Вы находитесь на странице: 1из 77

Construction Project Scheduling

and Control

Chapter 1
Introduction to Project
Management
Important definitions from the Project
Management Institute, PMI, PMBOK, 4th
edition, 2008:
Project: A temporary endeavor undertaken to
create a unique product, service, or result
 There are no two projects that are the same
 Every project has
 A start a finish points, and
 A deliverable.
Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 2
Introduction to Project
Management (Cont’d)
Program: A group of related projects managed in
coordinated way to obtain benefits and control not
available from managing them individually. Programs
may include elements of related work outside of the
scope of the discrete projects in the program
Programs may be:
 Temporary/one-time programs
 Ongoing (usually periodic/annual)
A program can be a large and complex project

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 3
Introduction to Project
Management (Cont’d)
Portfolio is a collection of projects or programs
and other work that are grouped together to
facilitate effective management of that work to
meet strategic business objectives. The
projects or programs of the portfolio may not
necessarily be dependent or directly related
Caution: US versus UK terminology

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 4
The Hierarchy

Portfolio Program

Program Project Project Project Project Tasks

Subproject Subproject Subproject

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 5
Project Management

Project Management
is the application of
knowledge, skills,
Cost / Time /
tools, and techniques Schedule
Budget
to project activities
to meet the project
requirements
Scope /
Quality

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 6
Scheduling as Part of Project
Management
Project management in construction includes:
 Scheduling / Time Management,
Project control
 Budget / Cost Management,
 Document Management Project administration,
 Risk Management Quality management,
 Procurement management, Safety management,
 Change / Scope management, Other

They are all interrelated

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 7
Planning and Scheduling

Planning and scheduling are two terms that


are often thought of as synonymous
 They are not!
 Scheduling is just one part of the planning effort
Project scheduling is the determination of the
timing and sequence of operations in the
project and their assembly to give the overall
completion time
Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 8
Project Planning
Project planning serves as a foundation for several
related functions such as cost estimating, scheduling,
and project control
The plan can include elements that has to do with
1.scope, 2. design and alternate designs, 3. cost,
4. time, 5. finance, 6. land, 7. procurement, 8.
operations, etc.

 The level of details needed

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 9
Planning and Scheduling

Planning is the process of determining how a


project will be undertaken. It answers the
questions:
 What?  Why
 How?  Where?
 Who?  By whom?
 How much?  When? (in general terms)

Scheduling deals with “when” on a detailed level

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 10
Planning and Scheduling

Schedule
when

The Plan

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 11
Question

Do all projects (of all types and sizes) have a


need for CPM scheduling?
Does the need vary?

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 12
Can the Following be Considered
Projects?
1. I like to improve my education
I plan to obtain my MBA from an accredited school by
end of 2019
2. I want to save a good amount of my salary
I will save (at least) $400/month so I can have $5,000
in 2 years
3. We like to reduce the overhead of our company
We like to reduce the OH from 22% to 18% by end of
2012
Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 13
Chapter 2: Steps for Scheduling a
Construction Project
The basic four steps
Myths about scheduling

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 14
Steps to Schedule a Project

1. Break down the project into activities:


 Reasonable activity size
 Contract restrictions?

 Simple versus complex activities


 WBS, coding, activity description
 Activity types: Task, milestone (start or finish),
Hammock (level of effort)

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 15
Factors to Be Considered in
Defining Activities
1. Nature of the work / Homogeneity
2. Location / Floor / Segment
3. Size / Duration
4. Timing / Chronology
5. Level of confidence in the duration
6. Responsibility
7. Phase

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 16
Definition

Activity: A basic unit of work as part of the


total project that is easily measured and
controlled
 It is also called Task
 It is time and resource consuming
 Unit of measure: simple or complex:
 Formwork + rebar + concrete + finish (4 activities), or
 FRP Concrete (one activity)

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 17
Events and Milestones

An event: a point in time that is usually the start or


finish of a certain activity(s)
 Duration = 0
Important events are called milestones
 start milestones such as NTP and
 finish milestones such as Substantial Completion
An activity has a start date and a finish date. An event
(or milestone) has a start date or a finish date

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 18
.

Level 5
Level 4
Level 2
Level 1

Level 3
Level 0

Foundation/
Substructure
110000

Columns
Soffit and Falsework Post-
121000

edges tensioned

123111
123110
Slabs
123100

Building
Shear shell
120000

Walls
122000

Scaffold Rebar
(tables)

123112
123120 Flat Slabs
.

123200

Elevated
Slabs Exterior
123000

Shores closure
Post-tension
130000

cable

123113
Tampa
123130

Waffle Office
100000

Slabs Beams/ Bldg


123300

Girders
124000

Reshores
Interior
123114

Concrete finishes

Constr. Project Sched. & Control - Dr. Mubarak - Part 1


140000

123140

One-way CIP Stairs


Slab and
123400
125000

beam
Mechanical
/ Electrical
150000

Site Work
160000

Example

Slide No. 19
Structure, WBS,
Work Breakdown
The CSI Masterformat in WBS
Format
Title Level
03 00 00 Concrete 1
03 10 00 Concrete Forming and Accessories 2
03 11 00 Concrete Forming 3
03 11 13 Structural Cast-in-Place Concrete Forming 4
03 11 13.13 Concrete Slip Forming 5
03 11 13.16 Concrete Shoring 5
03 11 13.19 Falsework 5
03 11 16 Architectural Cast-in Place Concrete Forming 4
03 11 16.13 Concrete Form Liners 5
03 11 19 Insulating Concrete Forming 4
03 11 23 Permanent Stair Forming 4

• Don’t forget level 0!

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 20
Steps to Schedule a Project

2. Estimate activity durations:


 Time unit: hour, day, week, month?
 Duration = Total Quantity/Productivity
 = 10,000 M3 / 800 M3/day
 = 12.5 days ≈ 13 days
 Multiple crews – multiple shifts
 Productivity adjustment factors
 Warning: don’t accept unrealistic expectations!
 Define calendars
Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 21
Steps to Schedule a Project

3. Set up the schedule logic:


 Establish logic relationships
 Sometimes there is more than one way to depict logic
 Tendency to overuse Finish-to-Start (FS) relationship

 Lags & leads


 External relationships
 Logic (hard) versus resource (soft) logic
 Imposed constraints

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 22
Steps to Schedule a Project

4. Draw network & perform CPM Calculations


(or input in the computer and execute):
 Imposed finish date?
 Non-work days
 Check software default rules / settings
 Make sure any specific requirement is met

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 23
Myths/Misconceptions
About Scheduling
I should get a very accurate schedule… I bought the
most expensive software in the market!
I hired a computer specialist to handle Primavera!
CPM schedules are bunch of nonsense. We do it just
because the owner required it.
We don’t need an expensive system
…it is all up here

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 24
Chapter III: Bar (Gantt) Charts

Defined as a graphic representation of project


activities shown in a time-scaled bar lines with
no links shown between activities
Developed in 1917 by Henry Gantt
Also known as Gantt charts

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 25
Bar (Gantt) Charts: Examples

Site Clearing
Excavation
Foundation
S.O.G.
Framing
Roofing
Finish Interior
2 4 '6 8 10 12 14 16 18 Time (days)

Excavate

Form Footings

Place Rebar

Place Concrete

Strip Forms
2 4 6 8 10 12 14 16 18 Days

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 26
Bar (Gantt) Charts

Example 3:

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 27
Bar (Gantt) Charts: Advantages

Time-scaled
Simple to prepare
Simple to read and interpret
Can be more effective and efficient if CPM based
 Still the most popular method
Bars can be dashed to indicate work stoppage
Can be loaded with other information (budget, man-
hours, resources, etc.)

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 28
Bar Charts: Disadvantages

Does not show logic


 Some computer programs can show links but it
may look so complicated and confusing
Not practical for projects with too many
activities
 As a remedy, we can use bar charts to show:
1. A small group of the activities (subnet)
2. Summary schedules

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 29
More About Bar Charts

Bar charts can be loaded with many types of


information such as:
 “As built” compared to “as planned” (target) bars
 Early versus late dates, with or w/out float
 S-curves cumulative and incremental budget, man-
hours, or percent complete
However, too much data-loading for Bar charts
will defeat its purpose of being simple

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 30
Examples for Loaded Bar Charts
Manhours

. Foundation 7,000

First Floor 6,000

Second Floor 5,000

Third Floor 4,000

Fourth Floor 3,000

Roof 2,000

Site 1,000

2 4 6 8 10 12 14 16 18 20 22 24 26 28 Days

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 31
Examples for Loaded Bar Charts
Data Date
Percent
Remove Old Roof As Planned Complete
As Built 100%
Replace rotten rafters 90%
80%
Install Sheathing 70%
60%
Install Felt 50%
40%
Install Shingles 30%
20%
Clean Up 10%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Days

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 32
Quiz 3
Are the following statements True or False:
1. The bar representing a 4-day activity is twice as long as a
bar representing a 2-day activity in a bar chart
2. Bar chart method lost its applicability with the introduction of
the Critical Path Method
3. A bar representing an activity in a bar chart may not be
continuous
4. Bar charts and Gantt charts are two different methods
5. Bar charts can be loaded with information other than the
timeline of the project

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 33
Part IV Logic Networks – The
Critical Path Method
Arrow and Node Networks: definitions,
examples, comments, comparisons
Time-Scaled Logic Diagrams
The Critical Path Method (CPM): Calculations,
examples, definitions, comments, lags,
imposed finish date, calendars

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 34
Networks: A Definition
Network: A graphical representation of the
activities (and events) comprising the project,
in a logical and chronological depiction
Network diagrams are basically two types:
 1. arrow networks and
 node networks:
 2. Basic node networks
 3. Precedence networks

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 35
Arrow Networks

Arrow network: A network on which activities


are represented by arrows between nodes
(events) A
10 20
Also called: 5
 I-J Method (10-20 for activity A above),
 Activity on Arrow (AOA) Network,
 Arrow Diagramming Method (ADM)

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 36
Arrow Networks

Network schedules were first developed by E. I.


Dupont de Nemours Company in conjunction with the
UNIVAC Applications Research Center of Remington
Rand between 1956 and 1958
At the beginning, Arrow Networks were the only way
to do CPM schedules
Since mid 1980s, Arrow Networks have become
obsolete. They were replaced by Node and Precedence
Networks

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 37
Arrow Networks:
Simple Example

Activity IPA*
A -
B A
C A
D B
E C, D

* IPA: Immediately Preceding Activities (or immediately followed by)

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 38
Example Solution
.

B 30 D
A E
10 20 40 50

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 39
Example 2 for Arrow Network
. Activity IPA
A -
B -
C -
D A
E A,B
F A,B,C
G E,F
H D,G
I D,G
Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 40
Solution
.

A D
20
H 70
d1 d3
10
B 30
E G
50 60 80

d2 I
C F
40

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 41
Comments on Arrow Networks

An arrow represents an activity


A node represents an event of starting and/or finishing
an activity or activities
Arrow networks can only accommodate finish-start
relationships
Dummy activities are required in Arrow Networks for
logic or identity

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 42
Comments on Arrow Networks

“Waiting” periods have to be incorporated in the


network as real activities with durations but zero
resources
Even though a network is not time-scaled, arrows go
from left to right since the “X-axis” is supposed to -
loosely- represent time
Once the number of activities increase, it gets difficult
and complicated

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 43
Node Networks

A node network is a network where nodes


represent activities and arrows represent logic
relationships (dependencies)
Also called activity on node (AON)
Precedence diagrams (or networks) are an
advanced form for node networks

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 44
Example 1 Using Node Networks
.

Activity IPA B D

A -
A E
B A
C A
C
D B
E C, D

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 45
Example 2 for Node Network
. Activity IPA
A -
B -
C -
D A
E A,B
F A,B,C
G E,F
H D,G
I D,G
Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 46
Solution of Example 2
.

A D H

PS B E G I
PF

C F

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 47
Tips for Proper Node Network
Drawing - 1
Improper Proper

A A
5 5

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 48
Tips for Proper Node Network
Drawing - 2
Improper Proper

A A
5 5

B B
3 3

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 49
Tips for Proper Node Network
Drawing - 3
Improper Proper

A A
5 5

B
B
3
3

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 50
Tips for Proper Node Network
Drawing - 4
Improper Proper
A
A 5
5
B
3
or
A
B
5
3

B
3

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 51
Tips for Proper Node Network
Drawing - 5
Improper Proper

A C A C
5 4 5 4

B D B D
3 7 3 7

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 52
Tips for Proper Node Network
Drawing - 6
Starting a network diagram
Improper Proper

A A
5 5

B B
PS
3 3

C C
4 4

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 53
Tips for Proper Node Network
Drawing - 7
Ending a network diagram
Improper Proper

X
X
5
5

Y Y
3 3 PF

Z Z
4 4

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 54
Quiz 4

True or False:
1. A node in an arrow diagram represents an event
2. An arrow in an arrow diagram represents an event
3. A node in a node diagram represents an event
4. An arrow in a node diagram represents a logic relationship
5. A milestone is a term used by scheduling software to indicate
an important event
6. One of the major advantages of networks over bar charts is
ability to depict logic

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 55
The Critical Path Method

The Critical Path Method (CPM): A scheduling


technique using networks for graphic display
of the work plan
 Network calculations determine when activities can
be performed, the expected completion date of the
project, and the critical path of the project

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 56
CPM Calculations: Example

Activity Duration IPA


(days)
A 5 -
B 8 A
C 6 A
D 9 B
E 6 B,C
F 3 C
G 1 D,E,F

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 57
CPM Calculations:
Example 1 Graphic Solution
.

5, 13 13, 22

B D
8 9

0, 5 5, 13 3 13, 19 13, 22 22, 23


A E G
5 6 1

0, 5 16, 22 22, 23

5 5, 11 8 11, 14
C F
6 3

10, 16 19, 22

All dates above represent the end of the day

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 58
CPM Calculations:
Example 1 Tabular Solution
Activity Duration ES EF LS LF TF

A 5 0 5 0 5 0

B 8 5 13 5 13 0

C 6 5 11 10 16 5

D 9 13 22 13 22 0

E 6 13 19 16 22 3

F 3 11 14 19 22 8

G 1 22 23 22 23 0

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 59
The Critical Path: Definition

The Critical Path: The longest continuous path


in a network from start to finish
 The critical path represents the summation of the
durations of activities along that path, including
lags and taking constraints in consideration
 The critical path establishes the minimum overall
project duration

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 60
The Critical Path
The definition “the path with zero float” is inaccurate. It
would be correct if we say “the path with least float”
For every network, there must be at least one critical path
but there might be more than one critical path
Multiple paths may share one or more activities
Activities on the critical path, by definition, have no float
(unless in some cases of imposed finished date, critical
activities then are those with least float)
A critical activity: An activity on the critical path. It
is an activity that is if delayed, the entire project
will get delayed

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 61
CPM Definitions

Forward pass: The process of going from the start to


finish of a network in order to calculate early start and
early finish dates for each activity, and the expected
finish date for the entire project
Backward pass: The process of going from the finish
to start of a network in order to calculate late start
and late finish dates for each activity.
Both passes identify the critical path and float times
for activities

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 62
CPM Definitions

Predecessor Activity: An activity that has to finish (or


start) in order for the succeeding activity(s) to start
(or finish). It has been also defined as an activity that
has some measurable portion of its duration logically
restraining a subsequent activity or activities
Successor Activity: An activity that cannot start (or
finish) until another activity (predecessor) has finished
(or started)

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 63
CPM Definitions

Early Start, ES: The earliest date the activity can start
within project constraints
Early Finish, EF: The earliest date the activity can
finish within project constraints
Late Start, LS: The latest date the activity can start
without delaying the completion of the project
Late Finish, LF: The latest date the activity can finish
without delaying the completion of the project

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 64
CPM Definitions

Total Float, TF: The maximum amount of time an


activity can be delayed from its early start (ES)
without delaying the entire project
 TF = LS – ES
= LF – EF
= LF – ES - Duration
Float is one of the most important, interesting, and
controversial issues in construction; not only from
technical point of view, but from legal point of view as
well

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 65
CPM Definitions

Total float is broken down into free float ,


independent float, and interfering float

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 66
CPM Calculations: Example 2

Activity Duration IPA


A 5 -
B 7 A
C 4 A
D 5 B
E 6 B,C
F 3 C
G 8 D,E
H 5 E
I 4 E,F
J 1 G,H,I
Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 67
CPM Calculations:
Example 2 Graphic Solution
1
12, 17 18, 26
D G
5, 12 5 8
B
7 13, 18 18, 26
26, 27
5, 12 3 J
0, 5 12, 18 18, 23
1
A E H
5 6 5 26, 27
4
0, 5 12, 18 21, 26 18, 22
3 I
5, 9 4
10
C 9, 12
4 F 22, 26
3
8, 12
19, 22

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 68
Free Float

Free Float, FF: The maximum amount of time


an activity can be delayed without delaying
the ES of the succeeding activity(s)
 FFi = min(ESi+1) – EFi 8, 15

 FF ≤ TF 2,8
E
7
B 10,17
6
4,10
12, 17
F
5

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 69
Free Float Calculation in Our
Example: Activities C, F, I
.

12, 18 18, 23 26, 27


E H J
6 5 1

12, 18 21, 26 18, 22 26, 27


I
5, 9 4
C 9, 12
4 F 22, 26
3
8, 12
19, 22

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 70
CPM Calculations:
Example 2 Tabular Solution

Activity ES EF LS LF TF FF
A 0 5 0 5 0 0
B 5 12 5 12 0 0
C 5 9 8 12 3 0
D 12 17 13 18 1 1
E 12 18 12 18 0 0
F 9 12 19 22 10 6
G 18 26 18 26 0 0
H 18 23 21 26 3 3
I 18 22 22 26 4 4
J 26 27 26 27 0 0

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 71
CPM Calculations: Example 3
.
Activity Duration IPA
A 5 -
B 6 A
C 5 A
D 3 A
E 3 B
F 4 B, C
G 4 D
H 7 B,C,G
I 8 E, F
J 2 F
K 3 H, J
L 2 I, J

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 72
CPM Calculations: Exercise
.

B E I
6 3 8

L
2
A C F J
5 5 4 2 PF

D G H K
3 4 7 3

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 73
CPM Calculations: Exercise
Graphic Solution
.
5, 11 1 11, 14 15, 23
B E I
6 3 8
23, 25
5, 11 12, 15 15, 23
L
1 5, 10 5 15, 17 2
0, 5 11, 15 25
23, 25
A C F J
5 5 4 2 PF
0, 5 6, 11 11, 15 20, 22
25

3 5, 8 3 8, 12 3 3
12, 19 19, 22
D G H K
3 4 7 3
8, 11 11, 15 15, 22 22, 25

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 74
CPM Calculations: Exercise
Tabular Solution
.

Activity ES EF LS LF TF FF
A 0 5 0 5 0 0
B 5 11 5 11 0 0
C 5 10 6 11 1 1
D 5 8 8 11 3 0
E 11 14 12 15 1 1
F 11 15 11 15 0 0
G 8 12 11 15 3 0
H 12 19 15 22 3 0
I 15 23 15 23 0 0
J 15 17 20 22 5 2
K 19 22 22 25 3 3
L 23 25 23 25 0 0

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 75
End-of-Day Convention

The dates on the activities represent the “end of day”.


That’s why we always start with day 0: end of day 0 =
start of day 1

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 76
Quiz 5

True or False:
1. You can find out the project’s estimated completion date
after performing the forward pass only
2. You can find out the project’s critical path after performing
the forward pass only
3. “Event” is another name for an activity
4. “Task” is another name for an activity
5. There could be more than one critical path in a CPM network
6. Total float must be equal to or greater than free float

Constr. Project Sched. & Control - Dr. Mubarak - Part 1 Slide No. 77

Вам также может понравиться