EPM CONSTRUCTION INC.

Address : Mezzanine floor, Emeco Bldg., 209 Doña Soledad Ave,


Brgy Don Bosco, Parañaque City

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


PARK CENTRAL TOWERS

Pre-Activity Training and Orientation on Quality Safety


(PATOQS)
Table of Contents

1.0 INTRODUCTION
1.1 Purpose
1.2 Construction Program
1.3 Company Background
2.0 SCOPE OF WORKS
2.1 Laying of CHB
2.2 Plastering
3.0 WORK METHODOLOGY
3.1 CHB Installation
3.2 Plastering Works
4.0 QUALITY CONTROL
5.0 SAFETY REQUIREMENT
6.0 APPENDICES

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


INTRODUCTIONS

 CONSTRUCTION PROGRAM
The construction programmed for the
 PURPOSE aforementioned work will be carries out in
The purpose of this procedure is to establish accordance with the approved
guidelines on how Pre Activity Training and methodology and existing guidelines set by
Orientation on Quality & Safety are the main contractor. The main objective of
conducted before the start of work activity the contractors is to deliver a quality tile
in support of the managements. installation in accordance with the plans
and specification. This is to be done by
maintaining good workmanship and
satisfactory within the specified period of
construction.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


EPM CONSTRUCTION INC.

EPM is committed to provide the highest level of construction services to


our clients. At EPM Construction, we understand that the ultimate goal of
any construction project is to deliver a facility that meets the needs of its
owners and its end-users. Our expertise in general construction and
specialty construction services allows us to meet a wide range of criteria -
from budget and schedule considerations to functional and aesthetic
requirements.
Our success is achieved upon completion and turn-over of a facility that
fulfills your needs at the highest quality for the lowest reasonable cost.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


2.0 Scope of Works

2.1 Laying of CHB


This procedure provides a
method of control of
block masonry work in
order to achieve
compliance with the
contract specifications
and drawings.
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
2.0 Scope of Works

2.2 PLASTERING
The scope of work consists
of surface preparation,
establishibg of plaster
thickness, plaster mix
preparation and
application, finishing and
curing works.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


3.0 Methodology (CHB LAYING)

B. Using the given


reference line and
A. Secure work
grade (Gridlines, offset
permit before mark,etc.), lay-out the
commencing the wall line on the floor. Use
activity. oil marker (pitik) to mark
this line. This line shall be
the “Finished wall line.”

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


3.0 Methodology (CHB LAYING)

C. Determine the finish


requirement of the wall as
reflected on the approved D. Transfer the “CHB Wall
wall setting/layout plans Line” to the adjacent wall/
(plaster, stone, cladding, bare, structure to have a vertical
etc.). From the Finished Wall “CHB Wall line”. It is critical to
line (again using oil marker) use Plumb and oil marker to
mark another line inward accomplish this step.
deducting the thickness of the
required Finish. This line shall be
your “CHB Wall Line”.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


3.0 Methodology (CHB LAYING)

F. Using the given


E. Transfer the CHB Wall
reference of Line and
Line to the soffit (ceiling)
Grade (1.0m FFL
for reference on
elevation offset), make .
installation of vertical
sure to transfer the 1m
strings as guide to laying
elevation reference to
CHB.
both end of the wall to
be laid with CHB

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


3.0 Methodology (CHB LAYING)

H. If without zocalo, mark a


G. Identify in wall setting line from the top of the slab
lay-out plans requirement (Bottom of the wall) up to
230mm, this will be your
for zocalo. Using the
“Top of First Layer” CHB.
height given in plans for Note:
zocalo, mark the location Given the height of one CHB is
average 200mm, we add a 30mm
of the elevation of “Top of mortar height at the bottom which is
Zocalo” with respect to thick enough to compensate the
the 1.0m elevation imperfection in the levelness of the
floor. Adjust as needed depending
marker. on the quality of slab concreting.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


3.0 Methodology (CHB LAYING)

I. Measure the acquired “Top of J. From this “Top of First Layer”


First Layer” CHB elevation from CHB mark or “Top of Zocalo”
the 1m elevation marker then put mark, measure 210mm upwards
this mark of the same elevation to till you reach the ceiling/soffit for
the other end of the wall. Install the both ends of the wall. These
guide string to both ends of the marked elevations will be the top
wall and verify if the 30mm elevation of each CHB to be laid
allowance for the imperfection of vertically. The mark will be used
slab is sufficient. Adjust mortar to place the guide string on each
thickness as necessary and layer.
repeat step (i).
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
3.0 Methodology (CHB LAYING)

J. From this “Top of First Layer”


CHB mark or “Top of Zocalo”
mark, measure 210mm upwards K. After the last full CHB was mark,
till you reach the ceiling/soffit for the remaining gap until you
the both ends of the wall. These reach the ceiling is the seruho
marked elevations will be the top depth.
elevation of each CHB to be laid
vertically. The mark will be used
to place the guide string on each
layer.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


REINFORCEMENT BAR INSTALLATION

1. Vertical Reinforcement dowels may be installed during concreting of floor slab or by post drilling
and fixing with structural epoxy.

Note:
 In post drilling, make sure to avoid hitting embedded elements (conduits, box, etc.), look for
markers placed on slabs.
2. Consult plans for schedule and spacing of reinforcements.

• Vertical- Stated in spacing (i.e. ““Provide Vertical Reinforcement 10mm dia. @400mm spacing)
• Horizontal – stated in spacing or number of Layers of CHB (i.e. “Provide Horizontal Reinforcement
of 10mm dia. @ every three (3) layers of CHB.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


REINFORCEMENT BAR INSTALLATION

3. Be aware of additional Ø16 reinforcement called for in plans for corners,


junctions, openings, jamb location, etc.

4. Complete rebar installation on identified location of Stiffener columns for walls


exceeding the length as specified in General Notes. Install prior CHB laying for ease
in installation and this will also serve as termination marker to the masons when
laying CHB.

5. Check plans and General notes for schedule of reinforcements of Lintel beam
requirements on top of openings and wall exceeding the height as specified in
General Notes.
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
REINFORCEMENT BAR INSTALLATION

6. For
high walls stiffener beams shall be provided @ 3000mm O.C. and for long walls stiffener
columns acting as columns shall be provided @ 4000mm O.C.

7. Drill dowels for horizontal reinforcement after identifying the lay-out of your CHB
stacks/layers. Install and fix with structural epoxy.

8. Drill dowels on slab soffits or beam soffits to match location of vertical reinforcements.
Please take notes of embedded elements and refer to provided markings to prevent
damage. Install and fix with structural epoxy or refer to plans if seismic isolator is required.

9.For vertical reinforcements, it is advisable to limit the length of splice to 1.50m for ease of
installation of CHB as reinforcements are needed to be inserted inside the cells of CHB.
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
3.0 Methodology (Plastering)

2.Using the given reference line and


grade (0.50 offset marking on the
floor for CHB Wall line), determine the
required thickness of cement plaster
1.Identify the area to be
as reflected on the wall setting out/
plastered based on the
lay out of plans and specification
approved IFC plans.
(20mm plaster thickness). Mark
another line inward deducting the
depth/thickness of the required finish.
This line will be the “Finished Wall line”.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


Methodology (Plastering)

3. The distance 4.From the established “Finished wall line”, transfer


from the finished the thickness of plaster (20mm thk) to the wall by
wall line to the setting plumb bob at 100mm, offset from the finish
CHB Wall line, is wall line. From the plumb bob line, measure 100mm
the depth/ toward the wall and install concrete buttons or nylon
thickness of string attached from concrete nailer (from upper
cement plaster to right to the lower left and vice versa of the CHB wall)
be applied on that will be used later on as plastering guide.
wall. .

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


Methodology (Plastering)

5.Mark termination of 6. For areas that requires


plastering for areas with waterproofing, coordinate
ceiling height. Add with the waterproofing
100mm from the required contractor for the height
ceiling height if plaster of reglet and mark it on
height is not provided in wall using 1-meter offset
the drawing. from finish floor elevation.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


Methodology (Plastering)

7. Install nylon string plaster


guides depending on the length
and height of walls to be
8.When installation of plaster
plastered with offset of 20mm
(serves as the thickness of the guide is complete, double
plaster) from the CHB wall. This check required depth or
plastering guide will serve as thickness of plastering versus
reference to achieve actual installed guide nylon
acceptable tolerance for strings prior to commencing
plumbness, squareness, with the first coat.
levelness and opening
requirement of wall.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


Methodology (Plastering)

11. BUTONES"
10. Extend 100 to before start of
9.Proceed with the 150 to 200mm plastering must be
application of high of plastering first inspected /
scratch coat. above ceiling approved by MDC
finish operations/Bureau
Veritas

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


Methodology (Plastering)

12. Before start of


13. Take note NOT to
plastering, make sure all
exceed the maximum
MEPF are embedded
required thickness for
already to avoid back
plastering
job /chipping works that
causes Kapak on walls

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


5.0 Quality Assurance and Control

Ensure that all materials and masonry


accessories to be used are approved
from consultant prior to execution of
work.
Masonry delivered to the site shall be
carefully unloaded and handled to
prevent chipping and breakage.
All works shall be carried out following
to the related method statement and
approved by consultant.
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
5.0 Quality Assurance and Control

All manpower that carrying out the works


shall be adequately trained and
equipped with the required ppe against
the work hazards.
 Required maintenance shall be done
frequently to the works related
equipment.
All the formworks, reinforcement and
embedded items shall be inspected and
approved by consultant.
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
6.0 Safety Requirement

 Safety requirements for chb laying and


plastering works shall be in accordance with
Occupational Health and Safety standards.
 All workers involved in the project shall be
inducted on the safety, health and
environmental issues before allowing
working at site.
 Use double scaffolding always and ensures
the scaffolding is adequately braced with
permanent structure, for working in heights.
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
6.0 Safety Requirement

Personal Protective Equipment (PPE)


 All required mandatory PPE like safety
helmet, safety shoes and hand gloves shall
be used during execution of work.
 Personnel working at height, shall wear full
body harness.

PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY


End of presentation

Thank You !