Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 1
Pre & Co-Processing Cost Split - Background
Report from Robert Szabot
Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 2
Objective
• To define Production cost of different AF product as well as AR
• To have more clear on economical judgment of production cost
• To support the implementation of standard cost reporting tools
Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 3
Flow process and Cost Centre Segregation (AF)
Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 5
Define Production Cost
• Total production cost of GZ1 = GZ 1 cost centre (Coarse shredder IO
allocation + Fine Shredder IO allocation)
• Total production cost of Coarse Product = Coarse Shredder IO allocation x
(volume of coarse/volume total GZ1)
• Total production cost of Fine product (SLC Fuel) = (Fine shredder IO
allocation + (Coarse shredder IO x (volume of fine/volume total GZ1))
• Total production cost of ILC fuel = production cost of Coarse Product +
Impregnation Cost of GZ2
Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 6
Flow process and Cost Centre Segregation (AR)
© 2013 Holcim
C4004 Cost Separation – Background
• At the moment Geocycle only have one cost centre admin
(C4004)
• Cost from all line function under Geocycle (Technical and
Operational, Sales and Marketing, Compliance and Field
Services Team) are mixed together in C4004
• Responsibility to manage cost in each function is not really
clear
• Income statement analysis also required separation cost of
each line function
Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 8
C4004 cost separation – follow Income Statement
Technical
and
Operational
Sales and
Marketing
Admin cost
Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 9
C4004 Cost Separation
• Split into 3 main cost centre
- Technical & Operational (include Field Services Team)
- Sales and Marketing (include Communication team)
- Admin (include Compliance team and Country Manager)
Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 10
End of Slides
Geocycle - Proposed Org Structure, Organization Review by ODD, 2013-12-16 © 2013 Holcim 11