3. Comparing Actual
with Planned
The Project S-Curve
Cumulative Cost
($ in thousands)
60
Cumulative
20 Budgeted Cost
Cumulative
Actual Cost
5 10 15 20 25 30 35 40 45 50
Elapsed Time (in weeks)
Project S-curve
Advantages Disadvantages
• Simplicity • Do not allow to make
• Provide realing tracking reasonable interpretation
info of budget of the cause of variance
expenditure
• Info visualized and
updated continously
Milestone Analysis
Milestones are events or stages of the project
that represent a significant accomplishment.
Milestones
…show completion of important steps
…can motivate the team
…offer reevaluation points
…help coordinate schedules with vendors and suppliers
…identify key review gates
…signal the team and suppliers
…delineate work packages
Tracking Gantt Chart
Benefits Drawbacks
• easy to understand • Do not indentify the
• Update quickly underlying source of
• Provide realtime project problem in case of task
slippage
control
• Do not allow for future
projection of the project’s
status
Earned Value Management
Cost
Project
S-Curves
Cost
Performance Schedule
Earned Cost
Value
Performance Schedule
Performance Schedule
Tracking Control Charts
Earned Value Terms
Planned value (PV): cost estimate of budgeted resource across project
life
Earned value (EV): real budgeted cost/”value” of work that has been
performed to date
Actual cost of work performed (AC): cumulative total cost incurred
Cost variance= EV-AC
Schedule variance= EV-PV
Schedule performance index (SPI)= EV/PV
Cost performance index (CPI)= EV/AC
Budgeted cost at completion (BAC): total budget for a project
Steps in Earned Value Management
Cost Overspend
PV EV
Budget
Slip
Schedule Performed
Schedule
6.4. Các phương pháp quản trị chi phí dự án
Earned Value Milestones
Bảng 6.5: Các chỉ số quản lý giá trị thu được EVM
Cost Variances
Actual Cost of Work Performed (AC) = 40 = 8+11+8+13
Cost Performance Index = .75 = 30/40 = EV/AC
Estimated Cost to Completion = 50.7 = (1/.75)x38
Completion Values in EVM
Accurate and up-to-date information is critical
in the use of EVM
0/100 Rule (short duration)
Level of detail
Process evaluation