CHB LAYING
AND
PLASTERING
Presented by:
AILEEN F. RONATAY
JR. QC ENGINEER
BUILDER OF A BETTER FUTURE
OUTLINE
I. OBJECTIVES
II. COMMON TOOLS USED IN INSPECTION
III. CHB LAYING INSPECTION
IV. PLASTERING
V. CODES AND STANDARDS
BUILDER OF A BETTER FUTURE
I. OBJECTIVES
2. LEVEL
3. SQUARE (ISKWALA)
III
CHB LAYING
INSPECTION
BUILDER OF A BETTER FUTURE
INSPECTION REQUIREMENT
• CHB cutting – Avoid excessive breaking of CHB. Use grinder in
cutting CHB to minimize wastage.
• Stiffener column, beams– provide for walls more than 3 meters in
length and 3 meters in height.
• Lintel beams– on top of door and window openings. Provide at
least 200 mm block-out both sides of CHB for beam anchorage.
• Mortar proportion is 1:3 (1 part cement to 3 parts sand)
• For walls aligned to columns and corewalls, adjust CHB layout by
20mm. The 20mm offset is allowance for plastering since
columns are straight-to-finish.
BUILDER OF A BETTER FUTURE
IV
PLASTERING
INSPECTION
BUILDER OF A BETTER FUTURE
PLASTERING CHECKLISTS
• PRE-APPLICATION
VERIFY AFC DRAWINGS / FLOOR PLANS
VERIFY WALL SCHEDULE / WALL TYPE
VERIFY APPROVED METHODOLOGY
VERIFY REQUIRED SURFACE FINISH IF SMOOTH OR ROUGH FINISH FOR
TILED AREAS
VERIFY LOCATION OF OPENINGS / BLOCKOUTS
VERIFY OFFSETS & REFERENCE ELEVATION
BUILDER OF A BETTER FUTURE
PLASTERING CHECKLISTS
• PRE-APPLICATION
CONDUCT TRADE TEST / QUALIFICATION OF FINISHING MASONS TO DO
PLASTERING
PROVIDE MOCK-UP SAMPLE OF PLASTERING INCLUDING VERTICAL AND
HORIZONTAL GROOVE
VERIFY ADEQUACY OF TOOLS AND EQUIPMENT
CHECK STRAIGHT-EDGE (BARA) IS NOT BENT
VERIFY EMBEDDED PIPES ARE TESTED & PASSED
BUILDER OF A BETTER FUTURE
PLASTERING CHECKLISTS
• SURFACE PREPARATION / LAYOUT
CHECK PLASTERING GUIDE / “BUTONES”
CHECK STRING LAYOUT FOR PLUMBNESS, ALIGNMENT, SQUARENESS OF
CORNERS, AND TARGET PLASTERING THICKNESS IF ATTATINED
CHECK CHB SURFACE PREPARATION
CHECK THAT ALL HOLES AND CHB GAPS ARE PROPERLY FILLED WITH
MORTAR
CHECK SMOOTH SURFACES ARE ROUGHEN
CHECK SCRATCH COAT WAS PROVIDED
BUILDER OF A BETTER FUTURE
PLASTERING CHECKLISTS
• SURFACE PREPARATION / LAYOUT
PLASTERING CHECKLISTS
• PLASTERING
PLASTERING CHECKLISTS
• PLASTERING
PLASTERING CHECKLISTS
• CURING
REQUIRE THAT NEWLY PLASTERED WALLS ARE MOIST CURED FOR 7 DAYS
(HOT WEATHER)
ENSURE THAT NEWLY PLASTERED WALLS WERE NOT SUBJECTED TO
EXCESSIVE VIBRATION, GRINDING OR CHIPPING
ENSURE THAT NEWLY PLASTERED WALLS ARE FULLY CURED PRIOR TO
PAINT APPLICATION
BUILDER OF A BETTER FUTURE
MANPOWER
1. SUPERINTENDENT / SUPERVISOR
• Responsible for reviewing drawings, and requesting tools
and materials needed for the plastering works.
• Check and ensure that works done are acceptable prior to
requesting for QC and client inspections.
2. FOREMAN
• Responsible for supervision of skilled mason during
plastering works.
BUILDER OF A BETTER FUTURE
2. FOREMAN
• Must ensure that works are done right the first time and all
the time.
• Conducts 100% visual and dimensional inspection on all
completed formworks.
3. MASON
• Responsible for the plastering and finishing works.
4. QC ENGINEER
• Responsible for ensuring that plastering works are in
compliance with the approved drawings and methodology
thru conduct of inspection.
PLASTERING WORK PROCEDURES
REMINDERS:
ACCEPTANCE CRITERIA
For walls to receive paint
• Surface should be smooth finished, uniform in texture, and no visible
cracks/kapaks due to poor adhesion.
• All corners should be square and all lines are straight.
• Openings are leveled and sufficient inside clear dimensions.
• Finish and measure so gap at any point between surface and a 3m long
straightedge, resting on 2 high spots and placed anywhere on the surface,
does not exceed 3mm
END OF PRESENTATION