Академический Документы
Профессиональный Документы
Культура Документы
Managing Projects
ISV
ISV Operations
Operations Management
Management -- 66thth Edition
Edition
Beni Asllani
Copyright 2009 John Wiley & Sons, Inc. University of Tennessee at
Lecture Outline
Project Planning
Project Scheduling
Project Control
CPM/PERT
Probabilistic Activity Times
Microsoft Project
Project Crashing and Time-
Cost Trade-off
Objective
Scope
Contract requirements
Schedules
Resources
Personnel
Control
Risk and problem analysis
Project team
made up of individuals from various
areas and departments within a company
Matrix organization
a team structure with members from
functional areas, depending on skills
required
Project manager
most important member of project team
Steps Techniques
Define Gantt chart
activities CPM/PERT
Sequence Microsoft
activities Project
Estimate time
Develop
schedule
Build house
Select paint
Select carpet
Finish work
1 3 5 7 9
Month
Copyright 2009 John Wiley & Sons, Inc. 9-14
Project Control
Time management
Cost management
Quality management
Performance management
Earned Value Analysis
a standard procedure for numerically
measuring a project’s progress, forecasting its
completion date and cost and measuring
schedule and budget variation
Communication
Enterprise project management
3
Lay Dummy
foundation
2 0 Build Finish
3 1 house work
1 2 4 6 7
Design house Order and 3 1
and obtain receive 1 1
Select Select
financing materials paint carpet
5
3
Lay foundation Lay
Dummy
foundation
2 0
2 3
1
Order material 2 4
Order material
2 4
Finish work
2 3
7
Star 1 1
t 3
Design 6
house and
3
1 5 1
obtain
financing 1 Select carpet
Order and
receive Select paint
materials
3 6
1 5 1
1
A: 1-2-4-7
3 + 2 + 3 + 1 = 9 months Critical path
B: 1-2-5-6-7 Longest path
3 + 2 + 1 + 1 + 1 = 8 months
through a
C: 1-3-4-7
3 + 1 + 3 + 1 = 8 months network
D: 1-3-5-6-7 Minimum
3 + 1 + 1 + 1 + 1 = 7 months project
Copyright 2009 John Wiley & Sons, Inc. completion 9-21
Activity Start Times
Start at 5
months
2 4
Finish at 9
2 3 months
7 Finis
Start 1 1 h
3
3 6
1 5 1
1 Start at 6
Start at 3 months
months
Earliest finish
1 0 3
3 0 3
Latest finish
1 0 3 7 8 9
3 1
Design
Finish
house and 6 6 7
obtain 3 3 4 work
financing 1
1 5 5 6
Select
Order and receive 1 carpet
materials Select pain
1 0 3 7 8 9
3 0 3 1 8 9
Design
house and 6 6 7 Finish
obtain 3 3 4 work
financing 1 7 8
1 4 5 5 5 6
Select
Order and receive 1 6 7 carpet
materials Select pain
Activity LS ES LF EF Slack S
*1
*1 00 00 33 33 0
*2
*2 33 33 55 55 0
33 44 33 55 44 1
*4
*4 55 55 88 88 0
55 66 55 77 66 1
66 77 66 88 77 1
*7
*7 88 88 99 99 0
* Critical Path
P(time)
a m t b a t m b
Time Time
P(time)
a m=t b
Time
Orientatio
7n
2,2,2
1 6 8 10 8 0.44
2 3 6 9 6 1.00
3 1 3 5 3 0.44
4 2 4 12 5 2.78
5 2 3 4 3 0.11
6 3 4 5 4 0.11
7 2 2 2 2 0.00
8 3 7 11 7 1.78
9 2 4 6 4 0.44
10 1 4 7 4 1.00
11 1 10 13 9 4.00
16 1 0 3
8 9
Start 2 0 6 Finis
7 9 1
6 0 6 h
5 6 9 6
11 16 25
3 6 9 9 9 13
9 16 2
4 12 1
3 0 3 6 3 7 5
6
3 2 5 4 5 9
7 3 5
2 1 1
4 6
Z
= tp x Time
x = 22 = 25 Time
(weeks)
Crashing
reducing project time by expending
additional resources
Crash time
an amount of time an activity is reduced
Crash cost
cost of reducing activity time
Goal
reduce project duration at minimum cost
2 4
1
8 2
7
1 4
1
2
3 6
4 5 4
4
$6,000 –
Crash cost
$5,000 –
Crashed activity
$4,000 –
Slope = crash cost per week
$3,000 –
Normal cost
$1,000 –
–
Crash time Normal time
| | | | | | |
0 2 4 6 8 10 12 14 Weeks
TOTAL
NORMAL CRASH ALLOWABLE CRASH
TIME TIME NORMAL CRASH CRASH TIME COST PER
ACTIVITY (WEEKS) (WEEKS) COST COST (WEEKS) WEEK
$400 3 6
4 5 4
4 $200
$3000
$200
$500 $7000
2 4
8 12 $700
7
1
TO… 7
4
Indirect cost
Cost ($)
Direct cost
Crashing Time
Project duration
Copyright 2009 John Wiley & Sons, Inc. 9-60
Copyright 2009 John Wiley & Sons, Inc.
All rights reserved. Reproduction or translation
of this work beyond that permitted in section 117
of the 1976 United States Copyright Act without
express permission of the copyright owner is
unlawful. Request for further information should
be addressed to the Permission Department,
John Wiley & Sons, Inc. The purchaser may make
back-up copies for his/her own use only and not
for distribution or resale. The Publisher assumes
no responsibility for errors, omissions, or
damages caused by the use of these programs
Copyright 2009 John Wiley & Sons, Inc. 9-61