HAKONE
ESTABLISHMENT OF SHOWCASE ENMS FOR SUSTAINABLE
EC PROMOTION IN ENERGY INTENSIVE INDUSTRY IN
INDONESIA
1) Establishment and Dissemination of showcase
EnMS in Industry based on ISO 50001
2) Development of Pilot Project ( S ) Possible by
ESCO Scheme.
3) Requirement for Goverment Support.
1. Background
2. Target / Expected Results
3. Problems or Barrier
4. Counter Measurements
5. Action Plan, Time Schedule, and Investment Analysis
6. Conclusion
b Management Responsibility
c Energy Policy
d Energy Planning
f Checking
h Sertification
Countinual Improvment after getting
2
Sertification ISO 50001 all industry
Energy Material Balance and SEU
3
implementation
To Make Fisibility Study of SEU to Propose of
4
Financial Shceme
5 Register the Pilot Project to JCM / METI
MOU betwen
Result and
Indonesia Need Support by Indonesian
Feedback from Investment Install and Energy
Absorption Chiller Register JCM Goverment with Goverment and Japan Goverment
JCM Periode Comissioning Monitoring
JApan
1 2 3 4 5 6 7 8 9 10 11 12
3 PT. Sri Rejeki Isman Tbk
1 2 3 4 5 6 7 8 9 10 11 12
Instalation of VSD for Fan at AC Cabin system Invesment By PT. Apac Inti Corpora
Replacement Fluorescent Lamp to LED lamp Invesment By PT. Apac Inti Corpora
Need Support by Indonesian
Replacement Screw Compressor With centrifugal
Goverment and Japan Goverment
Compressor
Motor belt replacement on Roving & Ring Frame Need Support by Indonesian
machines Goverment and Japan Goverment
6 PT. Pura Barutama
Installation of 75KW VSD for fan pump Invesment By PT. Pura Barutama
Installation of 250KW VSD for hydra pulper SM12 Invesment By PT. Pura Barutama
7 PT Pura Nusapersada
Modification chain grade to FBC Boiler (Hamada) Invesment By PT. Pura Nusapersada
Installation of 315KW VSD for fan pump Invesment By PT. Pura Nusapersada
Installation KWH Meter (measurement unit) to SDP Invesment By PT. Pura Nusapersada