AGCHEM CONSTRUCTION AND DEVELOPMENT

CORPORATION
195 Dona Soledad Extn., Better Living, Paranaque City, Philippines 1700

DATE PRESENTED:
APRIL 10, 2019
Table of Contents:

 1.0 INTRODUCTION
 1.1 Company Background

 2.0 PLUMBING SANITARY WORKS


 2.1 MAIN COMPONENTS
 2.1.1 Storm Drainage System
 2.1.2 Sewer and Ventilation System
 2.1.3 Water and Distribution System
Table of Contents:

 Methodology
 3.1 WATERLINE INSTALLATION
 3.2 SANITARY LINE INSTALLATION
 3.3 ACUWS COLLECTOR INSTALLATION
Table of Contents:

 4.0 TESTING AND COMMISSIONING

 5.0 SCHEDULE OF EQUIPMENT

 6.0 SAFETY PRECAUTION


Our Company Agchem Construction and Development Corporation
195 Dona Soledad Extn., Better living, Paranaque City

On January 1, 1995, Agchem underwent the most significant changes since its inception.
A substantial shift in ownership resulted to a major change in management. Those changes affected not only the
structure of our organization but also our culture and philosophy.
Today, Agchem will provide its customers quality and affordable services to fulfill their needs. Our organization will
pursue newer markets and products and enhance its marketing-client relationship. We will seek and continue to
modernize our processes.
The primary thrust of the new Agchem is that customers come first. We are determined to improve the quality of our
service to customers, whoever they might be.
Our people make this possible, through an acceptance of individual responsibility and accountability, through co-
operation and teamwork.
Our business success is the key to our future. Our aim is to operate profitability, but with full recognition of our vital
social role, and to be measured as one of the most efficient and effective construction companies in the country.
The principles of quality services and products, cooperative management, open exchange of knowledge and success
for all involved are fundamental concepts adopted by our organization.
PLUMBING SANITARY SCOPE OF WORKS

It is the art and Technique of installing pipes, fixtures and other apparatus in the Building for bringing in the supply
of liquids and substances and/ or ingredients and in removing them.
(from the Latin Plumbum for lead, as pipe were once made from lead) is the skilled trade working with pipes, tubing
and plumbing fixtures for drinking water systems and the drainage waste. The Plumbing industry is a basic and
substantial part of every developed economy due to need of clean water, and proper collection and transportation of
waste.
Plumbing also refers to a system of pipes and fixtures installed in a building of potable water and removal of
waterborne waste. Plumbing is usually distinguished from water and sewage system, in that plumbing serves one
building, while water and sewage serve a group of buildings or a city.
MAIN COMPONENTS OF PLUMBING SANITARY

STORM DRAINAGE SYSTEM

SEWER, WASTE AND VENT SYSTEM

WATER SUPPLY AND DISTRIBUTION SYSTEM


WATER SUPPLY AND DISTRIBUTION SYSTEM
MAIN WATER METER – records the volume of water delivered at the building. As a rule of
thumb, the size of the water is usually one size lower than the size of the supply pipe.
2.1.3 WATER SUPPLY AND DISTRIBUTION SYSTEM
WATER SUPPLY AND DISTRIBUTION SYSTEM
2.1.3 WATER SUPPLY AND DISTRIBUTION SYSTEM
PRESSURE REDUCING VALVE DETAIL

key plan
WATER SUPPLY AND DISTRIBUTION SYSTEM
RISER

This is the name conduit that brings water from the Domestic tank to the Elevated water tank at roof
deck.

DOWN FEED
UPFEED

TRANSFER PUMPS

WATER TANKS ( By others)


Basement Water Tanks ( Domestic Storage Water Tank )
Roof Deck Water Tank (Elevated Water Tank )

BOOSTER PUMPS and BLADDER TANK


This use to increase the pressure within the system.
METHODOLOGY
 WATERLINE INSTALLATION METHODOLOGY

Installation Procedures
a. Carry out examination of physical site condition of the area for ongoing activities, blockages
of egress, height restrictions feasibility .

b. Check material is approved by the consultant.

c. Ensure materials is properly stored using pipe rack.

d. Ensure safe access to working area.

e. Install necessary scaffoldings and make it safe to use by a certified or qualified person.

f. Prepare and fully sign Work Permit.


FOR PPR PIPE
Methodology of Testing

After completion of the piping installation, have it inspected by Agchem QAQC,


MDC MEPFS Engineer and BV Engineer. In case that there are punch list issued,
have the punch list be closed and seek the approval of the inspector and
prepare for testing.
Visual Inspection
Check that the pipework installed is per approved shop drawing (IFC).
Check the pipe size as per IFC drawing.
Check measurement for on center positions of fixture tapping point (inside toilet)
Check the pipe sleeve and wall penetration are installed.
Check spacing of hanger and support is as per IFC drawing.
Check the plumpness of vertical pipes is as per IFC drawing.
Testing and Commissioning

Pressure Test

All pipe ends shall be plugged and sealed.


Provide an air release valve at the highest portion of the pipe
Fill the pipe line with water using a test pump and build up the pressure in stages.
Bleed the pipe line thru the air release valve to free the system from the air
pocket.
Test pressure shall be 150 psi or 1.5 times the system working pressure.
Allow the pressure to stand for two (2) hours during which time there should be
no drop in test pressure.
In the event of pressure drop, inspect all piping and locate the leak
Repair and re-test until such portion or section satisfactory passed the test.
WATER SUPPLY AND DISTRIBUTION SYSTEM
WATER METER MANIFOLD SAMPLE
 THREADING OPERATION / METHOD
1. Make sure that machine and work area is properly set up and that the work area is free of bystanders and

other distractions. The operator should be the only person in the area while the machine is operated.

The cutter, reamer and die head should be up away from the operator, do not place in the operating position.

Make sure they are stable and will not fall. Fully open the chucks of the threading machine.

2. Insert pipe shorter from the front of the machine. Insert longer pipes through either end so that the longer section

extends out beyond the rear of the Threading Machine. Confirm that pipe stand are properly placed.

3. If needed, mark the pipe. Place pipe so that the area to be cut or end to be reamed or threaded is approximate

from the front of the chuck. If closer, the carriage may strike the machine during the threading and damage

the machine.

4. Turn the rear centering device clockwise (viewed from rear of machine) to close down onto pipe. Make sure that the

pipe is centered in the inserts. This improves pipe support and gives better results.

5. Turn the front chuck handwheel counterclockwise(viewed from front of machine) to close down onto pipe. Make sure

that the pipe is centered in the inserts. Use repeated and forceful counterclockwise spins of the handwheel to secure

the pipe in front chuck.


THREADING MACHINE PARTS AND SPECIFICATIONS
SUMMARY OF MATERIALS FOR SANITARY/PLUMBING WORKS
DESCRIPTION SIZES SUBMITTED MATERIALS METHOD OF JOINT METHOD OF TESTING
STORM DRAINAGE SYSTEM
Embedded Pipe
1 Parking Waste Stack 100mmᴓ/150mmᴓ G.I SUPREME WELDED/VICTAULIC FLOW TEST/GRAVITY
2 Perforated Pipe 100mmᴓ/150mmᴓ PVC EMERALD SOLVENT
3 Aircon Drain 100mmᴓ PVC EMERALD SOLVENT FLOW TEST/GRAVITY

SOIL WASTE AND VENT


1 Main Collector
Soil 250mmᴓ C.I. ASA/HEAVY DUTY Aokum & EPOXY GRAVITY TEST
2 LATERAL
Soil 100mmᴓ/150mmᴓ C.I. ASA/HEAVY DUTY Aokum & EPOXY GRAVITY TEST
Waste 200mmᴓ/150mmᴓ C.I. ASA/HEAVY DUTY Aokum & EPOXY GRAVITY TEST
Vent 100mmᴓ/200mmᴓ PVC EMERALD SOLVENT -

STORM DRAINAGE SYSTEM


1 Parking Waste Stack 150mmᴓ PVC EMERALD SOLVENT GRAVITY TEST
2 Perforated Pipe 100mmᴓ/150mmᴓ PVC EMERALD SOLVENT -
3 Aircon Drain 100mmᴓ/150mmᴓ PVC EMERALD SOLVENT GRAVITY TEST

SANITARY LINES
1 LATERAL
Soil 50mmᴓ/100mmᴓ/150mmᴓ C.I. TOP ONE Aokum & EPOXY GRAVITY TEST
Waste 50mmᴓ/100mmᴓ/150mmᴓ C.I TOP ONE Aokum & EPOXY GRAVITY TEST
SUMMARY OF MATERIALS
METHODOLOGY
 SANITARY LINE INSTALLATION

Installation Procedures
a. Complete the sanitary lay-out based on the approved IFC plan.
b. Secure the plumbness, sloping and bends of the lay-out before installing. Use level bar for the
checking the plumbness and sloping and check the standard bends for the piping.
c. For gully trap installation, check if all the holes are open and ready for installation of the piping
that will be tapped to gully trap.
d. For piping that will pass through walls, mark the portion where the pipe will pass through, cut
the marked area, use chisel or ball hammer for soft surfaces and chipping gun for hard surfaces.
Provide a one size larger pipe sleeve for the pipes that will pass through the wall. Restore the
chipped wall after the installation.
e. After installing the pipes, provide the hangers and supports. Use hand drill to embed the
support for the hangers. There should be a minimum of 1% and maximum of 2% sloping for
tapping of horizontal piping to vertical or risers.
f. After the completion of the piping, have it inspected by Agchem QAQC, MDC and Bureau
Veritas. In case that there are punchlists issued, have the punchlist be closed and if seek the
approval of the inspectors and prepare for testing.
SAMPLE SANITARY LAYOUT

LAVATORY DRAIN
WATER CLOSET DRAIN GULLY TRAP

VENT LINE
FLOOR CLEAN OUT
Sanitary Line – GRAVITY TESTING
TESTING AND COMMISSIONING
C. Hydrostatic Testing

a. Cold Water System (Vertical Pipes)


After the completion of a section of the system for every nine floors, it shall be subjected to
hydrostatic testing and proved tight under pressure of at least not less than 150psi above static
pressure for 2 hours. The section of the pipeline shall be filled with water and set the pressure
gauge to the specified test pressure measured at the highest elevation by means of a test pump
connected to the system. There shall be no drop in pressure within the required time duration of
hydro testing.
During the test, all exposed pipes, gate valves and fitting joints will be carefully examined and no
leak has to be found. If defects are found it shall be rectified first and the test shall be done
again.

b. Cold Water System (Lateral Pipes)


After a completion of a section of the system for every floor, same testing procedure will apply
to the cold water line lateral pipes.
Water Line
METHODOLOGY
 CONDENSATE DRAIN INSTALLATION

Installation Procedures
a. Complete the FCU drain lay-out based on the approved IFC plan.
b. Secure the plumbness, sloping and bends of the lay-out before installing. Use level bar for the
checking the plumbness and sloping and check the standard bends for the piping.
c. For piping that will pass through walls, mark the portion where the pipe will pass through, cut the
marked area, use chisel or ball hammer for soft surfaces and chipping gun for hard surfaces.
Provide a one size larger pipe sleeve for the pipes that will pass through the wall. Restore the
chipped wall after the installation.
d. After installing the pipes, provide the hangers and supports. Use hand drill to embed the support for
the hangers. There should be a minimum of 1% and maximum of 2% sloping for tapping of horizontal
piping to vertical or risers.
e. After the completion of the piping, have it inspected by Agchem QAQC, MDC and Bureau Veritas. In
case that there are punchlists issued, have the punchlist be closed and if seek the approval of the
inspectors and prepare for testing.
Sample Condensate Drain or FCU Drain
Condensate Drain / FCU – Gravity Test
SAFETY PRECAUTION
Safety Supervisors / Officers
 Their responsibility is to assist others to work smoothly and safely. ■
They have received specific safety training and are important
members of the construction team.

 They have legal responsibility or liability for the overall safety of the
construction site.
RISK ASSESTMENTS

Process Operation
Health and Safety Hazards Condition Condition For Hazards Risk
and
Risk to Happen
Routine Non-Routine Direct Indirect
Use of Scaffold during -Lack of Knowledge of -Fall to the ground
Installation X X Proper Erection of Scaffold -Severe Injury
-Damaged Scaffold used. -Death
-Sub-Standard Platforms
used.
-No Safety Fall Protection
when using scaffold, such
as, Life line and body
Harness.
Installation of Storm -Lack of Knowledge to -Respiratory illness
Drainage System, Soil and X X Installation. -Eye and Skin
Waste Plumbing System, -Poor Ventilation of Irritation/Injury
Domestic Water System Workplace -Burn
and Plumbing Fixtures, -Improper Handling of -Dizziness
pipes and fixtures when -Hand Injury
installation -Severe Injury
-Improper Posture During
Hauling and installation of
pipes
-Inhalation of Plastic Fumes
on Heating pipes Using
Fusion machine.
No PPE, Such as, Hard hat,
Goggles, Dust Mask, and
Cotton Gloves.
Testing of Installed Pipes -Lack of Knowledge on -Slip Incident
and Plumbing Fixtures X X Proper Testing -Damage to Property
-Improper Testing method -Severe Injury
that may cause to
resource Depletion
-Improper usage and
Disposal of water when
testing that may cause to
damage of Property
Primer paint application for -Lack of Knowledge about -Respiratory illness
Personal Safety
 Wear protective equipment.
 Do not drink liquor or take hazardous drugs while working.
 Pay attention to personal hygiene.
 Do not play in the workplace.
 Report to your supervisor immediately if you notice any unsafe
condition
Safety Measures
 Before you operate a machine, ensure that the dangerous part of
the machine has been installed with a guard.
 Avoid going to any area with insufficient lighting as there may be
some dangerous places which have not been provided with
fencing.
 Provide Dust Mask to avoid inhalation of fumes coming from PPR
Pipe.
 Keep vigilant all the time and watch out for moving cranes, hooks or
other lifting equipment.
 Before you use any electrical installation or tool, check the condition
of its electric cables.
 Use and handle chemicals with care.
Safety measures in using tools and
equipment
 Ladder
 Use a ladder which is of good construction, sound material and
adequate strength.
 Examine the ladder before using it and inspect it at regular
intervals.
 Place the ladder on a level and firm footing.
 Place the ladder at an appropriate angle.
 If there are electrical installations nearby, do not use metal
ladders.
Gas Welding and Flame Cutting
 Do not use the equipment for gas welding or flame cutting unless
you have attained the age of 18 years and hold a valid certificate.
 Wear personal protective equipment.
 Keep the workplace clean.
 Place fire extinguishers within reach.
Safety Measures
 Waste Disposal
 Dispose all wastes, and unwanted materials must be disposed at
a designated place.
 Notify your supervisor of the requirement for the separate
disposal of chemical or inflammable wastes.
 Do not leave planks with nails on passageways.
Thank you!