Академический Документы
Профессиональный Документы
Культура Документы
2
I am Muhammad Sajjad Akbar
Reg. No : NDU/F-15/LMS/MSPM-067
3
First of all, I convey my sincere
thanks and regards to all
respected teachers
ALTERNATE DISPUTE RESOLUTION; ANALYZING THE
EFFECTS OF LITIGATION ON TIME AND COST OF
PROJECTS.
Introduction
Problem Statement
Research Gap
Research Question
Research Objective
Significant of Study
Literature Review
Theoretical Framework
Reliability Test
Validity Test
Analysis
Results of CLRM
Hypotheses Testing
Discussion
Contribution
Conclusion
Future Direction
ABSTRACT
The Contractual stipulations regarding time and cost are the two criterions for
determining the success of project.
In Pakistan, most of the construction projects face time and cost overruns,
mainly due to disputes amongst the stakeholders. Disputes are directly
proportionate to time and cost overrun. This is a global phenomenon in the
construction industry, to which Pakistan is not an exception.
Earlier studies in this regard have focused upon the respective effects of
litigation and alternate dispute resolution, independently.
The instant study aims to investigate the success of both procedures, jointly.
Moreover, the role of contract management has also been investigated as
moderator.
Primary data was collected from professionals / experts conversant with the
litigation; non-probability, convenience, snow ball, and random sampling
techniques were adopted.
The findings of study revealed that disputes are positively associated with the
time and cost overrun (β = 1.129, P-value < 0.01);settlement through litigation
has an adverse impact (β=0.228, P-value <0.01); whereas, alternate dispute
resolution reduces the time and cost overrun (β=-0.066, P-value <0.05). The
contract management plays a vital role in both situations.
On the basis of results, study recommends the use of alternate dispute
resolution technique for dispute settlement for success of project rather
traditional formal method of litigation.
Introduction of Variables
Introduction of Topic
Introduction of Variables
The term Alternate dispute resolution (ADR) includes within its domain multiple informal
procedures for resolution of disputes among parties to contract. This is a process of dispute
resolution other than traditional formal process through courts.
Mediation Dispute
& Resolution
Negotiations Conciliation Board Arbitration
It is the process of resolving disputes through presentation before court of law of legal
jurisdiction. This is the most formal mechanism with pre-defined protocols and time lines.
The presentation can not be made with out legal counsel. This is a constitutional protected
method of dispute settlement.
Time & Cost overrun
Project time refers to the time lines agreed between parties for completion /
closing. Cost represents the amount /money for executing a certain projects.
The completion of project beyond contract stipulated time line is called time
overrun and cot spent in access of assigned amount is cost overrun.
Introduction of Topic
• The dispute are inevitable in the construction industry world wide to which
• Due to above and other reasons, disputes are bound to occur. As a result of
disputes, project completion period extends and also the cost at completion
exceeds the estimated cost. Parties in contract attempt to resolve the disputes
in interest of project and for ensuring project success. Rather parties in
dispute attempt to curtail time and cost overrun for their mutual benefit.
Because heavy financial implications are always associated with the disputes
litigation further adds to time & cost overrun. That is litigation renders the
Consequently due to huge delays and hiking costs, most of the projects either
become financially unviable or are abandoned by the parties.
Problem Statement
A lot of research has been conducted for understanding the affect of disputes,
ADR and litigation on time & cost overrun INDEPENDENTLY.
Whether ADR results into less time & cost overrun than the litigation.
How Contract Management effects on Time and Cost overrun when disputes
are resolved through litigation?
How contract management affects the project success when disputes are settled
through ADR.
Research Objectives
Contract Management
CM
LT
CD TC
ADR
HYPOTHESES OF THE STUDY
Hypothesis 1: Causes of delay and time & cost overrun are positively associated.
Hypothesis 3: Alternate dispute resolution and Time & cost overrun associated.
Hypothesis 4: Litigation mediate the relationship between causes of disputes and time &
cost overrun.
Hypothesis 5: Alternate dispute resolution mediates between Causes of delay and time
& cost overrun.
Hypothesis 6: Contract management affect the relationship between Causes of delay and
time & cost overrun.
Time Horizon
• The elements of the targets population who are willing and voluntarily
available to participate in the study constitute the sample.
Sampling Technique.
• The data is collected through friends and referral networks. And from the
professionals who were voluntarily ready to submit their responses. Among
volunteers, we selected randomly who were conversant with the topic.
Sample Size.
• Pilot study has been conducted with structured questionnaire for verifying
the reliability and validity of the instrument through Chronbach Alpha (α)
and factor analysis. Also through relative importance index (RII) and
ranking (R) of the statement.
• The primary data collected above is then checked for outlier and
normality.
Following measures are adopted and tailored for the instrument for
research by deleting and adding statements.
• The value of Chrombach Alpha both for pilot and main research are
found above 0.7.
• The results suggests that data is good enough for analysis and
conclusion therefore.
Normality of Variables
Statistics
CD LT TC ADR CM
CD1 CD2 CD3 CD4 CD5 CD6 CD7 CD8 CD9 CD10
N Valid 210 210 210 210 210 210 210 210 210 210
0 0 0 0 0 0 0 0 0 0
Missing
Skewness -1.995 -1.040 -1.472 -1.219 -1.061 -1.536 -1.016 -1.041 -.815 -.335
.168 .168 .168 .168 .168 .168 .168 .168 .168 .168
Std. Error of Skewness
Kurtosis 0.994 1.330 1.447 1.353 1.182 0.109 -.096 0.276 .267 -1.163
.334 .334 .334 .334 .334 .334 .334 .334 .334 .334
Std. Error of Kurtosis
Content Validity Validity
Convergent Validity
Discriminate Validity
Content Validity
The content validity is ascertained by the discussion with field professional
in preliminary pilot study. Each construct of a measure is discussed in detail
regarding the ease and proper understanding of the respondents. Moreover,
Internationally published instrument are taken as reference.
• Litigation – Measure by (Anika Gill, Jason Gray, 2015)
• Alternate dispute resolution (ADR)- Measure by (Anika Gill, Jason 2015)
• Contract Management –Measure by (Jade Hall, 2014)
• Causes of delay – Measure by (G.Sweis, R. Sweis, 2007)
• Time & Cost overrun –Measure by (Bench mark study Dubai)
Validity
Convergent Validity.
Approx df Sig.
The KMO values for all variables are found greater than 0.75 and
Barletts test was significant at 1% probability.
• After reliability test, the data was then subjected factor loading test.
• Factor loading test facilitated the reduction of data. Factors with eign
value greater than 1 are retained for further analysis.
• Nunnlay (1967) recommends that factors beyond 0.635 are considered
to be sufficient for exploratory studies. Dimovsi (1994) recommends
a range of 0.5 – 0.6 are good to be taken in further analysis.
• On the basis of results of factor loading test for validity, the most
relevant items are retained.
• The same was tested through descriptive test ( Relative importance
index & Ranking).
No of items before factor No of items after factor
loading loading
Causes of delay 37 10
Litigation 12 10
Alternate dispute 5 5
resolution
Contract management 10 5
94 42
74.76% are males and 40.95% of the respondents 71.9% of the respondents
67.14% of the respondents
25.24% are females. It are executives. 76.76% are were having qualification of
were above the age of 40
represents the realistcity of middle above level BS and Mphil. 28.18%
years. It means data has
data as most of the managers and 23-34% are were legal professionals and
been collected from mature
professionals conversant low level managers. It again above. The data was again
respondents.
with litigation are males. dictates that data can be highly relevant as the topic
reliably used for study as is related to theoretical
the respondents are senior knowledge.
level professionals.
Descriptive Analysis
Variables Mean Standard Deviation
• CLRM Analysis
Underlying Assumptions of Regression Analysis
• Tests of Multi-co-linearity
• Tests of Normality of Residuals.
• Tests of Homeosekadasticity (White test)
• Test of independence of data (Durbin Watson)
• Test of Correlation.
Test of Multi co-linearity.
Coefficients
Tolerance VIF
• The results of heterosekadasticity test for Disputes and Time & cost
overrun is as under.
Heteroskedasticity Test: (White test)
• Value of F-stat 12.14 > F-critical = +3.0 and P-value < 0.01 suggests
that there is no issue of hetersekadacity.
Test of Independence of data (Durbin Watson)
Litigation 2.48
TC CD LT ADR CM
• The above table dictates that all of the variables are statistically
associated. It was therefore considered adequate to perform
regression analysis.
RESULTS OF CLRM
TC = -0.683 + 1.129 CD
TC = -1.69 + 0.543 LT
TC = -3.36 + 0.163 ADR
TC = 0.591+ 0.875 CD + 0.228 LT
TC = -0.594 + 1.169 CD -0.066 ADR
TC = 0.049 + 0.753 CD – 0.045 X1
TC = -0.131 + 0.652 CD + 0.211 LT +0.028 X2
TC = 0.041+0.818 CD – 0.047 ADR - 0.043 X3
Hypotheses Testing
Hypothesis No. Independent Variables Dependent Variables Regression Co-efficient Decision
Litigation 0.228***
H -5 Causes of delay Time & cost overrun -0.066** Accepted
Contract management
-0.045***
Litigation 0.211***
Contract Management
0.028***
Contract Management
-0.043***
Discussion
• Disputes are positively associated with time and cost overrun.
• The critical causes which converts into disputes are extracted as
under.
Progress payment
Discrepancies in documents
Modifications due to poor document
Change orders
Finance Related
Ambiguities in documents
Change in specifications
Lack of co-ordination
Disputes
69