Академический Документы
Профессиональный Документы
Культура Документы
TESTING ELECTRICAL
EQUIPMENT LIGHTING
And
INSTALLATION FIXTURE
COMISSIONING
WORK INSTALLATION
4
SLAB
CONCRETE WALL
5
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
PROCEDURE FOR ELECTRICAL WORKS
Figure 1.1
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
Figure 1.2
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
1.3 Conduct actual measurement per scaled ..
…..drawing for the correct location of the
……boxes.
Figure 1.3
Figure 1.4
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
1.5 Nail the painted junction / square box by
using 3" long common nail.
Figure 1.5
1.6 Ensure that the boxes are properly fixed,
complete with fittings, connector, adapter,
locknut and bushing for EMT or PVC pipes.
Have the head of the nail half-cut for easy
removal after concrete pouring. Fill the box
with used paper or old newspaper to avoid
penetration of concrete inside the box during
concrete pouring.
Figure 1.6
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
1.7 Upon completion of rebar, lay-out the
conduit. Fix the conduit EMT or PVC to the boxes
and fittings. Follow lay-outing as indicated in the
plan.
Figure 1.7
Figure 1.8
Figure 1.9
Figure L
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
FIGURE 6.2.1
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
6.2.2 If there are any, select the correct type of
boxes for its application and install according
to the mounting heights. Check plumbness and
levelness when installing the box.
Figure 6.2.2
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
6.2.3 Ensure that the boxes are fixed in contact
with forms when placed. There must be no
space between the box and the forms.
Otherwise the box becomes too deep. Lay-out
the conduit; ensure it will extend up to the top
of the columns forms. Fix the fittings.
Figure 6.2.3
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY
6.3 Conduit and Boxes in walls and
partitions.
6.3.1 CHB Walls
When installing box on CHB walls, verify the
mounting heights, distances and the type of box to be
installed. Chip the CHB wall for the correct location of
the box and for lay-outing of the conduit. Check the
boxes plumbness and levelness. Have the proper
coordination for the plastering thickness.
Figure 6.3.1
PRE-ACTIVITY TRAINING ORIENTATION ON QUALITY