1.0 INTRODUCTION
1.1 Purpose
1.2 Construction Program
1.3 Company Background
2.0 SCOPE OF WORKS
2.1 Laying of CHB
2.2 Plastering
3.0 WORK METHODOLOGY
3.1 CHB Installation
3.2 Plastering Works
4.0 QUALITY CONTROL
5.0 SAFETY REQUIREMENT
6.0 APPENDICES
CONSTRUCTION PROGRAM
The construction programmed for the
PURPOSE aforementioned work will be carries out in
The purpose of this procedure is to establish accordance with the approved
guidelines on how Pre Activity Training and methodology and existing guidelines set by
Orientation on Quality & Safety are the main contractor. The main objective of
conducted before the start of work activity the contractors is to deliver a quality tile
in support of the managements. installation in accordance with the plans
and specification. This is to be done by
maintaining good workmanship and
satisfactory within the specified period of
construction.
2.2 PLASTERING
The scope of work consists
of surface preparation,
establishibg of plaster
thickness, plaster mix
preparation and
application, finishing and
curing works.
1. Vertical Reinforcement dowels may be installed during concreting of floor slab or by post drilling
and fixing with structural epoxy.
Note:
In post drilling, make sure to avoid hitting embedded elements (conduits, box, etc.), look for
markers placed on slabs.
2. Consult plans for schedule and spacing of reinforcements.
• Vertical- Stated in spacing (i.e. ““Provide Vertical Reinforcement 10mm dia. @400mm spacing)
• Horizontal – stated in spacing or number of Layers of CHB (i.e. “Provide Horizontal Reinforcement
of 10mm dia. @ every three (3) layers of CHB.
5. Check plans and General notes for schedule of reinforcements of Lintel beam
requirements on top of openings and wall exceeding the height as specified in
General Notes.
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
REINFORCEMENT BAR INSTALLATION
6. For
high walls stiffener beams shall be provided @ 3000mm O.C. and for long walls stiffener
columns acting as columns shall be provided @ 4000mm O.C.
7. Drill dowels for horizontal reinforcement after identifying the lay-out of your CHB
stacks/layers. Install and fix with structural epoxy.
8. Drill dowels on slab soffits or beam soffits to match location of vertical reinforcements.
Please take notes of embedded elements and refer to provided markings to prevent
damage. Install and fix with structural epoxy or refer to plans if seismic isolator is required.
9.For vertical reinforcements, it is advisable to limit the length of splice to 1.50m for ease of
installation of CHB as reinforcements are needed to be inserted inside the cells of CHB.
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
PRE ACTIVITY TRAINING AND ORIENTATION ON QUALITY SAFETY
3.0 Methodology (Plastering)
11. BUTONES"
10. Extend 100 to before start of
9.Proceed with the 150 to 200mm plastering must be
application of high of plastering first inspected /
scratch coat. above ceiling approved by MDC
finish operations/Bureau
Veritas