Академический Документы
Профессиональный Документы
Культура Документы
Project Phases
1. Project Identification
2. Project Formulation Study
a) A Preliminary Project Formulation Study- Prefeasibility Study
b) Feasibility Study or Detailed Project Report
3. Project Appraisal
4. Negotiations & Project Approval
5. EIA and clearance procedures
6. Tendering
1. Preparation of Tender Documents
2. Notice Inviting Tender (NIT)
3. Tendering
4. Tender opening, scrutiny, evaluation, negotiation, letter of award.
7. Pre-construction Planning
8. Project Implementation
9. Project Monitoring & Control
10. Commissioning & Closeout
11. Warranty Period
1.Project Identification
Identification of high priority projects
possible to finance and
whether the Govt. and users are interested.
Viable from technical and financial point of view.
Cost Benefit Ratio: Cost of the project less than the expected
benefits.
Aspects to be examined;
Functional Aspects: Operational and civil structural plans
Location & Site: Climate, topography, Infrastructure, land,
Labor etc.,
Construction Aspects: Design and technical requirement
Operational Aspects: Project Management, O&M,
Expenditure & Revenue generation, Occupational Safety &
Health
2.Project Formulation Study
After Project Identification: Whether the project should be
executed or not ?
Taken up in two stages: Prefeasibility & Feasibility Study
2. a Prefeasibility Study
Preliminary information related to project are collected
and
analyzed and
decision is taken whether to go for feasibility study or not.
It consists of Demand estimates on
satisfying overall national and regional demand,
alternative locations,
preliminary technical (Whether can be taken up)and
economic feasibility (Block Cost Estimates),
benefits and implementation
2a. Pre-Feasibility Studies
(Nainital Sewerage Plan: ADB
Funded)
Augmentation of old sewer
network = 5 km sewer length: 250
lacs.
GIS based mapping of the existing
sewerage system: 100 lacs
Sewer cleaning equipments.: 100
lacs
Slope stabilization of outfall sewer
with advanced nailing and
shortcrete technologies: 200 lacs
(4000 m2 @ Rs 5000/ m2)
Prefeasibility Study-Urban
Transport
Document the routes—
identify potential user groups by income and other
characteristics (e.g.,gender) along the proposed corridor,
assess their mobility needs and problems as Basis for project
design.
For the proposed design, estimate ridership by group and
their access to employment (destination)centers.
Consider options for route and mode type and design to
optimize ridership and access and Minimize disruption.
Document impacts and mitigation measures, both for
transit and NMT or alternate investments.
2 b. Feasibility Study or DPR
If decision has been taken to take up the work- based on
technical and economic feasibility. THEN
Owner hires a consultant to prepare a
FUNCTIONAL/DETAILED design and specifications
These documents become bid documents, along with
CONTRACTS-general & special conditions-
The report consists of : Precise and detailed account of what
is involved in actually setting up the project.
Objective of Feasibility Study is to examine:
Whether the project objectives are realistic
Recommendations are technically sound
Beneficial in terms of financial, economical and social,
environmental point of view
2b. Feasibility Study or
DPR- Contents
Introduction and Govt. policy
Objectives
Alternative locations
Marketing/demand analysis
Site investigation
Detail of structure, type, size and cost
Layout
Estimates
Specifications
O&M cost
Working capital, cash flow requirement
Environmental Management Plan
Resource Availability
3.Project Appraisal
Departmentally by
Employing Daily Labour Through Contractor
on muster roll
Piece Work
Agreemen
t-
Schedule
Lump Sum Labour
Rate
Contract Contract
Contract
Piece Work Agreement
Negotiation-
Lowest offer is higher than justified amount,
time does not permit to recall tender,
if modifications are proposed by the lowest tender in
the scope of work.
Though total cost is reasonable but certain items are
reasonably high or low by Etc.,
letter of award
Contractor warrants facility for one year and will fix and
defects during that time.
Post-occupancy evaluation may be performed by owner
to assess satisfaction of occupants.
Project Management
General goal of Construction:
Project on time
Within budget
With states quality standards
Safe Environment
Less than 20 % of projects meets the above requirement
Project management is essentially about managing the project from
an idea to through completion
Hence Project Management best described in terms of their
component processes
Five processes groups – initiating, planning, executing, controlling &
closing
Nine knowledge areas: Project integration management, project scope
management, Project time management, project communication
management, project risk and procurement management)