Generating Distribution
Station System 87
Consumer
STRUCTURE OF POWER SYSTEM
Trading, now a licensed activity and will also help in innovative pricing
which will lead to competition resulting in lowering of tariffs.
1. Short Term Open Access (STOA): open access allowed for the
period of less than one month.
Intra State Open Access: When buying and selling entity belongs to
same state. In this case SERC regulations are followed. In Odisha, it is
further categorized as STOA and LTOA.
2. Short Term Open Access (STOA): customers other than the long
term customers with maximum duration for which the short term
access allowed at a time shall not exceed one year.
CRITERIA FOR GRANTING OF SHORT TERM O A
• CGP shall have the right to Open Access for the purposes of carrying
electricity from his captive generating plant to the destination of his use.
DOP-1
Adv
Application FCFS
for M2
Adv
Application for
M3,
Approvals for
M2
Adv
Application for
M4, Day Ahead /
Approvals for PX LEGEND:
M3
DOP : Day of Operation
DL : Last day of M1
Approvals for
M4
New Open Access Regulations w.e.f.
01-April-2008
Open Access Regulations, 2008:
Provisions For Collective Transactions
With all the buyers and sellers bid-price, two separate curves
are being plotted by the Exchange.
Purchase price
Sail price
Price
Quantity
The supply curve shows the relationship between its price and the
amount of electricity the producers are willing to sell, the demand curve
indicates the quantum of electricity the buyers willing to purchase
provided the price is equal or less that the bid price, other things held
constant
The intersection of two curves is the equilibrium point, which determine
the volume of electricity and the sell price at that hour / block
Illustration of a typical
Bilateral Transaction
Quantum : 20 MW
NETWORK INVOLVED
Co-ordination for Scheduling,
JSL, Odisha
Settlement & System Operation by
CPP
Seller
OPTCL SLDC-OPTCL
Seam
Changes ER ISTS ERLDC
NR ISTS NRLDC
Haryana SLDC-Haryana
Buyer
JSL, Hissar
TRANSMISSION CHARGES
HARYANA OPTCL
36 paisa per unit 6.25 paisa per unit
NR ISTS ER ISTS
16.89 paisa per unit 16.89 paisa per unit
HARYANA OPTCL
3.93% Loss 3.75% Loss
19.116MW 19.75MW
WR ISTS ER ISTS
Withdrawal PoC Loss Injection PoC Loss
2% 1.23%
19.507MW
OPEN ACCESS TRANSACTIONS
5000
4564
4500
4000 3783
3464
3500
3000
MU
2500
2000 1866
1500
883
1000 829
500
0
2010-11 2011-12 2012-13 2013-14 2014-15 2015-16
YEAR
Thank you