Exercise 1
Discussion
You are looking at the reserves & resources for the LEMAN field, in Nigeria.
The PSC terms are for 10+5+5 years after the first booking of reserves, with a possibility to renew and renegotiate
during the last extension. The field has been discovered in 2005 through the LA1 well (in the west – block A). The
well was not completed and undeveloped reserves were booked.
In 2008, the block D was drilled and because the operator was cash constrained, only the eastern flank has been
producing for several years through 3 only producers (LD1, LD2 & LD3) in the flank (It is well known that things are
moving slowly around the LEMAN…).
9320
9300
Today, the wells are declining, and a redevelopment plan is presented. 9280
D
9260
C LD4 LD2
A B 9320 9240
LD1 LD2-ST1 9300
Also: 9320 9300 9220 9320
9300 9320 LC1
LA3 9300
9280
- Oil price is 70 USD/stb 9260 LB2
LD7 LD5
LA4 9200 LD8
- Fixed OPEX is USD25.55 million/annum 9280LB1
9300 9220
LA1
- There is no taxes at all. 9240 9300 9320 LD3 9280
9240
9260
9260
- ABEX is estimated at 250 million USD 9280 9320
LD6
LA2 9300
9320
Discussion
The current plan redevelopment plan is divided into several projects, presented as follows:
- Drilling of 1 side-track well (LD2 ST1) in the northern part of the D block – the drilling is finished but the well is
not completed yet.
- Drilling of 3 new wells in the flank and 2 wells in the attic of the reservoir – this is approved
- Drilling of LB1 well in the B block (approved), with the LB2 well pending.
- Drilling of 1 well in the C block (currently investigated)
- Development of the block A through 3 wells. The project is cash flow positive and is approved internally,
although the formal approval from the authorities is only expected in 2019.
- Water injection is considered and is being investigated
The gas production is steady, but it cannot be monetized as there is no market available
9320
9300
9280
D
9260
C LD4 LD2
A B 9320
LD1
9240
LD2-ST1 9300
9320 9300 9220 9320
9300 9320 LC1
LA3
9280 9300
9260 LB2
LD7 LD5
LA4 9200 LD8
X LA1
9280 LB1
9300
9220
9240
9240 9300
9320 9260
9260 LD3 9280
9280
LD6
9320
X'
LA2 9300
9320
Producer
Planned well
Section X-X'
Distance [m]
1000
1200
1400
1600
1800
2000
2200
2400
2600
2800
3000
3200
3400
3600
3800
4000
4200
4400
4600
4800
5000
5200
5400
200
400
600
800
0
9100
9120
9140
9160
9180
9200
9220 TBC
Depth [ft]
9240
?? ??
9260
9280
9300 ?? ?
9320
9340
9360
9380
9400
- Current rate = 265 stb / d - Current rate = 0 stb / d - Current rate = 300 stb / d
- BSW = 69% - BSW = 99% - BSW = 78%
- CumOil = 3.9 MMstb - CumOil = 2.4 MMstb - CumOil = 4.1 MMstb
- EUR [4.0, 4.25, 4.5] MMstb - EUR 2.4 MMstb - EUR [4.2, 4.6, 5.3] MMstb
- Reserves = [0.1, 0.35, 0.6] MMstb - Reserves = 0 MMstb - Reserves = [0.1, 0.5, 1.2] MMstb
1200.00
Oil Rate [stb/d]
800.00
1000.00 1000.00
600.00
Feb-08
Jul-09
Nov-10
Apr-12
Aug-13
Dec-14
May-16
Sep-17
Feb-19
Jun-20
Feb-08
Jul-09
Nov-10
Apr-12
Aug-13
Dec-14
May-16
Sep-17
Feb-19
Jun-20
Feb-08
Jul-09
Nov-10
Apr-12
Aug-13
Dec-14
May-16
Sep-17
Feb-19
Jun-20
Time Time Time
DCA: Rate Vs CumOil DCA: Rate Vs CumOil DCA: Oil Cut Vs CumOil
1810.00 2510.00 1.2
1610.00
2010.00 1.0
1410.00
1210.00 0.8
Oil Rate [stb/d]
1510.00
1010.00
Oil Cut
0.6
810.00
1010.00
610.00 0.4
410.00 510.00
0.2
210.00
A B C D Total
Low Mid High Low Mid High Low Mid High Low Mid High Low Mid High
STOIIP [MMstb]
RF
RF+
CumOIl
Developed reserves
Developed EUR to date
Total EUR (recoverable) through primary recovery
Total EUR with water injection
Remaining max "reserves" without Injection
Remaining max "reserves" with Injection
A B C D Total
Low Mid High Low Mid High Low Mid High Low Mid High Low Mid High
Reserves Manager Comments
Recovery for water injection (max potential)
NFA
Project 1
Project 2
Project 3
Project 4
Project 5
Project 6
Project 7
Project 8
Total EUR
Reserves
Developed producing
Developed non producing
Undeveloped
Contingent Resources
Prospective resources
Pi : initial pressure
GOR: Gas Oil Ratio (amount of gas dissolved in oil) – above 500 scf/stb, we generally have light oil
RSI : initial GOR (as the GOR will change with pressure)
BSW: water cut = water production / (oil production + water production). A new well should have 0% BSW, and a dead well will
have close to 100% water cut